# Structural

### **6.0 Structural**

The Structural menu in the home page of the ***cuteQM*** app used to add result after performing structural related inspections. This menu also helps you to view structural reports, graphical reports, and other reports.

### **6.1 Radiographic Testing (RT)** 

The RT method is one of the NDT inspection methods used for inspecting the materials in the structural project by using either x-rays or gamma rays. Once the RT inspection request added in the [**<u>NDT Inspection Request</u>**](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.8-ndt-inspection-r) tab, you can add the RT inspection result details by using this **Radiographic Testing (RT)** tab**.**

If you want to navigate **Radiographic Testing (RT)**,

1. Click the **Radiographic Testing (RT)** tab in the **Structural** menu. The **RT Report** page opens.
    
    [![image-1651915359832.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651915359832.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651915359832.png)
    
     **Figure 6.1: RT Report page**

#### **6.1.1 Add an RT Report**

If you want to add an RT report, do the following,

1. Click [![image-1651915422152.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651915422152.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651915422152.png) (**ADD** button) in the **RT Report** page. See Fig 6.1. A new window opens to add an RT report.
    
    [![image-1651915452611.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651915452611.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651915452611.png)
    
    [![image-1651915460726.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651915460726.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651915460726.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651915484902.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651915484902.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651915484902.png) **Tip**: A report number for a new RT report will be updated automatically in the **Report Number** box.
2. In the ****NDT By**** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an RT request number from a drop-down list.
4. In the **Prepared By** box, enter the name of a person who has prepared the RT report.
5. In the **Prepared Date** box, select the prepared date of the RT report.
6. In the **Reviewed By** box, enter the name of a person who has reviewed the RT report.
7. In the **Reviewed Date** box, select the reviewed date of the RT report.
8. In the **Approved By** boxes, enter the name of a person who has approved the RT report.
9. In the **Approved Date** box, select the approved date of the RT report.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The RT report is successfully added. Once you have added the RT report, you must add RT results for the respective added RT report.

#### **6.1.2 Add RT Results** 

If you want to add the RT results for the respective RT report, do the following,

1. Click the respective added RT report in the **RT Report** page. See Fig 6.1. The RT Results window opens.
    
    [![image-1651915646092.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651915646092.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651915646092.png)
    
     **Figure 6.1.1: RT Results page**
2. In the **Image Quality Indicator (IQI)** box, select IQI from a drop-down list.
3. In the **Source &amp; Size (MM)** box, select the RT source and their size from a drop-down list.
4. In the **Density** box, enter the radiographic density range.
5. In the **Code** box, select the code of the material from a drop-down list.
6. In the **Procedure Number** box, select the procedure number from a drop-down list.
7. In the **Sensitivity (%)** box, set the radiographic sensitivity by using up and down arrows.
8. In the **Approved By** boxes, enter the name of a person who has approved the RT report.
9. In the **Approved Date** box, select the approved date of the RT report.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The RT report is successfully added. Once you have added the RT report, you must add RT results for the respective added RT report.

#### **6.1.2 Add RT Results** 

If you want to add the RT results for the respective RT report, do the following,

1. Click the respective added RT report in the **RT Report** page. See Fig 6.1. The RT Results window opens.
    
    [![image-1651983962662.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651983962662.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651983962662.png)
    
     **Figure 6.1.1: RT Results page**
2. In the **Image Quality Indicator (IQI)** box, select IQI from a drop-down list.
3. In the **Source &amp; Size (MM)** box, select the RT source and their size from a drop-down list.
4. In the **Density** box, enter the radiographic density range.
5. In the **Code** box, select the code of the material from a drop-down list.
6. In the **Procedure Number** box, select the procedure number from a drop-down list.
7. In the **Sensitivity (%)** box, set the radiographic sensitivity by using up and down arrows.
8. In the **Developing Time (Mins)** box, set the developing time by using up and down arrows.
9. In the **Film/ Type** box, select the name of a film including type from a drop-down list.
10. In the **Placement of IQI** box, select any one option from source side and film side.
11. In the **Source to Object Distance (SOD)** box, enter the distance range between the source and the object.
12. In the **Screens Type** box, enter the type of screens.
13. In the **Visible Wire/ Hole** box, enter the relevant detail.
14. In the **Acceptance Criteria** box, select the acceptance criteria from a drop-down list.
15. In the ****Source to Film Distance (SFD)****box, enter the distance range between the source and the film.
16. In the **Focus Film Distance (FFD)** box, enter the focus film distance range.
17. In the **Source** box, select any one source option whether inside, outside, or other.
18. In the **Technique** box, select the radiographic technique from a drop-down list.
19. In the **Examination Stage** box, select the examination stage from the specified options.
20. In the **Material** box, select the material from a drop-down list.
21. In the **Surface Condition** box, select the condition of the surface from the specified options.
22. In the **Source Strength** box, enter the source strength range.
23. In the **Exposure Time (Mins)** box, set the exposure time by using up and down arrows.
24. In the **Note** box, enter any note if you want.
25. Click **Save RT Details**.

The RT results are successfully updated. Once you have updated the RT results, you must import joints added for the RT inspection.

#### **6.1.3 Import Joints**

If you want to import joints for the updated RT results,

1. Click [![image-1651984603138.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984603138.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984603138.png) (**Import Joints** button) in the **RT Results** See Fig 6.1.1. The **Joints** window opens with a list of joints.
    
    [![image-1651984618657.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984618657.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984618657.png)
2. Select the joints you want to import.
3. Click [![image-1651984648770.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984648770.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984648770.png) (**Import Selected Joints** button).
    
    The selected joints are imported for the respective RT results. Once you have imported the joints, you must add the marker results.

#### **6.1.4 Add Marker Results**

If you want to add marker results for the respective RT results,

[![image-1651984688412.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984688412.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984688412.png)

1. Click [![image-1651984710955.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984710955.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984710955.png) (Add icon) for the respective RT results. The **Marker Results** window opens.
    
    [![image-1651984728723.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984728723.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984728723.png)
2. If you want to add any additional markers,
    
    
    1. 1. Set the number in the **No. of Additional Markers** box by using up and down arrows.
        2. Click [![image-1651984771433.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984771433.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984771433.png) (**ADD** button).
3. If you want edit any existing marker results, 
    1. 1. Click [![image-1651984794840.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984794840.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984794840.png) (Edit icon) in the **Edit** column for the respective marker results.
            
            A new window opens to edit the marker results.
            
            [![image-1651984835180.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984835180.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984835180.png)
        2. Click any box where you want to edit the details, and edit the marker results.
        3. Click **Save**.
4. If you want delete any existing marker results, click (Delete icon) for the respective marker results.

#### **6.1.5 Add Report Photos**

If you want to add any report photos for the updated RT results,

1. Click [![image-1651984922206.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984922206.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984922206.png) (**ADD** button) in the **Report Photos** box in the **RT Results** window. See Fig 6.1.1. [![image-1651984944230.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984944230.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984944230.png)
2. Click [![image-1651984959950.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651984959950.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651984959950.png) (****Browse**** button) to browse a photo stored in your computer.
3. Click **Upload**.

The selected photo will be updated.

#### **6.1.6 Attach a File into an RT Report**

If you want to attach any file with any RT report listed in the **RT Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.1.7 Print an NDT – RT report**

If you want to print an NDT - RT report, click [![image-1651985039630.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985039630.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985039630.png) (print icon) provided in the **Report** column of the **RT Report** page. See Fig 6.1.

#### **6.1.8 Edit Any RT Report**

 If you want to edit any existing RT report in the **RT Report** page, do the following,

1. Click [![image-1651985091602.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985091602.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985091602.png) (Edit icon) in the **Edit** column for the respective RT report. See Fig 6.1. A new window opens to edit the RT report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.1.9 Export RT Report List**

You can export a list of RT reports added in the **RT Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.1.10 Filter Any RT Report** 

If you want to filter any RT report, do one of the following, [![image-1651985206408.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985206408.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985206408.png)

1. If you want to filter any RT report based on the report number, enter the corresponding report number in the **Report No** box in the **RT Report** page, and then Click **Search**.
2. If you want to filter any RT report based on the request number, enter the corresponding request number in the **Request No** box in the **RT Report** page, and then Click **Search**.
3. If you want to filter any RT report based on the drawing number, enter the corresponding drawing number in the ****Drawing No**** box in the ****RT Report**** page, and then Click ****Search****.



### **6.2 Ultrasonic Testing (UT)** 

The UT method is one of the NDT inspection methods used for inspecting the materials in the structural project by using high frequency sound waves. Once the UT inspection request added in the[<u> </u>**<u>NDT Inspection Request</u>**](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.8-ndt-inspection-r) tab, you can add the UT inspection result details by using this **Ultrasonic Testing (UT)** tab**.** If you want to navigate **Ultrasonic Testing (UT)**,

1. Click the **Ultrasonic Testing (UT)** tab in the **Structural** menu. The **UT Report** page opens.
    
    [![image-1651985300157.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985300157.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985300157.png)
    
     **Figure 6.2: UT Report page**

#### **6.2.1 Add an UT Report**

If you want to add an UT report, do the following,

1. Click [![image-1651985351149.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985351149.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985351149.png) (**ADD** button) in the U**T Report** page. See Fig 6.2. A new window opens to add an UT report.
    
    [![image-1651985371929.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985371929.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985371929.png)
    
    [![image-1651985395804.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985395804.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985395804.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651985407432.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985407432.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985407432.png)**Tip**: A report number for a new UT report will be updated automatically in the **Report Number** box.
2. In the ****NDT By**** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an UT request number from a drop-down list.
4. In the **Prepared By** box, enter the name of a person who has prepared the UT report.
5. In the **Prepared Date** box, select the prepared date of the UT report.
6. In the ****Reviewed By**** box, enter the name of a person who has reviewed the UT report.
7. In the **Reviewed Date** box, select the reviewed date of the UT report.
8. In the **Approved By** boxes, enter the name of a person who has approved the UT report.
9. In the **Approved Date** box, select the approved date of the UT report.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The UT report is successfully added. Once you have added the UT report, you must add UT results for the respective added UT report.

#### **6.2.2 Add UT Results** 

If you want to add the UT results for the respective UT report, do the following,

1. Click the respective added UT report in the **UT Report** page. See Fig 6.2. The UT Results window opens.
    
    [![image-1651985545268.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985545268.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985545268.png)
    
    [![image-1651985556004.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985556004.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985556004.png)
    
    [![image-1651985564176.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985564176.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985564176.png)
    
     **Figure 6.2.1: UT Results page**
2. In the **Test Method** box, select the test method from a drop-down list.
3. In the **Description** box, enter the description about the UT inspection.
4. In the **Material** box, select the material from a drop-down list.
5. In the **Test Equipment** box, select the test equipment from a drop-down list.
6. In the **Acceptance Criteria** box, select the acceptance criteria from a drop-down list.
7. In the **Couplant** box, select the couplant material from a drop-down list.
8. In the **Test** **Procedure Number** box, select the test procedure number from a drop-down list.
9. In the **Simulation Blocks** box, enter the detail of simulation blocks.
10. In the **Ref. Hole Diameter** box, enter the diameter value of the reference hole.
11. In the **Sensitivity Setting** box, enter the information about the sensitivity setting.
12. In the **Sides Scanned** box, enter the details of the sides that are scanned.
13. In the **Special Equipment** box, enter the name of the special equipment if any.
14. In the **Computerized Program Name** box, enter the computerized program name.
15. In the **Surface Scanned** box, the details of the surfaces that are scanned.
16. In the **Flaw Detector** box, select a flaw detector from a drop-down list.
17. In the **Scan Limitation** box, enter the limitation range of scanning.
18. In the **Bevel Type** box, enter the type of the bevel.
19. In the **Specification** box, select the specification from a drop-down list.
20. In the **Calibration Block** box, select the calibration block from a drop-down list.
21. In the **Remarks** box, enter your remarks if any.
22. In the **Technique** box, select the technique from a drop-down list.
23. In the **Examination Stage** box, select the examination stage from the specified options.
24. In the **Surface Condition** box, select the surface condition from the specified options.
25. Click **Save UT Details**.

The UT results are successfully updated. Once you have updated the UT results, you must add the probe and cable details for the UT inspection.

#### **6.2.3 Add Probe and Cable details** 

If you want to add probe and cable details for the updated UT results,

1. Click [![image-1651985830317.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985830317.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985830317.png) (**Add Probe/ Cable** button) in the **Probe&amp; Cable Details** window. See Fig 6.2.1. A new window opens to add the probe and cable details.
    
    [![image-1651985848658.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985848658.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985848658.png)
2. In the **Probe** box, select a probe from a drop-down list.
3. In the **Cable** box, select a cable from a drop-down list.
4. In the **Ref. dB** box, enter the reference decibel range.
5. In the **Surf Comp dB** box, enter the decibel range of the surface component.
6. In the **Test Range (MM)** box, enter the test range in millimeters.
7. In the **Reference Level** box, enter the reference level detail.
8. In the **Scanning dB** box, enter the scanning decibel range.
9. In the **TR Loss** box, enter the transmission loss detail.
10. Click **Save**.

The probe and cable details are successfully added. Once you have added the probe and cable details, you must add the reference setting details.

#### **6.2.4 Add Reference Setting details** 

If you want to add the reference setting details for the updated UT results,

1. Click [ ![image-1651985956553.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985956553.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985956553.png) (**Add Reference Setting** button) in the **Reference Setting Details** See Fig 6.2.1. A new window opens to add the reference setting details.
    
    [![image-1651985982525.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651985982525.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651985982525.png)
2. In the **Reference Block** box, select the reference block from a drop-down list.
3. In the **Probe Sr. No** box, select the serial number of the probe from a drop-down list.
4. In the **Reference** box, enter the reference detail.
5. In the **Eqpt Gain (dB)** box, enter the equipment gain in decibels.
6. In the **Damping** box, enter the damping ratio.
7. In the **Rejection** box, enter the rejection detail.
8. In the **Amplitude Height** box, enter the amplitude height range.
9. In the **Skip** box, enter the skip detail.
10. In the **Beam Path** box, enter the beam path detail.
11. In the **Range** box, enter the range detail.
12. Click **Save**.

The reference setting details are successfully added. Once you have added the reference setting details, you must import joints for the updated UT results.

#### **6.2.5 Import Joints for UT**

If you want to import joints for the updated UT results,

1. Click [![image-1651986113562.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986113562.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986113562.png) (**Import Joints** button) in the U**T Results** See Fig 6.2.1. The **Joints** window opens with a list of joints.
    
    [![image-1651986185110.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986185110.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986185110.png)
2. Select the joints you want to import.
3. Click [![image-1651986242236.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986242236.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986242236.png) (**Import Selected Joints** button).

The selected joints are imported for the respective UT results. Once you have imported the joints, you must add the UT detail results.

#### **6.2.6 Add UT Results**

If you want to add UT detail results for the respective UT results,

[![image-1651986280609.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986280609.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986280609.png)

1. Click [![image-1651986301680.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986301680.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986301680.png) (Add icon) for the respective UT results. The **UT Detail Results** window opens.
    
    [![image-1651986314412.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986314412.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986314412.png)
2. Click [![image-1651986326534.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986326534.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986326534.png) (**ADD** button) in the **UT Detail Results** window.
    
    A new window opens in the **Probes** column.
    
    [![image-1651986344825.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986344825.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986344825.png)
3. Select the probe from a drop-down list.
4. Enter other details in the respective columns.
5. Click **Save**.

#### **6.2.7 Add Report Photos**

If you want to add any report photos for the updated UT results,

1. Click [![image-1651986389344.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986389344.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986389344.png) (**ADD** button) in the **Report Photos** box in the **UT Results** See Fig 6.2.1. [![image-1651986402335.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986402335.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986402335.png)
2. Click [![image-1651986417627.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986417627.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986417627.png) (**Browse** button) to browse a photo stored in your computer.
3. Click **Upload**.

The selected photo will be updated.

#### **6.2.8 Attach a File into an UT Report**

If you want to attach any file with any UT report listed in the **UT Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.2.9 Print an NDT – UT Report**

If you want to print an NDT - UT report, click[![image-1651986568467.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986568467.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986568467.png)(print icon) provided in the **Report** column of the **UT Report** page. See Fig 6.2.

#### **6.2.10 Edit Any UT report**

 If you want to edit any existing UT report in the U**T Report** page, do the following,

1. Click [![image-1651986610066.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651986610066.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651986610066.png) (Edit icon) in the **Edit** column for the respective UT report. See Fig 6.2. A new window opens to edit the UT report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.2.11 Export UT Report List**

You can export a list of UT reports added in the **UT Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.2.12 Filter Any UT Report** 

If you want to filter any UT report, do one of the following,[![image-1651987820280.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651987820280.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651987820280.png)

1. If you want to filter any UT report based on the report number, enter the corresponding report number in the **Report No** box in the **UT Report** page, and then Click **Search**.
2. If you want to filter any UT report based on the request number, enter the corresponding request number in the ****Request No**** box in the ****UT Report**** page, and then Click ****Search****.

