# Inspection

### **5.0 Inspection**

The **Inspection** menu in the home page of the ***cuteQM*** app used add a Request for Inspection (RFI) fit up request, an RFI weld VI request, an NDT inspection request, a spool release request, a dimensional inspection request, an RFI painting and blasting work, and other AFI requests.

#### **5.1 RFI Fit up Request (Heat Numbers)**

The RFI Fit up Request tab allows you add an RFI fit up request to check the fit-up quality of pipes and joints used in the piping project by a sub-contractor. To navigate to the RFI fit up request adding page,

1. Click ****RFI Fit up Request**** in the ****Inspection**** menu. The **RFI Fit up Request** page opens.
    
    [![image-1651200865318.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651200865318.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651200865318.png)
    
     **Figure 5.1: RFI Fit up Request page**

#### **5.1.1 Add an RFI Fit up Request**

If you want to add an RFI fit up request, do the following steps,

1. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
2. In the **Inspection Date and Time** box, select the inspection date and time.
    
    [![image-1651200945483.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651200945483.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651200945483.png)**Note:** The inspection date should be as current date or upcoming dates. The system will not accept if you have given the previous dates. The fit up inspection date should not be later than the RFI weld visual inspection date.
3. In the ****Location**** box, select a location from a drop-down list.
4. In the ****System**** box, select a system from a drop-down list. Before saving the added fit up request, you must add joints for the fit-up request.
    
    [![image-1651201027630.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201027630.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201027630.png)**Note**: You can add multiple joints for one request.
    
    The **RFI Fit up Request** page shows a list of joints for the corresponding line and drawing numbers including the component details. If you want to add joints for the RFI Fit up request, do the following, [![image-1651201059763.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201059763.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201059763.png)
5. Before adding joints, click the respective[![image-1651201091892.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201091892.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201091892.png) (Add component details icon) of the joints which you want to add. The **Component – I &amp; II** box opens.
    
    [![image-1651201190682.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201190682.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201190682.png)
6. Check and edit the details of first and second components. 
    1. 1. Check the first and second components name. If you want to change the component, you can change the component by using a drop-down list.
        2. In the ****Material**** box, select the material that is the components is made with.
        3. Check the material specifications and grade.
        4. In the ****Diameter (MM)**** and ****Thickness (MM)**** boxes, select the diameter and thickness of the components from the given values.
        5. Click ****Save****. The component details will be saved successfully.
7. Click[![image-1651201285984.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201285984.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201285984.png) (Add icon) of the respective joints you want to add. The added joints will be moved and listed in the right side of the page.
    
    [![image-1651201308335.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201308335.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201308335.png)
8. In the ****Heat No 1**** box, enter the heat number of the first component if you know.
9. In the ****Heat No 2**** box, enter the heat number of the second component if you know.
10. In the ****Fitter**** box, select the fitter from a drop-down list.
11. In the ****WPS**** box, select the WPS from a drop-down list. [![image-1651201433945.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201433945.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201433945.png) **Tip**: If you want to remove any added joint, click [![image-1651201449656.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201449656.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201449656.png)(**Remove** icon) of the respective joint.
12. In the ****Description/Note**** box, enter the description for the added RFI fit up request.
13. Click ****Save****.

The RFI fit up request is successfully added. If you want to view the added request, navigate to [**<u>View RFI Fit up</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.2-view-rfi-fit-up-).


### **5.2 View RFI Fit up (Heat Numbers)**

The **View RFI Fit up** tab helps you to view and edit the RFI fit up requests, which are added by using the **RFI Fit up Request** tab. This tab also allows you to add a new RFI fit up request.

1. Click the **View RFI Fit up** tab in the **Inspection** menu.
    
    The **RFI Fit up Request List** page opens with a list of added RFI fit up requests.
    