If you want to filter any UT report based on the drawing number, enter the corresponding drawing number in the **Drawing No** box in the **UT Report** page, and then Click **Search**.


### **6.3 Dye Penetrant Testing (DPT)**

The DPT method is one of the oldest and simplest NDT inspection methods used for inspecting the materials in the structural project by using ultraviolet or white light, depending on the type of dye used - fluorescent or non fluorescent (visible). PT also called liquid penetrate inspection (LPI) or penetrant testing (PT).

Once the UT inspection request added in the [**<u>NDT Inspection Request</u>**](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.8-ndt-inspection-r) tab, you can add the UT inspection result details by using this **Dye Penetrant Testing (DPT)** tab**.** If you want to navigate **Dye Penetrant Testing (DPT)**,

1. Click the **Dye Penetrant Testing (DPT)** tab in the **Structural** menu. The **PT Report** page opens.
    
    [![image-1651987913649.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651987913649.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651987913649.png)
    
     **Figure 6.3: PT Report page**

#### **6.3.1 Add a DPT Report**

If you want to add a DPT report, do the following,

1. Click [![image-1651987980001.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651987980001.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651987980001.png) (**ADD** button) in the **PT Report** page. See Fig 6.3. A new window opens to add an PT report.
    
    [![image-1651988268574.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988268574.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988268574.png)
    
    [![image-1651988283988.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988283988.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988283988.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651988299424.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988299424.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988299424.png)**Tip**: A report number for a new PT report will be updated automatically in the **Report Number** box.
2. In the **NDT By** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an PT request number from a drop-down list.
4. In the **Prepared By** box, enter the name of a person who has prepared the PT report.
5. In the **Prepared Date** box, select the prepared date of the PT report.
6. In the **Reviewed By** box, enter the name of a person who has reviewed the PT report.
7. In the **Reviewed Date** box, select the reviewed date of the PT report.
8. In the **Approved By** boxes, enter the name of a person who has approved the PT report.
9. In the **Approved Date** box, select the approved date of the PT report.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The PT report is successfully added. Once you have added the PT report, you must add PT results for the respective added PT report.

#### **6.3.2 Add DPT Results** 

If you want to add the DPT results for the respective PT report, do the following,

1. Click the respective added PT report in the **PT Report** page. See Fig 6.3. The DPT Results window opens.
    
    [![image-1651988667279.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988667279.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988667279.png)
    
    [![image-1651988674053.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988674053.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988674053.png)
    
     **Figure 6.3.1: DPT Results page**
2. In the **Light Source** box, enter the light source detail.
3. In the **Description** box, enter the description.
4. In the **Test Procedure** box, select the test procedure from a drop-down list.
5. In the **Test Method** box, select the test method from a drop-down list.
6. In the **Acceptance Criteria** box, select the acceptance criteria from a drop-down list.
7. In the **Surface Condition** box, enter the condition of the surface.
8. In the **Dwell Time** box, enter dwell time range.
9. In the **Surface Temperature** box, enter the surface temperature value.
10. In the **Cleaner** box, select the cleaner from a drop-down list.
11. In the **Penetrant** box, select the penetrant from a drop-down list.
12. In the **Developer** box, select the developer from a drop-down list.
13. In the **Material Specification** box, enter the material specification.
14. In the **Material Thickness** box, enter the material thickness value.
15. In the **Development Time** box, enter the time for development.
16. In the **Welding Process** box, enter the type of welding process.
17. In the **Code** box, enter the code detail.
18. In the **Examination Stage** box, select the examination stage from the specified options.
19. In the **Item Tested** box, select the tested items from the specified options.
20. In the **Inspection Method** box, select the inspection method from the specified options.
21. In the **Material** box, select the material from a drop-down list.
22. In the **Remarks** box, enter your remarks if any.
23. Click **Save DPT Details**.

The DPT results are successfully updated. Once you have updated the DPT results, you must import joints added for the DPT inspection results.

#### **6.3.3 Import Joints for DPT**

If you want to import joints for the updated DPT results,

1. Click [![image-1651988870782.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988870782.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988870782.png) (**Import Joints** button) in the **DPT Results** window. See Fig 6.3.1. The **Joints** window opens with a list of joints.
    
    [![image-1651988896812.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988896812.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988896812.png)
2. Select the joints you want to import.
3. Click [![image-1651988911579.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988911579.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988911579.png) (**Import Selected Joints** button).
    
    The selected joints are imported for the respective DPT results.

#### **6.3.4 Add Report Photos**

If you want to add any report photos for the updated DPT results,

1. Click [![image-1651988951316.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988951316.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988951316.png) (**ADD** button) in the **Report Photos** box in the **DPT Results** window. See Fig 6.3.1. [![image-1651988976728.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988976728.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988976728.png)
2. Click [![image-1651988988048.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651988988048.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651988988048.png) (**Browse** button) to browse a photo stored in your computer.
3. Click **Upload**.
    
    The selected photo will be updated.

#### **6.3.5 Attach a File into a DPT Report**

If you want to attach any file with any DPT report listed in the **PT Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.3.6 Print an NDT – DPT report**

If you want to print an NDT - PT report, click [![image-1651989107514.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989107514.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989107514.png)(print icon) provided in the **Report** column of the **PT Report** page. See Fig 6.3.

#### **6.3.7 Edit Any DPT report**

 If you want to edit any existing DPT report in the **RT Report** page, do the following,

1. Click [![image-1651989141539.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989141539.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989141539.png) (Edit icon) in the **Edit** column for the respective DPT report. See Fig 6.3. A new window opens to edit the DPT report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.3.8 Export DPT Report List**

You can export a list of DPT reports added in the **PT Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.3.9 Filter Any DPT Report** 

If you want to filter any DPT report, do one of the following,[![image-1651989245911.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989245911.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989245911.png)

1. If you want to filter any DPT report based on the report number, enter the corresponding report number in the **Report No** box in the **PT Report** page, and then Click **Search**.
2. If you want to filter any DPT report based on the report number, enter the corresponding report number in the **Report No** box in the **PT Report** page, and then Click **Search**.

If you want to filter any DPT report based on the report number, enter the corresponding report number in the **Report No** box in the **PT Report** page, and then Click **Search**.



### **6.4 PT After Load Test**

The **PT After Load Test** tab in the **Structural** menu helps you to add PT results while performing the PT inspection after completing the load test.

Once the PT after load test inspection request added in the [**<u>NDT Inspection Request</u>**](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.8-ndt-inspection-r) tab, you can add the PT result details by using this **PT After Load Test** tab**.** If you want to navigate **PT After Load Test**,

1. Click the **PT After Load Test** tab in the **Structural** menu. The **PT After Load Test Report** page opens. [![image-1651989380363.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989380363.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989380363.png)
    
     **Figure 6.4: PT After Load Test Report page**

#### **6.4.1 Add a PT after load test report**

If you want to add a PT after load test report, do the following,

1. Click [![image-1651989429583.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989429583.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989429583.png) (**ADD** button) in the **PT After Load Test Report** page. See Fig 6.4. A new window opens to add a PT after load test report.
    
    [![image-1651989443350.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989443350.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989443350.png)
    
    [![image-1651989462745.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989462745.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989462745.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651989704531.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651989704531.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651989704531.png)**Tip**: A report number for a new PT report will be updated automatically in the **Report Number** box.
2. In the **NDT By** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an PT request number after load test from a drop-down list.
4. In the **Prepared By** box, enter the name of a person who has prepared the PT report after load test.
5. In the ****Prepared Date**** box, select the prepared date of the PT report after load test.
6. In the ****Reviewed By**** box, enter the name of a person who has reviewed the PT report after load test.
7. In the ****Reviewed Date**** box, select the reviewed date of the PT report after load test.
8. In the ****Approved By**** boxes, enter the name of a person who has approved the PT report after load test.
9. In the ****Approved Date**** box, select the approved date of the PT report after load test.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The PT report after load test is successfully added. Once you have added the PT report, you must add PT results for the respective PT report.

#### **6.4.2 Add PT Results** 

If you want to add the PT results for the respective PT report after load test, do the following,

1. Click the respective added PT report in the **PT After Load Test Report** page. See Fig 6.4. The **PT After Load Test Results** page opens.
    
    [![image-1651991710992.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651991710992.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651991710992.png)
    
     **Figure 6.4.1: PT After Load Test Results** **page**
2. In the **Light Source** box, enter the light source detail.
3. In the **Description** box, enter the description.
4. In the **Test Procedure** box, select the test procedure from a drop-down list.
5. In the **Test Method** box, select the test method from a drop-down list.
6. In the **Acceptance Criteria** box, select the acceptance criteria from a drop-down list.
7. In the **Surface Condition** box, enter the condition of the surface.
8. In the **Dwell Time** box, enter dwell time range.
9. In the **Surface Temperature** box, enter the surface temperature value.
10. In the **Cleaner** box, select the cleaner from a drop-down list.
11. In the **Penetrant** box, select the penetrant from a drop-down list.
12. In the **Developer** box, select the developer from a drop-down list.
13. In the **Material Specification** box, enter the material specification.
14. In the **Material Thickness** box, enter the material thickness value.
15. In the **Development Time** box, enter the time for development.
16. In the **Welding Process** box, enter the type of welding process.
17. In the **Examination Stage** box, select the examination stage from the specified options.
18. In the **Remarks** box, enter your remarks if any.
19. Click **Save PTLT Details**.

The PT after load test results are successfully updated. Once you have updated the PT results, you must import joints added for the PT after load test inspection results.

#### **6.4.3 Import Joints for PT After Load Test**

If you want to import joints for the updated PT after load test results,

1. Click [![image-1651991888610.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651991888610.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651991888610.png) (**Import Joints** button) in the **PT After Load Test Results** window. See Fig 6.4.1. The **Joints** window opens with a list of joints.
    
    [![image-1651991913384.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651991913384.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651991913384.png)
2. Select the joints you want to import.
3. Click [![image-1651991932082.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651991932082.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651991932082.png) (**Import Selected Joints** button).
    
    The selected joints are imported for the respective DPT results.

#### **6.4.4 Add Report Photos**

If you want to add any report photos for the updated PT after load test results,

1. Click [![image-1651991965975.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651991965975.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651991965975.png) (**ADD** button) in the **Report Photos** box in the **PT After Load Test Results** See Fig 6.4.1. [![image-1651991982159.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651991982159.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651991982159.png)
2. Click [![image-1651992000367.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992000367.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992000367.png) (**Browse** button) to browse a photo stored in your computer.
3. Click **Upload**.
    
    The selected photo will be updated.

#### **6.4.5 Attach a file into a PT After Load Test Report**

If you want to attach any file with any PT report listed in the **PT After Load Test Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.4.6 Print an NDT – PT After Load Test Report**

If you want to print an NDT – PT after load test report, click[![image-1651992108377.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992108377.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992108377.png)(print icon) provided in the **Report** column of the **PT After Load Test Report** page. See Fig 6.4.

#### **6.4.7 Edit Any PT After Load Test Report**

 If you want to edit any existing PT report in the **PT After Load Test Report** page, do the following,

1. Click [![image-1651992194889.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992194889.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992194889.png)(Edit icon) in the **Edit** column for the respective PT report. See Fig 6.4. A new window opens to edit the PT report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.4.8 Export PT after load test report list**

You can export a list of PT reports added in the **PT After Load Test Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.4.9 Filter Any PT After Load Test Report** 

If you want to filter any PT report, do one of the following,[![image-1651992271777.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992271777.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992271777.png)

1. If you want to filter any PT report based on the report number, enter the corresponding report number in the **Report No** box in the **PT After Load Test Report** page, and then Click **Search**.
2. If you want to filter any PT report based on the request number, enter the corresponding request number in the **Request No** box in the **PT After Load Test Report** page, and then Click **Search**.

If you want to filter any PT report based on the drawing number, enter the corresponding drawing number in the **Drawing No** box in the **PT After Load Test Report** page, and then Click **Search**.



### **6.5 Magnetic Particle Testing (MPT)**

MPT also referred to as Magnetic Particle Inspection is one of the NDT inspection methods used to detect defects or discontinuities such as cracks, at or near the surface in ferromagnetic metals such as iron, steel, nickel, cobalt and so on.

Once the MPT inspection request added in the [**<u>NDT Inspection Request</u>**](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.8-ndt-inspection-r) tab, you can add the MPT inspection result details by using this **Magnetic Particle Testing (MPT)** tab**.** If you want to navigate **Magnetic Particle Testing (MPT)**,

1. Click the **Magnetic Particle Testing (MPT)** tab in the **Structural** menu. The **MT Report** page opens.
    
    [![image-1651992414838.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992414838.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992414838.png) **Figure 6.5: MT Report page**

#### **6.5.1 Add an MPT Report**

If you want to add an MPT report, do the following,

1. Click [![image-1651992467914.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992467914.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992467914.png) (**ADD** button) in the **MT Report** page. See Fig 6.5. A new window opens to add an MPT report.
    
    [![image-1651992480844.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992480844.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992480844.png)
    
    [![image-1651992491566.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992491566.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992491566.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651992511163.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992511163.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992511163.png) **Tip**: A report number for a new MPT report will be updated automatically in the **Report Number** box.
2. In the **NDT By** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an MPT request number from a drop-down list.
4. In the **Prepared By** box, enter the name of a person who has prepared the MPT report.
5. In the **Prepared Date** box, select the prepared date of the MPT report.
6. In the **Reviewed By** box, enter the name of a person who has reviewed the MPT report.
7. In the **Reviewed Date** box, select the reviewed date of the MPT report.
8. In the **Approved By** boxes, enter the name of a person who has approved the MPT report.
9. In the **Approved Date** box, select the approved date of the MPT report.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The MPT report is successfully added. Once you have added the MPT report, you must add MPT results for the respective MPT report.

#### **6.5.2 Add MPT Results** 

If you want to add the MPT results for the respective MPT report, do the following,

1. Click the respective MPT report in the **MT Report** page. See Fig 6.5. The MPT Results window opens.
    
    [![image-1651992626683.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992626683.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992626683.png)
    
    [![image-1651992634124.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992634124.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992634124.png)
    
    [![image-1651992642609.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992642609.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992642609.png)
    
     **Figure 6.5.1: MPT Results page**
2. In the **Test Equipment** box, select the test equipment from a drop-down list.
3. In the **Description** box, enter the description.
4. In the **Test Procedure** box, select the test procedure from a drop-down list.
5. In the **Test Method** box, select the test method from a drop-down list.
6. In the **Black Magnetic Ink** box, select the type of black magnetic ink from a drop-down list.
7. In the **Surface Condition** box, enter the condition of the surface.
8. In the **Light Source** box, enter the light source detail.
9. In the **White Contrast Paint** box, select the type of white contrast paint.
10. In the **Material Specification** box, enter the material specification.
11. In the **Material Thickness** box, enter the material thickness value.
12. In the **Type of Current** box, enter the type of current.
13. In the **Lifting Capacity** box, select the lifting capacity value.
14. In the **Acceptance Criteria** box, select the acceptance criteria from a drop-down list.
15. In the **Yoke/ Prod Space** box, enter the relevant information.
16. In the **Particles Type** box, select the type of particles from a drop-down list.
17. In the **Particles Make &amp; model** box, enter the model of the particle including made of materials.
18. In the **Background Contrast &amp; Type** box, enter the type of background including contrast range.
19. In the ****Demagnetization**** box, if you want demagnetization select ****Yes**** otherwise select ****No****.
20. In the **Magnetizing Technique** box, enter the magnetizing technique.
21. In the **Surface Temperature** box, enter the surface temperature value.
22. In the **Calibration Sensitivity** box, enter the calibration sensitivity range.
23. In the **Method of Inspection** box, enter the inspection method.
24. In the **Code** box, enter the code detail.
25. In the **Color** box, select any color from the specified options.
26. In the **Suspension** box, select any suspension liquid from the specified options.
27. In the **Lighting** box, select any lighting from the specified options.
28. In the **Method** box, select any method from the specified options.
29. In the **Item Tested** box, select the tested items from the specified options.
30. In the **Examination Stage** box, select the examination stage from the specified options.
31. Click **Save MPT Details**.

The MPT results are successfully updated. Once you have updated the MPT results, you must import joints added for the MPT inspection results.

#### **6.5.3 Import Joints for MPT** 

If you want to import joints for the updated MPT results,

1. Click [![image-1651992843501.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992843501.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992843501.png) (**Import Joints** button) in the **MPT Results** See Fig 6.5.1. The **Joints** window opens with a list of joints.
    
    [![image-1651992855632.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992855632.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992855632.png)
2. Select the joints you want to import.
3. Click [![image-1651992877171.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992877171.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992877171.png) (**Import Selected Joints** button).
    
    The selected joints are imported for the respective MPT results.

#### **6.5.4 Add Report Photos**

If you want to add any report photos for the updated MPT results,

1. Click [![image-1651992927758.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992927758.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992927758.png) (**ADD** button) in the **Report Photos** box in the **MPT Results** window. See Fig 6.5.1. [![image-1651992937159.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992937159.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992937159.png)
2. Click [![image-1651992952724.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651992952724.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651992952724.png) (**Browse** button) to browse a photo stored in your computer.
3. Click **Upload**.

The selected photo will be updated.

#### **6.5.5 Attach a File into an MPT Report**

If you want to attach any file with any MPT report listed in the **MT Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.5.6 Print an NDT – MPT Report**

If you want to print an NDT - MPT report, click [![image-1651993041568.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651993041568.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651993041568.png) (print icon) provided in the **Report** column of the **MT Report** page. See Fig 6.5.

#### **6.5.7 Edit Any MPT Report**

 If you want to edit any existing MPT report in the **MT Report** page, do the following,

1. Click [![image-1651993088249.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651993088249.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651993088249.png)(Edit icon) in the **Edit** column for the respective MPT report. See Fig 6.5. A new window opens to edit the MPT report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.5.8 Export MPT Report List**

You can export a list of MPT reports added in the **MT Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.5.9 Filter Any MPT Report** 

If you want to filter any MPT report, do one of the following,[![image-1651993352168.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651993352168.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651993352168.png)

1. If you want to filter any MPT report based on the report number, enter the corresponding report number in the **Report No** box in the **MT Report** page, and then Click **Search**.
2. If you want to filter any MPT report based on the report number, enter the corresponding report number in the ****Report No**** box in the ****MT Report**** page, and then Click ****Search****.

If you want to filter any MPT report based on the drawing number, enter the corresponding drawing number in the **Drawing No** box in the **MT Report** page, and then Click **Search**.


### **6.6 MPI After Load Test (MPI)**

The **MPI After Load Test (MPI)** tab in the **Structural** menu helps you to add MPI results while performing the MPI inspection after completing the load test.

Once the MPI after load test inspection request added in the [**<u>NDT Inspection Request</u>**](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.8-ndt-inspection-r) tab, you can add the MPI result details by using this **MPI After Load Test (MPI) tab**.** If you want to navigate **MPI After Load Test (MPI)**,

1. Click the **MPI After Load Test (MPI)** tab in the **Structural** menu. The **MPI Report** page opens.
    
    [![image-1652024082308.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024082308.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024082308.png)
    
     **Figure 6.6: MPI Report page**

#### **3.6.1 Add an MPI After Load Test Report**

If you want to add an MPI after load test report, do the following,

1. Click [![image-1652024140271.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024140271.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024140271.png) (**ADD** button) in the **MPI Report** page. See Fig 6.6. A new window opens to add an MPI after load test report.
    
    [![image-1652024153566.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024153566.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024153566.png)
    
    [![image-1652024165147.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024165147.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024165147.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652024178795.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024178795.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024178795.png) **Tip**: A report number for a new MPI report will be updated automatically in the **Report Number** box.
2. In the ****NDT By**** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an MPI request number after load test from a drop-down list.
4. In the ****Prepared By**** box, enter the name of a person who has prepared the MPI report after load test.
5. In the ****Prepared Date**** box, select the prepared date of the MPI report after load test.
6. In the ****Reviewed By**** box, enter the name of a person who has reviewed the MPI report after load test.
7. In the ****Reviewed Date**** box, select the reviewed date of the MPI report after load test.
8. In the ****Approved By**** boxes, enter the name of a person who has approved the MPI report after load test.
9. In the ****Approved Date**** box, select the approved date of the MPI report after load test.
10. In the **Rep. Accept Date** box, select the report accept date.
11. In the **Inspection Date** box, select the date of inspection.
12. In the **Job Done Report Number** box, enter the report number of completed inspection job.
13. In the **Job Completed Date** box, select the completed date of the inspection job.
14. Click **Save**.

The MPI report after load test is successfully added. Once you have added the MPI report, you must add MPI results for the respective MPI report.

#### **6.6.2 Add MPI Results** 

If you want to add the MPI results for the respective MPI report after load test, do the following,

1. Click the respective MPI report in the **MPI Report** page. See Fig 6.6. The MPI Results page opens.
    
    [![image-1652024590451.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024590451.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024590451.png)
    
    [![image-1652024601471.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024601471.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024601471.png)
    
     **Figure 6.6.1: MPI Results page**
2. In the **Test Equipment** box, select the test equipment from a drop-down list.
3. In the **Description** box, enter the description.
4. In the **Test Procedure** box, select the test procedure from a drop-down list.
5. In the **Test Method** box, select the test method from a drop-down list.
6. In the **Black Magnetic Ink** box, select the type of black magnetic ink from a drop-down list.
7. In the **Surface Condition** box, enter the condition of the surface.
8. In the **Light Source** box, enter the light source detail.
9. In the **White Contrast Paint** box, select the type of white contrast paint.
10. In the **Material Specification** box, enter the material specification.
11. In the **Material Thickness** box, enter the material thickness value.
12. In the **Type of Current** box, enter the type of current.
13. In the **Lifting Capacity** box, select the lifting capacity value.
14. In the **Acceptance Criteria** box, select the acceptance criteria from a drop-down list.
15. In the **Yoke/ Prod Space** box, enter the relevant information.
16. In the **Particles Type** box, select the type of particles from a drop-down list.
17. In the **Particles Make &amp; model** box, enter the model of the particle including made of materials.
18. In the **Background Contrast &amp; Type** box, enter the type of background including contrast range.
19. In the **Demagnetization** box, if you want demagnetization select **Yes** otherwise select **No**.
20. In the **Magnetizing Technique** box, enter the magnetizing technique.
21. In the **Surface Temperature** box, enter the surface temperature value.
22. In the **Remarks** box, enter your remarks if any.
23. Click **Save MPI Details**.

The MPI results are successfully updated. Once you have updated the MPI results, you must import joints added for the MPI inspection results.

#### **6.6.3 Import Joints for MPI**

If you want to import joints for the updated MPI results,

1. Click [![image-1652024814416.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024814416.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024814416.png) (**Import Joints** button) in the **MPI Results** See Fig 6.6.1. The **Joints** window opens with a list of joints.
    
    [![image-1652024827712.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024827712.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024827712.png)
2. Select the joints you want to import.
3. Click [![image-1652024850661.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024850661.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024850661.png) (**Import Selected Joints** button).
    
    The selected joints are imported for the respective MPI results.

#### **6.6.4 Add Report Photos**

If you want to add any report photos for the updated MPI results,

1. Click [![image-1652024937690.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024937690.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024937690.png) (**ADD** button) in the **Report Photos** box in the **MPI Results** See Fig 6.6.1. [![image-1652024947546.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024947546.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024947546.png)
2. Click [![image-1652024965904.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652024965904.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652024965904.png) (**Browse** button) to browse a photo stored in your computer.
3. Click **Upload**.
    
    The selected photo will be updated.

#### **6.6.5 Attach a File into an MPI Report**

If you want to attach any file with any MPI report listed in the **MPI Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.6.6 Print an NDT – MPI Report**

If you want to print an NDT - MPI report, click [![image-1652025151954.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025151954.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025151954.png) (print icon) provided in the **Report** column of the **MPI Report** page. See Fig 6.6.

#### **6.6.7 Edit Any MPI Report**

 If you want to edit any existing MPI report in the **MPI Report** page, do the following,

1. Click [![image-1652025191428.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025191428.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025191428.png) (Edit icon) in the **Edit** column for the respective MPI report. See Fig 6.6. A new window opens to edit the MPI report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.6.8 Export MPI Report List**

You can export a list of MPI reports added in the **MPI Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.6.9 Filter any MPI report** 

If you want to filter any MPI report, do one of the following,[![image-1652025264711.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025264711.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025264711.png)

1. If you want to filter any MPI report based on the report number, enter the corresponding report number in the **Report No** box in the **MPI Report** page, and then Click **Search**.
2. If you want to filter any MPI report based on the request number, enter the corresponding request number in the ****Request No**** box in the ****MPI Report**** page, and then Click ****Search****.
3. If you want to filter any MPI report based on the drawing number, enter the corresponding drawing number in the ****Drawing No**** box in the ****MPI Report**** page, and then Click ****Search****.



### **6.7 PWHT**

The **PWHT** tab in the **Structural** menu helps you to add a PWHT report after completing the PWHT inspection process. If you want to add a PWHT report, do the following,

Once the RFI request for PWHT added using the [<u>RFI Request for PWHT</u>](http://wiki.cuteinfocomm.com/link/69#bkmrk-5.10%C2%A0-rfi-request-fo) tab, you can add the PWHT result details by using this **PWHT tab**.** If you want to navigate **PWHT**,

1. Click the **PWHT** tab in the **Structural** menu. The **PWHT Report** page opens.
    
    [![image-1652025363945.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025363945.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025363945.png)
    
     **Figure 6.7: PWHT Report page**

#### **9.7.1 Add a PWHT Report**

If you want to add a PWHT report, do the following,

1. Click [![image-1652025737782.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025737782.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025737782.png) (**ADD** button) in the **PWHT Report** page. See Fig 6.7. A new window opens to add a PWHT report.
    
    [![image-1652025753803.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025753803.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025753803.png)
    
    [![image-1652025807967.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025807967.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025807967.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652025824772.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025824772.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025824772.png)**Tip**: A report number for a new PWHT report will be updated automatically in the **Report Number** box.
2. In the **NDT By** box, select the creation of NDT whether by third party or internal from a drop-down list.
3. In the **Request Number** box, select an RFI request for PWHT number from a drop-down list.
4. In the **Prepared By** box, enter the name of a person who has prepared the PWHT report.
5. In the **Prepared Date** box, select the prepared date of the PWHT report.
6. In the **Reviewed By** box, enter the name of a person who has reviewed the PWHT report.
7. In the **Reviewed Date** box, select the reviewed date of the PWHT report.
8. In the ****Accepted/ Approved By**** boxes, enter the name of a person who has approved the PWHT report.
9. In the **Accepted/ Approved Date** box, select the approved date of the PWHT report.
10. Click **Save**.

The PWHT report is successfully added. Once you have added the PWHT report, you must add PWHT result details for the respective PWHT report.

#### **6.7.2 Add PWHT Results** 

If you want to add the PWHT results for the respective PWHT report, do the following,

1. Click the respective PWHT report in the **PWHT Report** page. See Fig 6.7. The **PWHT Results** page opens.
    
    [![image-1652025939153.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652025939153.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652025939153.png)
    
     **Figure 6.7.1: PWHT Results page**
2. In the **Inspection Date** box, select the inspection date.
3. In the **Material Specification** box, enter the specification for the material.
4. In the **Speed** box, enter the speed range.
5. In the **HT Procedure No** box, select the HT procedure number.
6. In the **Heating Rate** box, enter the heating rate value.
7. In the **Holding (Temperature)** box, enter the holding temperature.
8. In the **Holding Time** box, enter the holding time value.
9. In the **Cooling Rate** box, enter the cooling rate value.
10. In the **Remarks** box, enter your remarks if any.
11. Click **Save PWHT Details**.

The PWHT results are successfully updated. Once you have updated the PWHT results, you can edit the joints added for the PWHT inspection results in the **Joint Results** window.

#### **6.7.3 Add Report Photos**

If you want to add any report photos for the updated PWHT results,

1. Click [![image-1652026076553.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026076553.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026076553.png) (**ADD** button) in the **Report Photos** box in the **PWHT Results** See Fig 6.7.1. [![image-1652026087869.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026087869.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026087869.png)
2. Click [![image-1652026109369.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026109369.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026109369.png) (**Browse** button) to browse a photo stored in your computer.
3. Click **Upload**.

The selected photo will be updated.

#### **6.7.4 Attach a File into a PWHT Report**

If you want to attach any file with any PWHT report listed in the **PWHT Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.7.5 Print a PWHT Report**

If you want to print a PWHT report, click [![image-1652026175817.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026175817.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026175817.png) (print icon) provided in the **Report** column of the **PWHT Report** page. See Fig 6.7.

#### **6.7.6 Edit Any PWHT Report**

 If you want to edit any existing PWHT report in the **PWHT Report** page, do the following,

1. Click [![image-1652026236129.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026236129.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026236129.png)(Edit icon) in the **Edit** column for the respective PWHT report. See Fig 6.7. A new window opens to edit the PWHT report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.7.7 Export PWHT Report List**

You can export a list of PWHT reports added in the **PWHT Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.7.8 Filter Any PWHT Report** 

If you want to filter any PWHT report, use [![image-1652026324516.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026324516.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026324516.png) (**FILTER** button) in the **PWHT Report** page, See Fig 6.7 or do one of the following, [![image-1652026338211.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026338211.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026338211.png)

1. If you want to filter any PWHT report based on the report number, enter the corresponding report number in the **Report No** box in the **PWHT Report** page, and then Click **Search**.
2. If you want to filter any PWHT report based on the request number, enter the corresponding request number in the ****Request No**** box in the ****PWHT Report**** page, and then Click ****Search****.
3. If you want to filter any PWHT report based on the drawing number, enter the corresponding drawing number in the **Drawing No** box in the **PWHT Report** page, and then Click **Search**.



### **6.8 Hydrostatic Report**

Hydrostatic testing is a type of pressure test where the materials are tested for strength and leaks. The **Hydrostatic Report** tab in the **Structural** menu helps you to add a hydrostatic pressure test report after completing the hydrostatic testing in the structural project.

If you want to add a hydrostatic pressure test report, do the following,

1. Click the **Hydrostatic Report** Tab. The **Hydrostatic Pressure Test Report** page opens.
    
    [![image-1652026453734.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026453734.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026453734.png)
    
     **Figure 6.8: Hydrostatic Pressure Test Report** **page**

#### **6.8.1 Add a Hydrostatic Pressure Test Report**

If you want to add a hydrostatic pressure test report,

1. Click [![image-1652026525840.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026525840.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026525840.png) (**ADD** button) in the **Hydrostatic Pressure Test Report** page. See Fig 6.8. A new window opens to add a hydrostatic pressure test report.
    
    [![image-1652026540997.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026540997.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026540997.png)
    
    [![image-1652026550510.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026550510.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026550510.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652026565074.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026565074.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026565074.png)**Tip**: A report number for a new hydrostatic pressure test report will be updated automatically in the **Report Number** box.
2. In the **Drawing** box, select the drawing from a drop-down list.
3. In the ****Prepared By**** box, enter the name of a person who has prepared the hydrostatic pressure test report.
4. In the **Prepared Date** box, select the preparation date of the report.
5. In the ****Reviewed By**** box, enter the name of a person who has reviewed the hydrostatic pressure test report.
6. In the **Reviewed Date** box, select the reviewed date of the report.
7. In the **Approved By** box, enter the name of a person who has approved the hydrostatic pressure test report.
8. In the **Approved Date** box, select the approved date of the report.
9. Click **Save**.

The hydrostatic pressure test report is successfully added. Once you have added the hydrostatic pressure test report, you must add the pressure test result details for the added report.

#### **6.8.2 Add Pressure Test Results for an Added Hydrostatic Pressure Test Report**

If you want to add the details of pressure test results for the added hydrostatic pressure test report, do the following,

1. Click [![image-1652026694611.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026694611.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026694611.png) (Edit icon) in the **Edit Report** column of the **Hydrostatic Pressure Test Report** See Fig 6.8. Multiple windows open.
    
    [![image-1652026708096.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652026708096.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652026708096.png)
    
     **Figure 6.8.1: Pressure test results page**
2. If you want to add test parameters, do the following steps,
    
    
    1. 1. Navigate to the **Test Parameters** window. See Fig 6.8.1.
        2. In the **Test Pressure** box, enter the test pressure value.
        3. In the **Test Temperature** box, enter the test temperature value.
        4. In the **Item/Part** box, select any item/part from a drop-down list.
        5. In the **Test Medium** box, enter the test medium information.
        6. In the **Holding Period** box, enter the holding period value.
        7. In the **Design Pressure** box, enter the design pressure value.
        8. In the **Test Date** box, select the test date.
        9. In the **Position** box, enter the position detail.
        10. In the **Operating Pressure** box, enter the operating pressure value.
        11. In the **Hydrostatic Test (HT) Procedure No** box, enter the hydrostatic test procedure number.
        12. In the **Maximum Allowable Working Pressure (MAWP)** box, enter the maximum allowable working pressure value.
        13. In the ****Design Temperature**** box, enter the design temperature value.
        14. In the ****Maximum Allowable Pressure (MAP)****box, enter the maximum allowable pressure value.
        15. In the ****Results/ Remarks**** box, select the result from a drop-down list.
        16. In the **Chloride** box, enter the chloride value.
        17. In the **Actual Test Pressure** box, enter the actual test pressure value.
        18. In the **Test Location** box, enter the test location detail.
        19. In the **Test Observation** box, enter the test observation detail.
        20. In the **Test Code** box, select the test code from the specified options.
        21. Click **Save**.
            
            The test parameters are successfully added.
3. If you want to add equipment details, do the following steps, 
    1. 1. Navigate to the **Equipment Details** window. See Fig 6.8.1.
        2. In the ****Conducted By**** box, select any one option whether internal or external from a drop-down list.
        3. In the **Position** box, select the position from a drop-down list.
        4. In the **Equipment Details** box, select the equipment from a drop-down list.
        5. Click **Save**.
            
            The equipment details are successfully added.
4. If you want to add test record, do the following,
    
    
    1. 1. Navigate to the **Test Records** window. See Fig 6.8.1.
        2. In the **Time** box, enter the time duration of testing.
        3. In the **PG- Bottom** box, enter the pressure value in the bottom of the bars.
        4. In the **PG- Top** box, enter the pressure value in the top of the bars.
        5. In the **Water** box, enter the temperature of the water.
        6. In the **Air** box, enter the temperature of the air.
        7. In the **Remarks** box, enter your remarks if any.
        8. Click **Save**.
            
            The test records are added successfully.
5. If you want to add report photos, do the following,
    
    
    1. 1. Navigate to the **Report Photos** window. See Fig 6.8.1.
        2. Click [![image-1652027036155.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027036155.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027036155.png) (**ADD** button) in the **Report Photos** window.
            
            [![image-1652027053497.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027053497.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027053497.png)
        3. Click (****Browse**** button) to browse a photo stored in your computer.
        4. Click **Upload**.
            
            The selected photo will be updated.

#### **6.8.3 Print a Hydrostatic Pressure Test Report**

If you want to print a hydrostatic pressure test report, click[![image-1652027120652.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027120652.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027120652.png) (print icon) provided in the **Report** column of the **Hydrostatic Pressure Test Report** page. See Fig 6.8.

#### **6.8.4 Print a Hydrostatic Pressure Test Report with Certificates**

If you want to print a hydrostatic pressure test report with certificates, click [![image-1652027156165.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027156165.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027156165.png)(print icon) provided in the **Report** **with Certificates** column of the **Hydrostatic Pressure Test Report** page. See Fig 6.8.

#### **6.8.5 Attach a File into a Hydrostatic Pressure Test Report**

If you want to attach any file with any hydrostatic pressure test report listed in the **Hydrostatic Pressure Test Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.8.6 Edit Any Hydrostatic Pressure Test Report**

If you want to edit any existing hydrostatic pressure test report in the **Hydrostatic Pressure Test Report** page, do the following,

1. Click [![image-1652027232973.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027232973.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027232973.png)(Edit icon) in the **Edit** column for the respective hydrostatic pressure test report. See Fig 6.8.
    
    A new window opens to edit the hydrostatic pressure test report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.



### **6.9 Vacuum Test**

Vacuum test performed to check for the existence of any leak in the materials utilized in the Structural project. The **Vacuum Test** tab in the **Structural** menu helps you to add a vacuum test report once the vacuum test has completed.

If you want to add a vacuum test report, do the following,

1. Click the **Vacuum Test** Tab. The **Vacuum Test** page opens.
    
    [![image-1652027304515.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027304515.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027304515.png)
    
     **Figure 6.9: Vacuum Test** **page**

#### **6.9.1 Add a Vacuum Test Report**

If you want to add a vacuum test report,

1. Click [![image-1652027605837.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027605837.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027605837.png) (**ADD** button) in the **Vacuum Test Report** page. See Fig 6.9. A new window opens to add a vacuum test report.
    
    [![image-1652027640696.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027640696.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027640696.png)
    
    [![image-1652027661534.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027661534.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027661534.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652027680045.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027680045.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027680045.png) **Tip**: A report number for a new vacuum test report will be updated automatically in the **Report Number** box.
2. In the **Description** box, enter the description for the vacuum test.
3. In the **Sub-System** box, select the sub-system from a drop-down list.
4. In the **Inspection Date** box, select the inspection date.
5. In the **Frame No** box, enter the frame number.
6. In the **Elevation** box, enter the elevation detail.
7. In the **Longitudinal** box, enter the longitudinal detail.
8. In the **Location** box, enter the location where the vacuum test is performed.
9. In the **Drawing No** box, select the drawing number from a drop-down list.
10. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
11. In the **Remarks** box, enter your remarks if any.
12. Click **Save**.

The vacuum test report is successfully added.

#### **6.9.2 Submit and Approve a Vacuum Test Report**

Once you have added the vacuum test report, the **Submission** column in the **Vacuum Test** page is appeared with [![image-1652027790673.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027790673.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027790673.png) (Submit and Reject icons).

1. If you want to submit the vacuum test report, click [![image-1652027811581.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027811581.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027811581.png) (Submit icon) in the **Submission** column. Otherwise click [![image-1652027820882.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027820882.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027820882.png)(Reject icon) to reject the request. Once you have submitted the vacuum test report, the **Request Status** column in the **Vacuum Test** page is appeared with [![image-1652027841004.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027841004.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027841004.png)(Accept and Reject icons).
2. If you want to approve the vacuum test report, click [![image-1652027878917.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027878917.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027878917.png) (Submit icon) in the ****Request Status**** Otherwise click [![image-1652027887313.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027887313.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027887313.png)(Reject icon) to reject the request.

#### **6.9.3 Print a Vacuum Test Report**

If you want to print a vacuum test report, click [![image-1652027921149.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027921149.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027921149.png) (print icon) provided in the **Report** column of the **Vacuum Test Report** page. See Fig 6.9.

#### **6.9.4 Attach a File into a Vacuum Test Report**

If you want to attach any file with any vacuum test report listed in the **Vacuum Test** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.9.5 Edit Any Vacuum Test Report**

If you want to edit any existing vacuum test report in the **Vacuum Test** page, do the following,

1. Click [![image-1652027997598.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652027997598.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652027997598.png)(Edit icon) in the **Edit** column for the respective vacuum test report. See Fig 6.9. A new window opens to edit the vacuum test report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.9.6 Export Vacuum Test Report List**

You can export a list of vacuum test reports added in the **Vacuum Test** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.9.7 Filter Any Vacuum Test Report**

If you want to filter any vacuum test report from the list of in the **Vacuum Test** page, you can use the [![image-1652028071435.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028071435.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028071435.png) (**FILTER** button). To know how to filter, see the topic, ”**Filter Any Area**”.


### **6.10 Back-Gouging**

Back-gouging is a removing process performed to remove weld metal and base metal from the weld root side by grinding, gas cutting or by using gouging electrode.

The **Back-Gouging** tab in the **Structural** menu helps you to add a back-gouging report once the back-gouging process has completed. If you want to add a back-gouging report, do the following,

1. Click the **Back-Gouging** Tab. The **Back-Gouging** page opens.
    
    [![image-1652028169487.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028169487.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028169487.png)
    
     **Figure 6.10: Back-Gouging page**

#### **6.10.1 Add a Back-Gouging Report**

If you want to add a back-gouging report,

1. Click [![image-1652028254343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028254343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028254343.png) (**ADD** button) in the B**ack-Gouging** page. See Fig 6.10. A new window opens to add a back-gouging report.
    
    [![image-1652028276185.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028276185.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028276185.png)
    
    [![image-1652028285653.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028285653.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028285653.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652028301208.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028301208.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028301208.png) **Tip**: A report number for a new back-gouging report will be updated automatically in the **Report Number** box.
2. In the **Description** box, enter the description for the back-gouging.
3. In the **Sub-System** box, select the sub-system from a drop-down list.
4. In the **Inspection Date** box, select the inspection date.
5. In the **Frame No** box, enter the frame number.
6. In the **Elevation** box, enter the elevation detail.
7. In the **Longitudinal** box, enter the longitudinal detail.
8. In the **Location** box, enter the location where the back-gouging is performed.
9. In the **Drawing No** box, select the drawing number from a drop-down list.
10. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
11. In the **Remarks** box, enter your remarks if any.
12. Click **Save**.

The back-gouging report is successfully added.

#### **6.10.2 Add Back-Gouging Report Photos**

1. Click [![image-1652028400682.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028400682.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028400682.png) (Edit icon) in the **Edit Report** column of the **Back-Gouging** page. See Fig 6.10. The **Report Photos** box opens.
    
    [![image-1652028419255.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028419255.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028419255.png)
2. Click [![image-1652028432824.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028432824.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028432824.png) (**ADD** button) in the **Report Parameters** box.
    
    [![image-1652028468290.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028468290.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028468290.png)
3. Click [![image-1652028486070.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028486070.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028486070.png) (**Browse** button) to browse a photo stored in your computer.
4. Click **Upload**.

The selected photo will be updated.

#### **6.10.3 Submit and Approve a Back-Gouging Report**

Once you have added the back-gouging report, the **Submission** column in the **Back-Gouging** page is appeared with [![image-1652028570280.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028570280.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028570280.png)(Submit and Reject icons).

1. If you want to submit the back-gouging report, click [![image-1652028589685.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028589685.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028589685.png)(Submit icon) in the **Submission** column. Otherwise click [![image-1652028599840.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028599840.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028599840.png) (Reject icon) to reject the request.
    
    Once you have submitted the back-gouging report, the **Request Status** column in the **Back-Gouging** page is appeared with (Accept and Reject icons).
2. If you want to approve the back-gouging report, click [![image-1652028628364.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028628364.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028628364.png)(Submit icon) in the ****Request Status**** Otherwise click [![image-1652028636624.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028636624.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028636624.png)(Reject icon) to reject the request.

#### **6.10.4 Print a Back-Gouging Report**

If you want to print a back-gouging report, click[![image-1652028668149.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028668149.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028668149.png)(print icon) provided in the **Report** column of the **Back-Gouging** page. See Fig 6.10.

#### **6.10.5 View the Back-Gouging Signature Details** 

If you want to view the signature details of the persons who has completed the back-gouging, click [![image-1652028713712.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028713712.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028713712.png)(Sign icon) provided in the **Sign Details** column of the **Back-Gouging** page. See Fig 6.10.

#### **6.10.6 Attach a File into a Back-Gouging Report**

If you want to attach any file with any back-gouging report listed in the **Back-Gouging** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.10.7 Edit Any Back-Gouging Report**

If you want to edit any existing back-gouging report in the **Back-Gouging** page, do the following,

1. Click [![image-1652028803775.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028803775.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028803775.png)(Edit icon) in the **Edit** column for the respective back-gouging report. See Fig 6.10. A new window opens to edit the back-gouging report.
    
    [![image-1652028821255.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028821255.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028821255.png)
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.10.8 Export Back-Gouging Report List**

You can export a list of back-gouging reports added in the **Back-Gouging** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.10.9 Filter Any Back-Gouging Report**

If you want to filter any back-gouging report from the list of in the **Back-Gouging** page, you can use the (**FILTER** button). To know how to filter, see the topic, ”**Filter Any Area**”.


### **6.11 Final Visual** 

Visual testing is one of methods of NDT of optical type. Final visual testing is usually performed with the naked eye or with magnifying glasses (magnifiers) with magnification up to 7x.

The **Final Visual** tab in the **Structural** menu helps you to add a final visual test report after completing the final visual test. If you want to add a final visual test report, do the following,

1. Click the **Final Visual** Tab. The **Final Visual Test** page opens.
    
    [![image-1652028936757.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028936757.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028936757.png)
    
     **Figure 6.11: Final Visual Test page**

#### **6.11.1 Add a Final Visual Test Report**

If you want to add a final visual test report,

1. Click [![image-1652028997630.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652028997630.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652028997630.png) (**ADD** button) in the **Final Visual Test page. See Fig 6.11. A new window opens to add a final visual test report.
    
    [![image-1652029012910.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029012910.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029012910.png)
    
    [![image-1652029023886.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029023886.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029023886.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
2. In the **Report Number** box, enter the report number for the final visual test.
3. In the **Description** box, enter the description for the final visual test.
4. In the **System** box, select the system from a drop-down list.
5. In the **Inspection Date** box, select the inspection date.
6. In the **Frame No** box, enter the frame number.
7. In the **Elevation** box, enter the elevation detail.
8. In the **Longitudinal** box, enter the longitudinal detail.
9. In the **Location** box, enter the location where the final visual test is performed.
10. In the **Drawing No** box, select the drawing number from a drop-down list.
11. In the **Assessment Checklist** box, enter the assessment checklist detail.
12. In the **Checklist No** box, select the check list number from a drop-down list.
13. In the **Discipline** box, enter the discipline detail.
14. In the **Site** box, enter the site detail.
15. In the **Contractor** box, enter the name of a contractor.
16. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
17. In the **Module No** box, enter the module number.
18. In the **Area/ Component** box, enter the area/ component detail.
19. In the **Stage of Completion** box, select the stage of completion of visual test from the given options.
20. In the **Document Type** box, enter the type of document.
21. In the **Class** box, enter the class detail.
22. In the **Status** box, enter the status of the visual test.
23. In the **Rev. Date** box, enter the revision date of the visual test.
24. In the **Contractor Document Number** box, enter the document number of the contractor.
25. In the **Equipment** box, enter the equipment name.
26. In the **Inspector/ Representative** box, enter the name of inspector/ representative.
27. In the **Detail Description/Tagging** box, enter the detail description.
28. In the **Remarks** box, enter your remarks if any.
29. Click **Save**.
    
    The final visual test report is successfully added.

#### **6.11.2 View Checklist Details**

If you want to view the check list details, do the following,

1. Click [![image-1652029207861.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029207861.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029207861.png) (Add icon) in the **Edit** column for the respective final visual test report in the **Final Visual Test**  See Fig 6.11. The **Check List Details** window opens.
    
    [![image-1652029227467.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029227467.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029227467.png)
    
    The **Check List Details** window shows a list of added check lists using the [<u>Check List</u>](#_Check_List) tab. This window also shows the results of check list whether accepted or not.

#### **6.11.3 Submit and Approve a Final Visual Test Report**

Once you have added the visual test report, the **Request Status** column in the **Final** **Visual Test** page is appeared with[![image-1652029276973.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029276973.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029276973.png)(Submit and Reject icons).

1. If you want to submit the visual test report, click [![image-1652029305930.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029305930.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029305930.png)(Submit icon) in the **Request Status** column. Otherwise click [![image-1652029319325.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029319325.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029319325.png) (Reject icon) to reject the request.
    
    Once you have submitted the visual test report, the **Completed Status** column in the **Final Visual Test** page is appeared with [![image-1652029334379.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652029334379.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652029334379.png)(Accept and Reject icons).
2. If you want to approve the visual test report, click [![image-1652034360649.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034360649.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034360649.png)(Submit icon) in the ****Completed Status**** Otherwise click [![image-1652034368986.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034368986.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034368986.png)(Reject icon) to reject the request.

#### **6.11.4 Print a Final Visual Checklist Report**

If you want to print a final visual checklist report, click[![image-1652034420278.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034420278.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034420278.png)(print icon) provided in the **Checklist** **Report** column of the **Final Visual Test** page. See Fig 6.11.

#### **6.11.5 Print a General Visual Checklist Report**

If you want to print a general visual checklist report, click [![image-1652034456172.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034456172.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034456172.png)(print icon) provided in the **General Report** column of the **Final Visual Test** page. See Fig 6.11.

#### **6.11.6 Print a Final Visual Test Report**

If you want to print a final visual test report, click[![image-1652034511305.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034511305.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034511305.png)(print icon) provided in the **Report** column of the **Final Visual Test** page. See Fig 6.11.

#### **6.11.7 Attach a File into a Final Visual Test Report**

If you want to attach any file with any final visual test report listed in the **Final Visual Test** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.11.8 Edit Any Final Visual Test Report**

If you want to edit any existing final visual test report in the **Final Visual Test** page, do the following,

1. Click [![image-1652034604746.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034604746.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034604746.png)(Edit icon) in the **Edit** column for the respective final visual test report. See Fig 6.11. A new window opens to edit the final visual test report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.11.9 Export Final Visual Test Report List**

You can export a list of final visual test reports added in the **Final Visual Test** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.11.10 Filter Any Final Visual Test Report**

If you want to filter any visual test report from the list of in the **Final Visual Test** page, you can use the (**FILTER** button). To know how to filter, see the topic, ”**Filter Any Area**”.


### **6.12 Machining Report**

The **Machining Report** tab in the **Structural** menu used to add a machining report once the machining process has completed. If you want to add a machining report, do the following,

1. Click the **Machining Report** Tab. The **Machining** page opens.
    
    [![image-1652034801414.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034801414.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034801414.png)
    
     **Figure 6.12: Machining page**

#### **6.12.1 Add a Machining Report**

If you want to add a machining report,

1. Click [![image-1652034863719.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034863719.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034863719.png) (**ADD** button) in the **Machining** page. See Fig 6.12. A new window opens to add a machining report.
    
    [![image-1652034883455.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034883455.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034883455.png)
    
    [![image-1652034896342.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034896342.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034896342.png) **Tip**: A report number for a new machining report will be updated automatically in the **Report Number** box.
2. In the **Remarks** box, enter your remarks if any.
3. Click **Save**.

The machining report is successfully added.

#### **6.12.2 Add Machining Report Details**

1. Click [![image-1652034965359.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034965359.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034965359.png)(Edit icon) in the **Edit Report** column of the **Machining** page. See Fig 6.12. The **Machining Report Details** window opens.
    
    [![image-1652034981315.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652034981315.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652034981315.png)
2. Click [![image-1652035004879.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035004879.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035004879.png) (**ADD** button) in the **Machining Report Details** window.
    
    A new window opens in the **Drawing No** column.
    
    [![image-1652035021483.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035021483.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035021483.png)
3. In the ****Drawing No**** column, select the drawing number from a drop-down list.
4. In the **Piece Mark No** column, click and select the piece mark number from a drop-down list.
5. In the **Description** column, click and enter the description.
6. In the **Material Grade** column, click and enter the material grade.
7. In the ****Hole Before Line Boring (mm)****column, enter the size of a hole made before line boring.
8. In the **Hole After Line Boring (mm)** column, enter the size of a hole made after line boring.
9. In the **Deviation** column, enter the deviation between holes.
10. In the **Inspection Date** column, select the inspection date.
11. In the **Remarks** column, enter your remarks if any.
12. Click **Save**.

The added machining report details will be updated.

#### **6.12.3 Submit and Approve a Machining Report**

Once you have added the machining report details, the **Submission** column in the **Machining** page is appeared with[![image-1652035192415.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035192415.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035192415.png) (Submit and Reject icons).

1. If you want to submit the machining report, click [![image-1652035161967.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035161967.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035161967.png) (Submit icon) in the **Submission** Otherwise click [![image-1652035182259.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035182259.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035182259.png)(Reject icon) to reject the request. Once you have submitted the machining report, the **Request Status** column in the **Machining** page is appeared with
    
    [![image-1652035259166.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035259166.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035259166.png)(Accept and Reject icons).
2. If you want to approve the machining report, click [![image-1652035273434.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035273434.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035273434.png)(Submit icon) in the **Request Status** column. Otherwise click
    
    [![image-1652035284857.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035284857.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035284857.png) (Reject icon) to reject the request.
3. If you have completed the machining report, click [![image-1652035313097.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035313097.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035313097.png)(Completed icon) in the **Completed** **Status** column. If incomplete, click [![image-1652035325959.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035325959.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035325959.png) (Incomplete icon).

#### **6.12.4 Print a Machining Report**

If you want to print a machining report, click[![image-1652035362855.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035362855.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035362855.png)(print icon) provided in the **Report** column of the **Machining** page. See Fig 6.12.

#### **6.12.5 Attach a File into a Machining Report**

If you want to attach any file with any machining report listed in the **Machining** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.12.6 Edit Any Machining Report**

If you want to edit any existing machining report in the **Machining** page, do the following,

1. Click [![image-1652035434175.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035434175.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035434175.png)(Edit icon) in the **Edit** column for the respective machining report. See Fig 6.12. A new window opens to edit the machining report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.12.7 Export Machining Report List**

You can export a list of machining reports added in the **Machining** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.12.8 Filter any machining report**

If you want to filter any machining report from the list in the **Machining** page, you can use the (**FILTER** button). To know how to filter, see the topic, ”**Filter Any Area**”.



### **6.13 Load Test Report**

The **Load Test Report** tab in the **Structural** menu used to add a load test report once the load test has completed. If you want to add a load test report, do the following,

1. Click the **Load Test Report** Tab. The **Load Test Report** page opens.
    
    [![image-1652035600195.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035600195.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035600195.png)
    
     **Figure 6.13: Load Test Report page**

#### **6.13.1 Add a Load Test Report**

If you want to add a load test report,

1. Click [![image-1652035688811.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035688811.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035688811.png) (**ADD** button) in the **Load Test Report** page. See Fig 6.13. A new window opens to add a load test report.
    
    [![image-1652035715846.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035715846.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035715846.png)
    
    [![image-1652035726023.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035726023.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035726023.png) **Tip**: A report number for a new load test report will be updated automatically in the **Report Number** box.
2. In the **Prepared By** box, enter the name a person who has prepared the load test report.
3. In the **Prepared Date** box, enter the prepared date of the load test report.
4. In the **Reviewed By** box, enter the name a person who has reviewed the load test report.
5. In the **Reviewed Date** box, enter the reviewed date of the load test report.
6. In the **Approved By** box, enter the name a person who has approved the load test report.
7. In the **Approved Date** box, enter the approved date of the load test report.
8. Click **Save**.

The load test report is successfully added. Once you have added the load test report, you must add the details for the added report.

#### **6.13.2 Add Load Test Report Details** 

1. Click [![image-1652035815704.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035815704.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035815704.png)(Edit icon) in the **Edit Report** column of the **Load Test Report**  See Fig 6.14. The **Load Test Parameters**, **Equipment Details**, and **Report Photos** windows open in the **Load Test Report** page.
    
    [![image-1652035839349.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035839349.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035839349.png)
2. If you want to add the load test parameters in the ****Load Test Parameters**** window, do the following, 
    1. 1. 1. In the **Load Test Pressure Required** box, enter the required range of load test pressure.
            2. In the **Test Load** box, enter the test load detail.
            3. In the **Test Duration** box, enter the load test time duration.
            4. In the **Pressure Gauge Reading** box, enter the pressure gauge reading value.
            5. In the **Hydraulic Jack System S/N** box, enter the hydraulic jack system detail.
            6. In the **Pull up Jack Capacity** box, enter the value of pull up jack capacity.
            7. In the **Document Procedure No** box, select the document procedure number from a drop-down list.
            8. In the **Description of Items** box, enter the item description.
            9. In the **Reference Drawing** box, enter the reference drawing detail.
            10. In the **Client Reference Drawing No** box, enter the client reference drawing number.
            11. In the **Load Test Pressure Requirement** box, enter the requirement for load test pressure.
            12. In the **Actual Pressure Requirement** box, enter the requirement for actual pressure.
            13. In the **Holding Time** box, enter the holding time duration.
            14. In the **Result** box, select the result from a drop-down list.
            15. Click **Save**.
3. If you want to add the equipment details in the ****Equipment Details**** window, do the following, 
    1. 1. 1. Click [![image-1652035992474.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652035992474.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652035992474.png) (****ADD**** button) in the ****Equipment Details**** window. A new window opens to add the equipment details.
                
                [![image-1652036038406.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036038406.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036038406.png)
            2. In the **Conducted By** box, select **Internal** if the load test is conducted internally or select **External** if the load test is conducted externally.
            3. In the **Equipment Details** box, select the equipment from a drop-down list.
            4. Click **Save**.
4. If you want to add the report photos in the **Report Photos** window, do the following, 
    1. 1. 1. Click [![image-1652036087252.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036087252.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036087252.png) (**ADD** button) in the **Report Photos** window.
                
                [![image-1652036081886.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036081886.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036081886.png)
            2. Click [![image-1652036107417.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036107417.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036107417.png) (**Browse** button) to browse a photo stored in your computer.
            3. Click **Upload**.
                
                The selected photo will be updated.

#### **6.13.3 Print a Load Test Report**

If you want to print a load test report, click [![image-1652036218554.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036218554.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036218554.png)(print icon) provided in the **Report** column of the **Load Test Report** page. See Fig 6.13.

[![image-1652036232278.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036232278.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036232278.png) **Tip**: If you want to lock any load test report, click the check box provided in the **Lock Report?** column of the **Load Test Report** page. See Fig 6.13.

#### **6.13.4 Attach a File into a Load Test Report**

If you want to attach any file with any load test report listed in the **Load Test Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](#_Attach_a_file)” in the **Client Master Drawing** section.

#### **6.13.5 Edit Any Load Test Report**

If you want to edit any existing load test report in the **Load Test Report** page, do the following,

1. Click [![image-1652036689318.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036689318.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036689318.png)(Edit icon) in the **Edit** column for the respective load test report. See Fig 6.13. A new window opens to edit the load test report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **6.13.6 Export Load Test Report List**

You can export a list of load test reports added in the **Load Test Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](#_Export_areas_list)” in the **Area** option.

### **6.14 Survey Booking**

Survey Booking is an enhanced survey booking process, which helps the surveyors to manage their survey requirements more efficiently with respect to time and scope.

The **Survey Booking** tab in the **Structural** menu helps in adding a survey booking once the survey booking process has completed.

If you want to add a survey booking, do the following,

1. Click the **Survey Booking** Tab. The **Survey Booking** page opens.
    
    [![image-1652036984277.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652036984277.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652036984277.png)
    
     **Figure 6.14: Survey Booking page**

#### **6.14.1 Add a Survey Booking**

If you want to add a survey booking,

1. Click [![image-1652037090632.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652037090632.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652037090632.png) (**ADD** button) in the **Survey Booking** page. See Fig 6.15. A new window opens to add a survey booking.
    
    [![image-1652037226578.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652037226578.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652037226578.png)
2. In the **Surveyor** box, enter the name of a surveyor.
3. In the ****Survey Date**** box, select the survey date from a drop-down list.
4. In the **Authority** box, enter the name of authority person.
5. In the **Client Rep** box, enter the name of the client representative.
6. In the **Location** box, enter the location where the survey to be performed.
7. Click **Save**.

The survey booking is successfully added.

#### **6.14.2 Add Survey Booking Details**

1. Click [![image-1652037653290.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652037653290.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652037653290.png) (Edit icon) in the **Edit Report** column of the **Survey Booking**  See Fig 6.14. The **Survey Booking Details** window opens.
    
    [![image-1652037676250.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652037676250.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652037676250.png)
2. Click [![image-1652037732440.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652037732440.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652037732440.png) (**ADD** button) in the **Survey Booking Details** window.
    
    A new window opens to add the survey booking details.
    
    [![image-1652037763898.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652037763898.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652037763898.png)
3. In the **Time** box, select the survey time.
4. In the **Description** box, enter the description for the survey booking.
5. In the ****Trade**** box, enter the trade detail.
6. In the ****Type**** box, enter the type of survey.
7. In the ****QC Code**** box, enter the QC code.
8. In the ****Location**** box, enter the location where the survey is to be performed.
9. In the ****Drawing No**** box, select the drawing number from a drop-down list.
10. In the ****For CTR**** box, enter the CTR detail.
11. In the ****For RG/ CA**** box, enter the RG/ CA detail.
12. In the ****Requested By**** box, enter the name of a person who has requested for the survey booking.
13. In the ****For CPY**** box, enter the CPY detail.
14. In the **Sub Contractor** box, select the sub-contractor name from a drop-down list.
15. In the **Remarks** column, enter your remarks if any.
16. Click **Save**.

The survey booking details will be updated.

#### **6.14.3 Print a Survey Booking Report**

If you want to print a survey booking report, click [![image-1652038207770.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038207770.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038207770.png)(print icon) provided in the **Report** column of the **Survey Booking** page. See Fig 6.14.

#### **6.14.4 Attach a File into a Survey Booking**

If you want to attach any file with any survey booking listed in the **Survey Booking** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](#_Attach_a_file)” in the **Client Master Drawing** section.

#### **6.14.5 Edit Any Survey Booking**

If you want to edit any existing survey booking in the **Survey Booking** page, do the following,

1. Click [![image-1652038274986.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038274986.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038274986.png) (Edit icon) in the **Edit** column for the respective survey booking. See Fig 6.14. A new window opens to edit the survey booking.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.14.6 Export Survey Booking List**

You can export a list of survey booking added in the **Survey Booking** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](#_Export_areas_list)” in the **Area** option.

#### **6.14.7 Filter Any Survey Booking**

If you want to filter any survey booking from the list in the **Survey Booking** page, you can use the [![image-1652038364954.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038364954.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038364954.png) (**FILTER** button). To know how to filter, see the topic, ”**Filter Any Area**”.


### **6.15 Dimensional Control Report**

Dimensional control used to determine part-to-part variation and clearance between two parts of material. By applying Dimensional Control, accurate three-dimensional information can be determined and mapped at various stages throughout the Structural project.

The **Dimensional Control Report** tab in the **Structural** menu used to add a dimensional control report once the dimensional control has completed. If you want to add a dimensional control report, do the following,

1. Click the **Dimensional Control Report** Tab. The **Dimensional Control Report** page opens.
    
    [![image-1652038426047.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038426047.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038426047.png)
    
     **Figure 6.15: Dimensional Control Report page**

#### **6.15.1 Add a dimensional control report**

If you want to add a dimensional control report,

1. Click [![image-1652038481610.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038481610.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038481610.png) (**ADD** button) in the **Dimensional Control Report**  See Fig 6.15. A new window opens to add a dimensional control report.
    
    [![image-1652038499123.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038499123.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038499123.png)
    
    [![image-1652038517464.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038517464.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038517464.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652038529623.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038529623.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038529623.png) **Tip**: A report number for a new dimensional control report will be updated automatically in the **Report Number** box.
2. In the **Drawing** box, select the drawing from a drop-down list.
3. In the **Prepared By** box, enter the name a person who has prepared the dimensional control report.
4. In the **Prepared Date** box, enter the prepared date of the dimensional control report.
5. In the **Reviewed By** box, enter the name a person who has reviewed the dimensional control report.
6. In the **Reviewed Date** box, enter the reviewed date of the dimensional control report.
7. In the **Approved By** box, enter the name a person who has approved the dimensional control report.
8. In the **Approved Date** box, enter the approved date of the dimensional control report.
9. Click **Save**.

The dimensional control report is successfully added. Once you have added the dimensional control report, you must add the details for the added dimensional control report.

#### **6.15.2 Add Dimensional Control Report Details** 

1. Click [![image-1652038626257.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038626257.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038626257.png) (Edit icon) in the **Edit Report** column of the **Dimensional Control Report**  See Fig 6.15. The **<u>D</u>imensional Control Parameters**, **<u>D</u>imensional Control Details**, and **Report Photos** windows open in the **<u>D</u>imensional Control Report** page.
    
    [![image-1652038646861.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038646861.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038646861.png)
    
    [![image-1652038661379.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038661379.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038661379.png)
    
    [![image-1652038672058.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038672058.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038672058.png) **Tip**: If you want to add any notes for dimensional control report, you can add in the **Notes** window provided in the **<u>D</u>imensional Control Report** page.
2. If you want to add the dimensional control parameters in the ****D****imensional Control Parameters**** window, do the following, 
    1. 1. 1. In the **Date of Survey** box, enter the survey date.
            2. In the **Time** box, enter the survey time.
            3. In the **Weather** box, enter the weather details.
            4. In the **Temp C** box, enter the temperature control value.
            5. In the ****Location**** box, enter the location where the dimensional control is to be performed
            6. In the **Instrument** box, select the instrument from a drop-down list.
            7. In the **Description** box, enter the description for dimensional control.
            8. In the **Status** box, enter the status for dimensional control.
            9. Click **Save**.
3. If you want to add the dimensional control details in the **Dimensional Control Details** window, do the following,
    
    
    1. 1. 1. Click [![image-1652038799188.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038799188.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038799188.png) (****ADD**** button) in the ****Dimensional Control Details**** window. Boxes opens in the respective columns to add the dimensional control details.
                
                [![image-1652038880049.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038880049.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038880049.png)
                
                [![image-1652038915645.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038915645.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038915645.png) **Tip**: You can add multiple dimensional control result details by using the **ADD** button. If you want to order the added details, use the up and down symbols in the **Order By** column.
            2. In the **Symbol/ Description** column, enter the symbol or description for the dimensional control.
            3. In the **Drawing** column, enter the drawing detail.
            4. In the **Tolerance** column, enter the tolerance value.
            5. In the **Actual** column, enter the actual value.
            6. In the **Result** column, enter the result for the dimensional control.
            7. In the **Remarks** column, enter your remarks if any.
            8. Click **Save Changes**.
4. If you want to add the report photos in the ****Report Photos**** window, do the following, 
    1. 1. 1. Click [![image-1652038993773.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652038993773.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652038993773.png) (**ADD** button) in the **Report Photos** window.
                
                [![image-1652039009541.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039009541.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039009541.png)
            2. Click [![image-1652039023301.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039023301.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039023301.png) (**Browse** button) to browse a photo stored in your computer.
            3. Click **Upload**.
                
                The selected photo will be updated.

#### **6.15.3 Print a Dimensional Control Report**

If you want to print a dimensional control report, click [![image-1652039097349.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039097349.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039097349.png)(print icon) provided in the **Report** column of the **Dimensional Control** **Report** page. See Fig 6.15.

#### **6.15.4 Attach a File into a Dimensional Control Report**

If you want to attach any file with any dimensional control report listed in the **Dimensional Control** **Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.15.5 Edit Any Dimensional Control Report**

If you want to edit any existing dimensional control report in the **Dimensional Control** **Report** page, do the following,

1. Click [![image-1652039222474.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039222474.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039222474.png)(Edit icon) in the **Edit** column for the respective dimensional control report. See Fig 6.15. A new window opens to edit the dimensional control report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.15.6 Export Dimensional Control Report List**

You can export a list of dimensional control reports added in the **Dimensional Control** **Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.


### **6.16 Trail Fit Report**

Trail Fit report prepared to send the trail fit-up photos once the trail fit-up has completed. The **Trail Fit Report** tab in the **Structural** menu used to add a trail fit report. If you want to add a trail fit report, do the following,

1. Click **Trail Fit Report** in the **Structural** menu. The **Trail Fit Report** page opens. [![image-1652039316791.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039316791.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039316791.png)
    
     **Figure 6.16: Trail Fit Report page**

#### **6.16.1 Add a Trail Fit Report**

If you want to add a trail fit report,

1. Click [![image-1652039377787.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039377787.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039377787.png) (**ADD** button) in the **Trail Fit Report** page. See Fig 6.16. A new window opens to add a trail fit report.
    
    [![image-1652039414571.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039414571.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039414571.png)
    
    [![image-1652039430813.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039430813.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039430813.png) **Tip**: A report number for a new trail fit report will be updated automatically in the **Report Number** box.
2. In the ****Prepared By**** box, enter the name a person who has prepared the trail fit report.
3. In the **Prepared Date** box, enter the prepared date of the trail fit report.
4. In the **Reviewed By** box, enter the name a person who has reviewed the trail fit report.
5. In the **Reviewed Date** box, enter the reviewed date of the trail fit report.
6. In the **Approved By** box, enter the name a person who has approved the trail fit report.
7. In the **Approved Date** box, enter the approved date of the trail fit report.
8. Click **Save**.

The trail fit report is successfully added. Once you have added the trail fit report, you must add the trail fit details for the added trail fit report.

#### **6.16.2 Add Trail Fit Report Details** 

1. Click [![image-1652039531457.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039531457.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039531457.png) (Edit icon) in the **Edit Report** column of the **Trail Fit** **Report**  See Fig 6.16. The **Report Photos** window opens in the **Trail Fit** **Report** page.
    
    [![image-1652039547712.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039547712.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039547712.png)
    
    [![image-1652039569533.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039569533.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039569533.png) **Tip**: If you want to add any remarks for trail fit report, you can add in the **Remarks** window provided in the **Trail Fit** **Report** page.
2. If you want to add the report photos in the **Report Photos** window, do the following,
    
    
    1. 1. Click [![image-1652039599062.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039599062.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039599062.png) (**ADD** button) in the **Report Photos** window.
            
            [![image-1652039609077.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039609077.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039609077.png)
        2. Click [![image-1652039632753.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039632753.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039632753.png) (**Browse** button) to browse a photo stored in your computer.
        3. Click **Upload**.
            
            The selected photo will be updated.

#### **6.16.3 Print a Trail Fit Report**

If you want to print a trail fit report, click [![image-1652039696442.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039696442.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039696442.png) (print icon) provided in the **Report** column of the **Trail Fit** **Report** page. See Fig 6.16.

[![image-1652039751225.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039751225.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039751225.png) **Tip**: If you want to lock any trail fit report, click the check box provided in the **Lock Report?** column of the **Trail Fit Report** page. See Fig 6.16.

#### **6.16.4 Attach a File into a Trail Fit Report**

If you want to attach any file with any trail fit report listed in the **Trail Fit Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.16.5 Edit Any Trail Fit Report**

If you want to edit any existing trail fit report in the **Trial Fit Report** page, do the following,

1. Click [![image-1652039899804.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652039899804.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652039899804.png)(Edit icon) in the **Edit** column for the respective trail fit report. See Fig 3.16. A new window opens to edit the trail fit report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.16.6 Export Trail Fit Report List**

You can export a list of trail fit reports added in the **Trail Fit Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.


### **6.17 Heat Straightening Report**

Heat straightening is a repair procedure in which controlled heat is applied in specific patterns to the plastically deformed regions of damaged material in repetitive heating and cooling cycles to gradually straighten the material.

The **Heat Straightening Report** tab in the **Structural** menu used to add a heat straightening report once the heat straightening process has completed. If you want to add a heat straightening report, do the following,

1. Click the **Heat Straightening Report** Tab. The **Heat Straightening Report** page opens.
    
    [![image-1652040040963.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040040963.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040040963.png)
    
     **Figure 6.17: Heat Straightening Report page**

#### **6.17.1 Add a Heat Straightening Report**

If you want to add a heat straightening report,

1. Click [![image-1652040202665.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040202665.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040202665.png) (**ADD** button) in the **Heat Straightening Report**  See Fig 6.17. A new window opens to add a heat straightening report.
    
    [![image-1652040215343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040215343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040215343.png)
    
    [![image-1652040226440.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040226440.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040226440.png) **Tip**: A report number for a new heat straightening report will be updated automatically in the **Report Number** box.
2. In the **Description** box, enter the description for the heat straightening report.
3. In the **Description** box, enter the description for the heat straightening report.
4. In the **Prepared Date** box, enter the prepared date of the heat straightening report.
5. In the **Prepared Date** box, enter the prepared date of the heat straightening report.
6. In the **Reviewed Date** box, enter the reviewed date of the heat straightening report.
7. In the **Approved By** box, enter the name a person who has approved the heat straightening report.
8. In the ****Approved Date**** box, enter the approved date of the heat straightening
9. Click **Save**.

The heat straightening report is successfully added. Once you have added the heat straightening report, you must add the heat straightening details for the added report.

#### **6.17.2 Add Heat Straightening Details** 

1. Click [![image-1652040473971.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040473971.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040473971.png)(Edit icon) in the **Edit Report** column of the **Heat Straightening Report** page. See Fig 6.17. The **Report Parameters** and **Report Photos** windows open in the **Heat Straightening Report** page.
    
    [![image-1652040495655.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040495655.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040495655.png)
2. If you want to add the report parameters in the **Report Parameters** window, do the following, 
    1. 1. Click [![image-1652040588764.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040588764.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040588764.png) (**ADD** button) in the **Report Parameters** window.
        2. In the **Description** box, enter the description for heat straightening.
        3. In the **Size** box, enter the thickness of the material.
        4. In the **Start** **Time** box, enter the start time of heat straightening.
        5. In the **End Time** box, enter the end time of heat straightening.
        6. In the **Temperature** box, enter the temperature range for heat straightening.
        7. In the **Length** box, enter the length of material to do heat straightening.
        8. In the **Heating Speed** box, enter the heating speed of heat straightening.
        9. In the **Cycle** box, enter the detail of heat straightening cycle.
        10. In the **Remarks** box, enter your remarks if any.
        11. Click **Save**.
3. If you want to add the report photos in the **Report Photos** window, do the following,
    
    
    1. 1. Click [![image-1652040633894.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040633894.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040633894.png) (**ADD** button) in the **Report Photos** window.
            
            [![image-1652040643621.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040643621.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040643621.png)
        2. Click [![image-1652040661294.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040661294.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040661294.png) (**Browse** button) to browse a photo stored in your computer.
        3. Click **Upload**.
            
            The selected photo will be updated.

#### **6.17.3 Print a Heat Straightening Report**

If you want to print a heat straightening report, click[![image-1652040740042.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040740042.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040740042.png)(print icon) provided in the **Report** column of the **Heat Straightening Report** page. See Fig 6.17.

#### **6.17.4 Attach a File into a Heat Straightening Report**

If you want to attach any file with any heat straightening report listed in the **Heat Straightening Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

### **6.17.5 Edit Any Heat Straightening Report**

If you want to edit any existing heat straightening report in the **Heat Straightening Report** page, do the following,

1. Click [![image-1652040830944.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040830944.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040830944.png) (Edit icon) in the **Edit** column for the respective heat straightening report. See Fig 6.17. A new window opens to edit the heat straightening report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.17.6 Export Heat Straightening Report List 

You can export a list of heat straightening reports added in the **Heat Straightening Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.


### **6.18 Inspection Release Note**

Inspection Release Note is a written announcement which is issued by QC contractor to denote the successful completion of the inspection.

The **Inspection Release Note** tab in the **Structural** menu used to add an inspection release note after completion of the inspection. If you want to add an inspection release note, do the following,

1. Click the **Inspection Release Note** Tab. The **Release Form** page opens.
    
    [![image-1652040963563.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652040963563.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652040963563.png)
    
     **Figure 6.18: Release Form page**

#### **6.18.1 Add an Inspection Release Note**

If you want to add an inspection release note,

1. Click [![image-1652041151175.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041151175.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041151175.png) (**ADD** button) in the **Release Form** page. See Fig 6.18. A new window opens to add an inspection release note.
    
    [![image-1652041167463.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041167463.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041167463.png)
    
    [![image-1652041183324.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041183324.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041183324.png) **Tip**: A report number for a new inspection release note will be updated automatically in the **Report Number** box.
2. In the **Activity** box, select the activity from a drop-down list.
3. In the **Prepared By** box, enter the name a person who has prepared the inspection release note.
4. In the **Prepared Date** box, enter the prepared date of the inspection release note.
5. In the **Reviewed By** box, enter the name a person who has reviewed the inspection release note.
6. In the **Reviewed Date** box, enter the reviewed date of the inspection release note.
7. In the **Approved By** box, enter the name a person who has approved the inspection release note.
8. In the ****Approved Date**** box, enter the approved date of the inspection release note.
9. Click **Save**.

The inspection release note is successfully added. Once you have added the inspection release note, you must add the details for the added note.

#### **6.18.2 Add Inspection Release Note Details** 

1. Click [![image-1652041374618.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041374618.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041374618.png)(Edit icon) in the **Edit Report** column of the **Release Form**  See Fig 6.18. The **Release Form Parameters**, **Details**, and **Report Photos** windows open in the **Release Form** page.
    
    [![image-1652041408835.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041408835.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041408835.png)
2. If you want to add the release form parameters in the ****Release Form Parameters**** window, do the following, 
    1. 1. In the **Test Package No** box, enter the test package number.
        2. In the **Tag ID** box, enter the tag ID number.
        3. In the **Activity** box, enter the activity detail.
        4. In the ****Comments**** box, enter any comments relevant to the inspection release note.
        5. Click **Save**.
3. If you want to add the release note details in the ****Details**** window, do the following, 
    1. 1. Click [![image-1652041487140.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041487140.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041487140.png) (**ADD** button) in the **Details** window.
            
            A new window opens to add the release note details.
            
            [![image-1652041519404.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041519404.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041519404.png)
        2. In the **Description** box, enter the description for the inspection release note.
        3. If the company’s QC contractor issues the inspection release note, select the check box provided with the **QC Contractor/ Company** and select the date in the respective **Date** box.
        4. If the company’s QC contractor issues the inspection release note, select the check box provided with the **QC Contractor/ Company** and select the date in the respective **Date** box.
        5. Click **Save**.
4. If you want to add the report photos in the ****Report Photos**** window, do the following, 
    1. 1. Click [![image-1652041617005.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041617005.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041617005.png) (**ADD** button) in the **Report Photos** window.
            
            [![image-1652041643105.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041643105.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041643105.png)
        2. Click [![image-1652041659019.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041659019.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041659019.png) (****Browse**** button) to browse a photo stored in your computer.
        3. Click **Upload.**

The selected photo will be updated.

#### **6.18.3 Print an Inspection Release Form Report**

If you want to print an inspection release form report, click [![image-1652041726928.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041726928.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041726928.png)(print icon) provided in the **Report** column of the **Release Form** page. See Fig 6.18.

[![image-1652041741059.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041741059.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041741059.png) **Tip**: If you want to lock any inspection release note, click the check box provided in the **Lock Report?** column of the **Release Form** page. See Fig 6.18.

#### **6.18.4 Attach a File into an Inspection Release Note**

If you want to attach any file with any inspection release note listed in the **Release Form** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.18.5 Edit Any Inspection Release Note**

If you want to edit any existing inspection release note in the **Release Form** page, do the following,

1. Click [![image-1652041888095.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652041888095.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652041888095.png) (Edit icon) in the **Edit** column for the respective inspection release note. See Fig 6.18. A new window opens to edit the inspection release note.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.18.6 Export Inspection Release Note List**

You can export a list of inspection release notes added in the **Release Form** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.19 Shell Plate Rolling Report**

Shell Plate Rolling is a process of rolling different kinds of metal plates into a round or conical shape by using a plate rolling machine in the Structural project.

The **Shell Plate Rolling Report** tab in the **Structural** menu used to add a shell plate rolling report once the shell plate rolling process has completed. If you want to add a shell plate rolling report, do the following,

1. Click the **Shell Plate Rolling Report** Tab. The **Shell Plate Rolling Report page opens.
    
    [![image-1652042003752.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042003752.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042003752.png)
    
     **Figure 6.19: Shell Plate Rolling Report page.**

#### **6.19.1 Add a Shell Plate Rolling Report**

If you want to add a shell plate rolling report,

1. Click [![image-1652042137837.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042137837.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042137837.png) (**ADD** button) in the **Shell Plate Rolling** **Report**  See Fig 6.19. A new window opens to add a shell plate rolling report.
    
    [![image-1652042165785.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042165785.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042165785.png)
    
    [![image-1652042180519.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042180519.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042180519.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652042209049.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042209049.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042209049.png) **Tip**: A report number for a new shell plate rolling report will be updated automatically in the **Report Number** box.
2. In the **Drawing** box, select the drawing from a drop-down list.
3. In the **Prepared By** box, enter the name a person who has prepared the shell plate rolling report.
4. In the **Prepared Date** box, enter the prepared date of the shell plate rolling report.
5. In the **Prepared Date** box, enter the prepared date of the shell plate rolling report.
6. In the **Reviewed By** box, enter the name a person who has reviewed the shell plate rolling report.
7. In the ****Reviewed Date**** box, enter the reviewed date of the shell plate rolling report.
8. In the ****Approved By**** box, enter the name a person who has approved the shell plate rolling report.
9. In the **Approved Date** box, enter the approved date of the shell plate rolling report.
10. Click **Save**.

The shell plate rolling report is successfully added. Once you have added the shell plate rolling report, you must add the details for the added report.

#### **6.19.2 Add Shell Plate Rolling Report Details** 

1. Click [![image-1652042478858.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042478858.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042478858.png)(Edit icon) in the **Edit Report** column of the **Shell Plate Rolling Report** page. See Fig 6.19. The **Shell Plate Rolling** **Details** and **Report Photos** windows open in the **Shell Plate Rolling** **Report** page.
    
    [![image-1652042500387.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042500387.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042500387.png)
    
    [![image-1652042516881.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042516881.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042516881.png)**Tip**: If you want to add any notes for the shell plate rolling report, you can add in the **Notes** window provided in the **Shell Plate Rolling** **Report** page.
2. If you want to add the shell plate rolling details in the ****Shell Plate Rolling Details**** window, do the following, 
    1. 1. 1. Click [![image-1652042564607.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042564607.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042564607.png) (****ADD**** button) in the ******Shell Plate Rolling Details window.******Boxes opens in the respective columns to add the shell plate rolling details.
                
                [![image-1652042590993.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042590993.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042590993.png)
            2. In the **PLATE HEAT NO** column, enter the heat number of the plate.
            3. In the **DATE** column, select the date when the shell plate rolling process is performed.
            4. In the **(S)** **EXTREME CURVATURE** column, enter the extreme curvature value for the respective **A SIDE** and **B SIDE** of the rolling plate.
            5. In the **(R)** **CURVATURE** column, enter the radius curvature value of the rolling plate.
            6. In the **LENGTH** column, enter the length of **C SIDE** and **D SIDE** of the rolling plate.
            7. In the **EDGE- PREPARATION** column, enter the root and angle values for **A, B, C,** and **D** **SIDES**, respectively.
            8. Click **Save Changes**.
3. If you want to add the report photos in the **Report Photos** window, do the following,
    
    
    1. 1. 1. Click [![image-1652042689944.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042689944.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042689944.png) (**ADD** button) in the **Report Photos** window.
                
                [![image-1652042706147.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042706147.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042706147.png)
            2. Click (****Browse**** button) to browse a photo stored in your computer.
            3. Click **Upload.**
                
                The selected photo will be updated.

#### **6.19.3 Print a Shell Plate Rolling Report**

If you want to print a shell plate rolling report, click[![image-1652042776179.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042776179.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042776179.png)(print icon) provided in the **Report** column of the **Shell Plate Rolling** **Report** page. See Fig 6.19.

#### **6.19.4 Attach a File into a Shell Plate Rolling Report**

If you want to attach any file with any shell plate rolling report listed in the **Shell Plate Rolling** **Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.19.5 Edit Any Shell Plate Rolling Report**

If you want to edit any existing shell plate rolling report in the **Shell Plate Rolling** **Report** page, do the following,

1. Click [![image-1652042866288.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652042866288.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652042866288.png) (Edit icon) in the **Edit** column for the respective shell plate rolling report. See Fig 6.19. A new window opens to edit the shell plate rolling report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.19.6 Export Shell Plate Rolling Report List**

You can export a list of shell plate rolling reports added in the **Shell Plate Rolling** **Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.



### **6.20 Deviation Request Report**

Deviation Report used to find out any deviations in the materials utilized in the Structural project. The **Deviation Request Report** tab in the **Structural** menu helps you to add a deviation request report.

If you want to add a deviation request report, do the following,

1. Click the **Deviation Request Report** Tab. The **Deviation Request Report page opens.
    
    [![image-1652043019256.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043019256.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043019256.png)
    
     **Figure 6.20: Deviation Request Report page**

#### **6.20.1 Add a Deviation Request Report** 

If you want to add a deviation request report,

1. Click [![image-1652043095016.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043095016.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043095016.png) (**ADD** button) in the **Deviation Request Report  See Fig 6.20. A new window opens to add a deviation request report.
    
    [![image-1652043111365.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043111365.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043111365.png)
    
    [![image-1652043125157.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043125157.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043125157.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652043138881.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043138881.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043138881.png) **Tip**: A report number for a new deviation request report will be updated automatically in the **Report Number** box.
2. In the **Inspection Date** box, select the inspection date of the deviation request report.
3. In the ****Prepared By**** box, enter the name a person who has prepared the deviation request report.
4. In the **Prepared Date** box, enter the prepared date of the deviation request report.
5. In the ****Reviewed By**** box, enter the name a person who has reviewed the deviation request report.
6. In the **Reviewed Date** box, enter the reviewed date of the deviation request report.
7. In the **Reviewed Date** box, enter the reviewed date of the deviation request report.
8. In the **Approved Date** box, enter the approved date of the deviation request report.
9. Click **Save**.

The deviation request report is successfully added. Once you have added the deviation request report, you must add the details for the added deviation request.

[![image-1652043228212.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043228212.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043228212.png)**Tip**: If you want to add a copy of added deviation request report, click **Revision** in the **Revision** column of the **Deviation Request Report** page.

#### **6.20.2 Add Deviation Request Details** 

1. Click [![image-1652043298916.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043298916.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043298916.png)(Edit icon) in the **Edit Report** column of the **Deviation Request Report  See Fig 6.20. The **Material Clarification, Ref. Documents, Query Description, Attachments, Proposed Solutions,** and **Technip Response** windows open in the **Deviation Request Report** page.
    
    [![image-1652043333938.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043333938.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043333938.png)
    
    [![image-1652043347497.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043347497.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043347497.png)
    
    [![image-1652043360441.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043360441.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043360441.png)
    
    [![image-1652043369867.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043369867.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043369867.png)
2. To add the material clarification details, do the following,
    
    
    1. 1. 1. In the ****From**** and ****To**** boxes, enter details of deviation occurred up to which material.
            2. In the ****Impact**** box, if the deviation leads to the cost impact then select ****Cost Impact**** or if the deviation leads to the schedule impact then select ****Schedule Impact****.
            3. In the ****Criticality**** box, if there is need to correct the deviation in the materials immediately then select ****Urgent**** otherwise select ****Routine**** based on the deviation criticality.
            4. In the **Classification** box, if the classification of deviation is mandatory then select **Mandatory** otherwise select **Non- Mandatory**.
            5. In the ****Requirements**** box, if you need clarification for the deviations occurred then select ****Clarification**** otherwise select ****Change to Project Requirement****.
            6. Click **Save**.
3. To add reference documents of the material deviations,
    
    
    1. 1. 1. Click [![image-1652043488794.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043488794.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043488794.png) (****ADD**** button) in the  ****Documents**** window. A new window opens in the **Technip Document No** column to add the reference document number.
            2. Enter the revision detail for the reference document number in the ****Revision**** column.
            3. Enter the vendor document number in the **Vendor Document No** column.
            4. Enter the revision detail for the vendor document number in the **Revision** column.
            5. Click **Save Changes**.
4. If you want to add query description, you can add in the **Query Description** window.
5. To add any attachment for the deviation request report,
    
    
    1. 1. 1. Click [![image-1652043596005.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043596005.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043596005.png) (**ADD** button) in the **Attachments** window.
                
                A new window opens in the **Document No** column to add the number of a document to be attached.
            2. Enter the revision detail for the document number in the **Revision** column.
            3. Enter the title of the document in the **Title** column.
            4. Click **Save Changes**.
6. If you want to add the proposed solution details for the material deviation, you can add in the **Proposed Solutions** window.
7. If you want to add the proposed solution details for the material deviation, you can add in the **Proposed Solutions** window.

#### **6.20.3 Print a Deviation Request Report**

If you want to print a deviation request report, click[![image-1652043691026.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043691026.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043691026.png) (print icon) provided in the **Report** column of the **Deviation Request Report** page. See Fig 6.20.

#### **6.20.4 Attach a File into a Deviation Request Report**

If you want to attach any file with any deviation request report listed in the **Deviation Request Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.20.5 Edit Any Deviation Request Report**

If you want to edit any existing deviation request report in the **Deviation Request Report** page, do the following,

1. Click [![image-1652043784079.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043784079.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043784079.png)(Edit icon) in the **Edit** column for the respective deviation request report. See Fig 6.20. A new window opens to edit the deviation request report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.20.6 Export Deviation Request Report List**

You can export a list of deviation request reports added in the **Deviation Request** **Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.


### **6.21 Technical Query Report**

Technical query usually raised to get clarification on technical fault, which is occurred in the execution of the Structural project. The Technical query can be raised between site operations of the contractor and engineering team of the contractor.

The **Technical Query Report** tab in the **Structural** menu used to add a technical query report. If you want to add a technical query report, do the following,

1. Click the **Technical Query Report** Tab. The **Technical Query Report page opens.
    
    [![image-1652043929311.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652043929311.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652043929311.png)
    
     **Figure 6.21: Technical Query Report page**

#### **6.21.1 Add a Technical Query Report** 

If you want to add a technical query report,

1. Click [![image-1652044006507.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044006507.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044006507.png) (**ADD** button) in the **Technical Query Report page. See Fig 6.21. A new window opens to add a technical query report.
    
    [![image-1652044027139.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044027139.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044027139.png)
    
    [![image-1652044040343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044040343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044040343.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving. [![image-1652044196130.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044196130.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044196130.png)**Tip**: A report number for a new technical query report will be updated automatically in the **Report Number** box.
2. In the **Inspection Date** box, select the inspection date of the technical query report.
3. In the **Prepared By** box, enter the name a person who has prepared the technical query report.
4. In the ****Prepared Date**** box, enter the prepared date of the technical query report.
5. In the ****Reviewed By**** box, enter the name a person who has reviewed the technical query report.
6. In the ****Reviewed Date**** box, enter the reviewed date of the technical query report.
7. In the **Approved By** box, enter the name a person who has approved the technical query report.
8. In the ****Approved Date**** box, enter the approved date of the deviation request report.
9. Click ****Save.****

The technical query report is successfully added. Once you have added the technical query report, you must add the details for the added report.

[![image-1652044315613.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044315613.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044315613.png)**Tip**: If you want to add a copy of added technical query report, click **Revision** in the **Revision** column of the **Technical Query** **Report** page.

#### **6.21.2 Add Technical Query Report Details** 

1. Click [![image-1652044403145.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044403145.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044403145.png)(Edit icon) in the **Edit Report** column of the **Technical Query** **Report** See Fig 6.21. The **Material Clarification, Ref. Documents, Query Description, Attachments, Proposed Solutions,** and **Technip Response** windows open in the **Technical Query** **Report** page.
    
    [![image-1652044447645.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044447645.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044447645.png)[![image-1652044460024.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044460024.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044460024.png)
    
    [![image-1652044493495.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044493495.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044493495.png)
2. To add the material clarification details, do the following,
    
    
    1. 1. 1. In the **From** and **To** boxes, enter details of technical fault.
            2. In the ****Impact**** box, if the technical fault leads to the cost impact then select ****Cost Impact**** or if the technical fault leads to the schedule impact then select ****Schedule Impact****.
            3. In the ****Impact**** box, if the technical fault leads to the cost impact then select ****Cost Impact**** or if the technical fault leads to the schedule impact then select ****Schedule Impact****.
            4. In the ****Criticality**** box, if there is need to correct the technical fault immediately then select ****Urgent**** otherwise select ****Routine**** based on the technical fault criticality.
            5. In the ****Classification**** box, if the classification of technical fault is mandatory then select ****Mandatory**** otherwise select ****Non- Mandatory****.
            6. In the ****Requirements**** box, if you need clarification for the technical fault occurred then select ****Clarification**** otherwise select ****Change to Project Requirement****.
            7. Click **Save**.
3. To add reference documents of the technical fault,
    
    
    1. 1. 1. Click [![image-1652044678729.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044678729.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044678729.png) (**ADD** button) in the **Ref. Documents** window.
                
                A new window opens in the **Technip Document No** column to add the reference document number.
            2. Enter the revision detail for the reference document number in the **Revision** column.
            3. Enter the vendor document number in the **Vendor Document No** column.
            4. Enter the revision detail for the vendor document number in the **Revision** column.
            5. Click **Save Changes**.
4. If you want to add query description for technical fault, you can add in the ****Query Description**** window.
5. To add any attachment for the technical query report,
    
    
    1. 1. Click [![image-1652044785199.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044785199.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044785199.png) (**ADD** button) in the **Attachments** window.
            
            A new window opens in the **Document No** column to add the number of a document to be attached.
        2. Enter the revision detail for the document number in the **Revision** column.
        3. Enter the title of the document in the **Title** column.
        4. Click **Save Changes**.
6. If you want to add the proposed solution details for the technical fault, you can add in the **Proposed Solutions** window.
7. If you want to add the Technip response for the technical fault, you can add in the **Technip Response** window.

#### **6.21.3 Print a Technical Query Report**

If you want to print a technical query report, click[![image-1652044903649.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652044903649.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652044903649.png) (print icon) provided in the **Report** column of the **Technical Query** **Report** page. See Fig 6.22.

#### **6.21.4 Attach a File into a Technical Query Report**

If you want to attach any file with any technical query report listed in the **Technical Query Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.21.5 Edit Any Technical Query Report**

If you want to edit any existing technical query report in the **Technical Query Report** page, do the following,

1. Click [![image-1652045036774.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045036774.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045036774.png) (Edit icon) in the **Edit** column for the respective technical query report. See Fig 6.21. A new window opens to edit the technical query report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.21.6 Export Technical Query Report List**

You can export a list of technical query reports added in the Technical Query Report page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.



### **6.22 Electrical Continuity Report**

Electrical continuity test is a technique to check and verify the current flow in the metal paths. The **Electrical Continuity Report** tab in the **Structural** menu used to add an electrical continuity report after the completion of electrical continuity test.

If you want to add an electrical continuity report, do the following,

1. Click the **Electrical Continuity Report** Tab. The **Electrical Continuity Report page opens.
    
    [![image-1652045163507.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045163507.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045163507.png)
    
     **Figure 6.22: Electrical Continuity Report page**

#### **6.22.1 Add an Electrical Continuity Report**

If you want to add an electrical continuity report,

1. Click [![image-1652045230351.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045230351.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045230351.png) (**ADD** button) in the **Electrical Continuity Report**  See Fig 6.22. A new window opens to add an electrical continuity report.
    
    [![image-1652045286986.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045286986.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045286986.png)
    
    [![image-1652045317440.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045317440.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045317440.png) **Tip**: A report number for a new electrical continuity report will be updated automatically in the **Report Number** box.
2. In the ****Prepared By**** box, enter the name a person who has prepared the electrical continuity report.
3. In the **Prepared Date** box, enter the prepared date of the electrical continuity report.
4. In the ****Reviewed By**** box, enter the name a person who has reviewed the electrical continuity report.
5. In the **Reviewed Date** box, enter the reviewed date of the electrical continuity report.
6. In the **Approved By** box, enter the name a person who has approved the electrical continuity report.
7. In the ****Approved Dat e****box, enter the approved date of the electrical continuity report.
8. Click **Save**.

The electrical continuity report is successfully added. Once you have added the electrical continuity report, you must add the details for the added report.

#### **6.22.2 Add Electrical Continuity Report Details** 

1. Click [![image-1652045470699.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045470699.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045470699.png) (Edit icon) in the **Edit Report** column of the **Electrical Continuity** **Report**  See Fig 6.22. The **Electrical Continuity Parameters**, **Electrical Continuity**, and **Report Photos** windows open in the **Electrical Continuity** **Report** page.
    
    [![image-1652045492051.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045492051.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045492051.png)
    
    [![image-1652045508125.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045508125.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045508125.png) **Tip**: If you want to add any notes for the electrical continuity report, you can add in the **Notes** window provided in the **Electrical Continuity** **Report** page.
2. If you want to add the electrical continuity parameters in the ****Electrical Continuity Parameters**** window, do the following, 
    1. 1. 1. In the ****Item Measured**** box, enter the number of items, which are measured for electrical continuity.
            2. In the **Procedure No** box, enter the electrical continuity procedure number.
            3. Click **Save**.
3. If you want to add the electrical continuity details in the **Electrical Continuity** window, do the following, 
    1. 1. 1. Click [![image-1652045597409.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652045597409.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652045597409.png) (****ADD**** button) in the ******Electrical Continuity****** window. Boxes opens in the respective columns to add the electrical continuity details.
                
                [![image-1652046520219.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046520219.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046520219.png)
            2. In the **Location Test** column, enter the location test detail.
            3. In the ****Reading**** column, enter the electrical continuity reading values for the respective ****Reading 1**** and ****Reading 2****.
            4. In the ****Average Reading 1 and 2****columns, enter the average reading value.
            5. In the **Specification Requirement** column, enter the specification requirement detail.
            6. In the **Result** column, enter the result of the electrical continuity test.
            7. In the **Remarks** column, enter you remarks if any.
            8. Click **Save Changes**.
4. If you want to add the report photos in the ****Report Photos**** window, do the following, 
    1. 1. 1. Click [![image-1652046594768.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046594768.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046594768.png) (**ADD** button) in the **Report Photos** window.
                
                [![image-1652046606117.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046606117.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046606117.png)
            2. Click [![image-1652046623106.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046623106.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046623106.png) (**Browse** button) to browse a photo stored in your computer.
            3. Click **Upload**.
                
                The selected photo will be updated.

#### **6.22.3 Print an Electrical Continuity Report**

If you want to print an electrical continuity report, click[![image-1652046700590.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046700590.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046700590.png) (print icon) provided in the **Report** column of the **Electrical Continuity** **Report** page. See Fig 6.22.

#### **6.22.4 Attach a File into an Electrical Continuity Report**

If you want to attach any file with any electrical continuity report listed in the **Electrical Continuity Report** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.22.5 Edit Any Electrical Continuity Report**

If you want to edit any existing electrical continuity report in the **Electrical Continuity Report** page, do the following,

1. Click [![image-1652046842113.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046842113.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046842113.png)(Edit icon) in the **Edit** column for the respective electrical continuity report. See Fig 6.22. A new window opens to edit the electrical continuity report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.22.6 Export Electrical Continuity Report List**

You can export a list of electrical continuity reports added in the **Electrical Continuity Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.


### **6.23 Joint Summary Report**

The **Joint Summary report** tab in the **Structural** menu used to view a joint summary report. If you want to see a joint summary report,

1. Click the **Joint Summary Report** tab. A list of joint summary reports opens.
    
    [![image-1652046962819.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046962819.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046962819.png)
    
     **Figure 6.23: Joint Summary Report page**
    
    [![image-1652046988847.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652046988847.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652046988847.png) **Tip**: If you want to view a joint summary report for all projects, click the check box provided with the **All Projects** option.

#### **6.23.1 Export Joint Summary Report List**

You can export a list of joint summary reports in the **Joint Summary Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.


### **6.24 Joint Status Report (Skid)**

The **Joint Status Report (Skid)** tab in the **Structural** menu helps you to view a joint status report (Skid) based on an inspection status report.

If you want to view a joint status report (Skid),

1. Click the **Joint Status Report** **(Skid)** tab. A joint status report (Skid) opens.
    
    [![image-1652047103519.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047103519.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047103519.png)
    
     **Figure 6.24: Joint Status Report (Skid)** **page**

#### **6.24.1 Print a Joint Status Report (Skid)**

If you want to print a joint status report (Skid), use [![image-1652047182625.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047182625.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047182625.png) and [![image-1652047193157.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047193157.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047193157.png) (print icons) provided in the **Joint Status** **Report (Skid)** page. See Fig 6.24.

1. If you want to print the current page of the joint status report (Skid), click [![image-1652047219242.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047219242.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047219242.png) (print icon including the page number).
2. If you want to print all the pages of the joint status report (Skid), click [![image-1652047240540.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047240540.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047240540.png)(print icon).

#### **6.24.2 Export Joint Status Report (Skid) List**

You can export a joint status report (Skid) in the **Joint Status Report (Skid)** page in various formats by using the option [![image-1652047294521.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047294521.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047294521.png) provided in the upper right corner of the **Joint Status Report (Skid)** page.


### **6.25 Joint Status Report (Project)**

The **Joint Status Report (Project)** tab in the **Structural** menu helps you to view a joint status report (project) depends on the project type.

If you want to view a joint status report (project),

1. Click the **Joint Status Report** **(Project)** tab. A joint status report (project) opens.
    
    [![image-1652047361864.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047361864.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047361864.png)
    
     **Figure 9.25: Joint Status Report (Project) page**
2. In the **Project** box, select a project for which you want to view a joint status report (project), from a drop-down list.
    
    A joint status report (project) opens for the selected project.

#### **6.25.1 Print a Joint Status Report (Project)**

If you want to print a joint status report (project), use[![image-1652047446876.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047446876.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047446876.png) and [![image-1652047459582.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047459582.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047459582.png) (print icons) provided in the **Joint Status** **Report** **(Project)** page. See Fig 6.25.

1. If you want to print the current page of the joint status report (project), click [![image-1652047492141.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047492141.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047492141.png)(print icon including the page number).
2. If you want to print all the pages of the joint status report (project), click [![image-1652047511343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047511343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047511343.png)(print icon).

#### **6.25.2 Export Joint Status Report (Project) List**

You can export a joint status report (project) in the **Joint Status Report (Project)** page in various formats by using the option[![image-1652047561730.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047561730.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047561730.png) provided in the upper right corner of the **Joint Status Report (Project)** page.


### **6.26 Joint Status Report (Weekly)**

The **Joint Status Report (Weekly)** tab in the **Structural** menu helps you to view a joint status report (Weekly) on a weekly basis.

If you want to view a joint status report (Weekly),

1. Click the **Joint Status Report** **(Weekly)** tab. A joint status report (Weekly) opens.
    
    [![image-1652047779006.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047779006.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047779006.png)
    
     **Figure 6.26: Joint Status Report (Weekly) page**
2. In the **From Date** and **To Date** boxes, select the from and to dates in respectively.
3. Click **Go**.
    
    A joint status report (Weekly) opens for the selected dates.

#### **6.26.1 Print a Joint Status Report (Weekly)**

If you want to print a joint status report (Weekly), use [![image-1652047892172.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047892172.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047892172.png)and [![image-1652047908641.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047908641.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047908641.png) (print icons) provided in the **Joint Status** **Report** **(Weekly)** page. See Fig 6.26.

1. If you want to print the current page of the joint status report (Weekly), click [![image-1652047938697.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047938697.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047938697.png) (print icon including the page number).
2. If you want to print all the pages of the joint status report (Weekly), click [![image-1652047961932.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652047961932.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652047961932.png)(print icon).

#### **6.26.2 Export Joint Status Report (Weekly) List**

You can export a joint status report (Weekly) in the **Joint Status Report (Weekly)** page in various formats by using the option [![image-1652048047107.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048047107.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048047107.png) provided in the upper right corner of the **Joint Status Report (Weekly)** page.



### **6.27 Inspection Status Report**

Inspection Status Report shows the overall inspection reports such as from fit-up inspection status to NDT inspection status.

If you want to view an inspection status report, do the following,

1. Click the **Inspection Status Report** tab. The **Inspection Status Report** page opens.
    
    [![image-1652048124122.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048124122.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048124122.png)
    
    [![image-1652048131033.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048131033.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048131033.png)
    
    [![image-1652048138243.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048138243.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048138243.png)
    
    [![image-1652048143835.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048143835.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048143835.png)
    
     **Figure 6.27: Inspection Status Report page**
    
    The **Inspection Status Report** page contains joint information, RFI fit-up, RFI weld VI, and NDT inspection status.
2. In the **From Date** and **To Date** boxes, select the from and to dates in respectively.
3. Click **Search**.
    
    The inspection status report opens for the selected dates.
    
    [![image-1652048214170.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048214170.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048214170.png) **Tip**: If you want to view the inspection status report including the weld and NDT inspection date, click the check box provided with the **Weld Date/ NDT Date** option.

#### **6.27.1 Print an Inspection Status Report** 

If you want to print an inspection status report, use[![image-1652048273665.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048273665.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048273665.png) (print icon) provided in the **Inspection Status** **Report** page. See Fig 6.27.

#### **6.27.2 Export Inspection Status Report List**

You can export a list of inspection status report in the **inspection Status Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.



### **6.28 Weld Traceability Record**

The **Weld Traceability Record** tab in the **Structural** menu used to add and track a weld traceability record.

If you want add a weld traceability record, do the following,

1. Click the **Weld Traceability Record** tab. The **Weld Traceability Record** page opens.
    
    [![image-1652048387272.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048387272.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048387272.png)
    
     **Figure 6.28: Weld Traceability Record page**

#### **6.28.1 Add a Weld Traceability Record**

If you want to add a weld traceability record, do the following,

1. Click [![image-1652048479543.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048479543.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048479543.png) (**ADD** button) in the **Weld Traceability Record** page. See Fig 6.28. A new window opens to add a weld traceability record.
    
    [![image-1652048494833.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048494833.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048494833.png)
    
    [![image-1652048507407.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048507407.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048507407.png) **Note**: The field notified with a symbol (\*) is mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1652048538854.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048538854.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048538854.png) **Tip**: A report number for a new weld traceability record will be updated automatically in the **Report Number** box.
2. In the **Drawing Number** box, select a drawing number from a drop-down list.
3. In the **Date** box, enter the date of adding the weld traceability record.
4. In the **Prepared By** box, enter the name of a person who has prepared the weld traceability record.
5. In the **Prepared Date** box, select the prepared date of the weld traceability record.
6. In the **Reviewed By** box, enter the name of a person who has reviewed the weld traceability record.
7. In the **Reviewed Date** box, select the reviewed date of the weld traceability record.
8. In the **Approved By** boxes, enter the name of a person who has approved the weld traceability record.
9. In the ****Approved Date**** box, select the approved date of the weld traceability record.
10. If you want to display Not Applicable (NA) in any field instead of leaving as an empty one, select the **Is NA?** check box.
11. In the **Remarks** box, enter your remarks if any.
12. In the **Comments** box, enter your comments if any.
13. Click **Save**.
    
    The weld traceability record is successfully added.

#### **6.28.2 Print a Weld Traceability Report**

If you want to print a weld traceability report, click[![image-1652048718116.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048718116.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048718116.png) (print icon) provided in the **Report** column in the Weld Traceability Record page. See Fig 6.28.

#### **6.28.3 Attach a File into a Weld Traceability Record**

If you want to attach any file with the weld traceability record listed in the **Weld Traceability Record** page, follow the procedures given in the topic “[**<u>Attach a file into a client master drawing</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.2.2%C2%A0attach-a-file-)” in the **Client Master Drawing** section.

#### **6.28.4 Edit Any Weld Traceability Record** 

 If you want to edit any existing weld traceability record in the **Weld Traceability Record** page, do the following,

1. Click [![image-1652048863926.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048863926.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048863926.png)(Edit icon) in the **Edit** column for the respective weld traceability record. See Fig 6.28. A new window opens to edit the weld traceability record.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **6.28.5 Export Weld Traceability Record List**

You can export a list of weld traceability record added in the **Weld Traceability Record** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.

#### **6.28.6 Filter Any Weld Traceability Record**

If you want to filter any weld traceability record from the list in the **Weld Traceability Record** page, you can use the [![image-1652048966742.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652048966742.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652048966742.png) (**FILTER** button). To know how to filter, see the topic, ”**Filter Any Area**”.



### **6.29 Weld Rejection Rate**

In Structural project, Weld Rejection Rate is the difference between the tested length and repair length of the welded material, which are calculated using RT and UT inspection. The Weld Rejection Rate is used to calculate the weld success rate.

The **Weld Rejection Rate** tab in the **Structural** menu shows a weld rejection rate report including weekly and cumulative weld success rate summary details.

If you want to view a weld rejection rate report,

1. Click the **Weld Rejection Rate** tab. The weld rejection rate report page opens.
    
    [![image-1652049050613.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049050613.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049050613.png)
    
     **Figure 9.29: Weld Rejection Rate Report page**
2. In the **Project** box, select a project for which you want to view a weld rejection rate report, from a drop-down list.
3. In the **From Date** and **To Date** boxes, select the from and to dates in respectively.
4. Click **Show Report**.
    
    The weld rejection rate report opens for the selected project.

#### **6.29.1 Print a Weld Rejection Rate Report**

If you want to print a weld rejection rate report, use[![image-1652049203474.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049203474.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049203474.png) and [![image-1652049212838.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049212838.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049212838.png) (print icons) provided in the **Weld Rejection Rate** **Report** page. See Fig 6.29.

1. If you want to print the current page of the weld rejection rate report, click [![image-1652049246147.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049246147.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049246147.png) (print icon including the page number).
2. If you want to print all the pages of the weld rejection rate report, click [![image-1652049266955.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049266955.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049266955.png) (print icon).

#### **6.29.2 Export Weld Rejection Rate Report** 

You can export the weld rejection rate report in various formats by using the option [![image-1652049322650.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049322650.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049322650.png) provided in the upper right corner of the **Weld Rejection Rate Report** page.


### **6.30 Weld Rejection Rate (MPI)**

In Structural project, Weld Rejection Rate (MPI) is the difference between the tested length of and repair length of the Complete Joint Penetration (CJP) and Fillet welding materials, which are calculated using MPI inspection. The Weld Rejection Rate is used to calculate the weld success rate.

The **Weld Rejection Rate** **(MPI)** tab in the **Structural** menu shows a weld rejection rate report including weekly and cumulative weld success rate summary details.

If you want to view a weld rejection rate report,

1. Click the **Weld Rejection Rate (MPI)** tab. The **Weld Rejection Rate Report** page opens.
    
    [![image-1652049397923.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049397923.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049397923.png)
2. In the **Project** box, select a project for which you want to view a weld rejection rate report, from a drop-down list.
3. In the **Report Type** box, select the report type from a drop-down list.
4. In the **From Date** and **To Date** boxes, select the from and to dates in respectively.
5. Click **Show Report**.
    
    The weld rejection rate report opens for the selected project.

#### **6.30.1 Print a Weld Rejection Rate Report**

If you want to print a weld rejection rate report, use [![image-1652049461136.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049461136.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049461136.png) and [![image-1652049473558.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049473558.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049473558.png) (print icons) provided in the **Weld Rejection Rate** **Report** page. See Fig 6.30.

1. If you want to print the current page of the weld rejection rate report, click [![image-1652049499294.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049499294.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049499294.png) (print icon including the page number).
2. If you want to print all the pages of the weld rejection rate report, click [![image-1652049520253.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049520253.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049520253.png) (print icon).

#### **6.30.2 Export Weld Rejection Rate Report** 

You can export the weld rejection rate report in various formats by using the option [![image-1652049571075.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049571075.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049571075.png) provided in the upper right corner of the **Weld Rejection Rate Report** page.


### **6.31 Inspection Progress Status Report**

The **Inspection Progress Status Report** tab in the **Structural** menu helps you to view an inspection progress status report depends on the project type.

If you want to view an inspection progress status report,

1. Click the **Inspection Progress Status Report** tab. The inspection progress status report page opens.
    
    [![image-1652049627996.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049627996.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049627996.png)
    
     **Figure 6.31: Inspection Progress Status Report page**
2. In the **Project** box, select a project for which you want to view an inspection progress status report, from a drop-down list.
3. Click **Show Report**.
    
    The inspection progress status report opens for the selected project.

#### **6.31.1 Print an Inspection Progress Status Report**

If you want to print an inspection progress status report, use [![image-1652049726649.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049726649.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049726649.png) and [![image-1652049737678.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049737678.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049737678.png) (print icons) provided in the **Inspection Progress Status** **Report** page. See Fig 6.31.

1. If you want to print the current page of the inspection progress status report, click [![image-1652049767881.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049767881.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049767881.png) (print icon including the page number).
2. If you want to print all the pages of the inspection progress status report, click [![image-1652049799140.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049799140.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049799140.png) (print icon).

#### **6.31.2 Export Inspection Progress Status Report** 

You can export the inspection progress status report in the **Inspection Progress Status Report** page in various formats by using the option [![image-1652049858780.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049858780.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049858780.png) provided in the upper right corner of the **Inspection Progress Status Report** page.


### **6.32 Welder Performance Report**

Welder performance report used to view the welder performance details. If you want to view a welder performance report, do the following,

1. Click the **Welder Performance** tab. The **Welder Performance Report** page opens.
    
    [![image-1652049909338.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652049909338.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652049909338.png)
    
     **Figure 6.32: Welder Performance Report page**
2. In the **Project** box, select a project for which you want to view a welder performance report, from a drop-down list.
3. In the **From Date** and **To Date** boxes, select the from and to dates in respectively.
4. In the **Joint type** box, select the joint type from a drop-down list.
5. Click **Load Report**.

The welder performance report opens for the selected project.

#### **6.32.1 Print a Welder Performance Report**

If you want to print a welder performance report, use [![image-1652050004576.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050004576.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050004576.png) and [![image-1652050014487.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050014487.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050014487.png) (print icons) provided in the **Welder Performance Report** page. See Fig 6.32.

1. If you want to print the current page of the welder performance report, click [![image-1652050038083.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050038083.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050038083.png) (print icon including the page number).
2. If you want to print all the pages of the welder performance report, click (print icon).

#### **6.32.2 Export Welder Performance Report** 

You can export the welder performance report in various formats by using the option [![image-1652050086168.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050086168.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050086168.png) provided in the upper right corner of the **Welder Performance Report** page.


### **6.33 Welder Statistic Report**

Welder Statistics Report shows the statistical data of the welders. If you want to view a welder statistics report, do the following,

1. Click the **Welder Statistic Report** tab in the **Structural** meu. The **Welder Statistic Report** page opens.
    
    [![image-1652050195567.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050195567.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050195567.png)
    
     **Figure 9.33: Welder Statistic Report page**
2. In the **From Date** and **To Date** boxes, select the from and to dates in respectively.
3. Click **Load Report**.

The welder statistic report opens for the selected dates.

#### **6.33.1 Print a Welder Statistic Report**

If you want to print a welder statistic report, use [![image-1652050275812.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050275812.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050275812.png)and [![image-1652050288670.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050288670.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050288670.png) (print icons) provided in the **Welder Statistic Report** page. See Fig 6.33.

1. If you want to print the current page of the welder statistic report, click [![image-1652050320148.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050320148.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050320148.png) (print icon including the page number).
2. If you want to print all the pages of the welder statistic report, click [![image-1652050340084.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050340084.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050340084.png)(print icon).

#### **6.33.2 Export Welder Statistic Report**

You can export the welder statistic report in various formats by using the option [![image-1652050401231.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050401231.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050401231.png)provided in the upper right corner of the **Welder Statistic Report** page.


### **6.34 Joint Summary Report (Detailed)**

Joint Summary Report (Detailed) used to track the detailed weld joints summary. Do the following steps to view a joint summary report,

1. Click the **Joint Summary Report (Detailed)** tab. The **Welding Summary Report** page opens. [![image-1652050462332.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050462332.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050462332.png)
    
    [![image-1652050476776.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050476776.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050476776.png)
    
     **Figure 6.34: Welding Summary Report page**

#### **6.34.1 Edit Joint Details**

If you want to edit the joint details in the welding summary details,

1. Click the respective joint number in the **Joint No** column of the **Welding Summary Report** page. The Joint Details window opens
    
    [![image-1652050572704.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050572704.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050572704.png)
2. Click [![image-1652050595820.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652050595820.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652050595820.png)(Edit icon) in the **Edit** column for the respective joint numbers of the columns where you want to make changes in the thickness of the weld joint, piece mark number, and heat number.
3. Edit the details in the respective columns.
4. Click **Save**.

#### **6.34.2 Print a Welding Summary Report**

If you want to print a welding summary report, use [![image-1652051286060.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1652051286060.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1652051286060.png) (print icon) provided in the **Welding Summary Report** page. See Fig 6.35.

#### **6.34.3 Export Welding Summary Report List**

You can export a list of welding summary reports added in the **Welding Summary Report** page in the pdf and excel formats. To know how to export, see the topic, “[**<u>Export Areas list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data-qXJ/#bkmrk-3.1.4%C2%A0export-areas-l)” in the **Area** option.