    [![image-1651201553190.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201553190.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201553190.png)
    
     **Figure 5.2: RFI Fit up Request List page**

#### **5.2.1 Add an RFI Fit up Request**

If you want to add an RFI fit up request, do the following,

1. Click [![image-1651201649669.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201649669.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201649669.png) (****ADD**** button) in the ******RFI Fit up Request List****** page. The system redirects you into **RFI Fit up Request** page. To know how to add an RFI fit up request, See the topic, “**[<u>Add an RFI Fit up Request</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.1.1-add-an-rfi-fit)**”.

Once you have added the RFI fit up request, you must submit the added request for inspection.

#### **5.2.2 Add Representative for Added RFI Fit up Request**

If you want to add a representative for any added RFI fit up request,

1. Click [![image-1651201749585.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201749585.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201749585.png)(Edit icon) in the ****Representative**** column for the respective RFI fit up request. The **Edit Form** window opens.
    
    [![image-1651201773894.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201773894.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201773894.png)
2. In the ****Representative**** box, enter the name of a representative.
3. In the ****Inspection Date**** box, select the date of inspection.
4. In the ****Remarks**** box, enter your remarks if any.
5. Click ****Save****.

#### **5.2.3 Edit an RFI Fit up Request** 

If you want to edit any existing RFI fit up request in the **RFI** **Fit up Request** page, do the following,

1. Click (Edit icon) in the ****Edit**** column for the respective RFI fit up request. See Fig 5.2. The **RFI Fit up Visual Request** page opens with the details of the selected RFI fit up request.
    
    [![image-1651201875898.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201875898.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201875898.png)
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.2.4 Submit and Approve an RFI Fit up Request**

Once you have added the RFI fit up request, the **Submission** column in the **RFI Fit up Request Lists** page is appeared with[![image-1651201968441.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201968441.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201968441.png)(Submit and Reject icons). See Fig 5.2.

1. If you want to submit the RFI fit up request, click [![image-1651201981884.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201981884.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201981884.png)(Submit icon) in the **Submission** column. Otherwise click [![image-1651201995224.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651201995224.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651201995224.png)(Reject icon) to reject the request.
    
    Once you have submitted the RFI fit up request, the **Request Status** column in the **RFI Fit up Requests List** page is appeared with[![image-1651202048663.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202048663.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202048663.png)(Approve and Reject icons).
2. If you want to approve the RFI fit up request, click (Submit icon) in the ****Request Status**** Otherwise click [![image-1651202071851.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202071851.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202071851.png)(Reject icon) to reject the request.

The approved request will be moved to for inspection.

#### **5.2.5 Add Results of RFI Fit up Inspection**

After completing the RFI fit up inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651202154608.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202154608.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202154608.png) (Add icon) in the **Results** column of the respective request.
    
    The **RFI Fit up Request List** window opens with a list of joints.
    
    [![image-1651202170647.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202170647.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202170647.png)
2. If you want to update the heat numbers for both the components, click (Edit icon) of the respective component. The Heat Number window opens with a list of heat numbers and MIR numbers.
    
    [![image-1651202202766.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202202766.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202202766.png)
3. Select the heat numbers you want to update.
4. Click ****Save &amp; Close****. The heat numbers will be updated successfully.
5. If you want to update the WPS number in the **WPS Number** column, you can change the WPS number from a drop-down list.
6. Update the result for root gap by selecting ****Accepted**** or ****Rejected**** in the ****Root Gap**** column based on the inspection.
7. Update the result for straight/ alignment by selecting ****Accepted**** or ****Rejected**** in the ****Strgt/Align**** column based on the inspection.
8. In the ****Edge Prep**** column, select the type of the edge preparation from a drop-down list.
9. In the ****Result**** column, update the RFI fit up inspection result by selecting ****Pending****, ****Accepted****, ****Rejected****, or ****Cancelled****.
10. In the ****Remarks**** column, enter you remarks if any. [![image-1651202298446.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202298446.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202298446.png)**Note**: If you want to attach any document to add more information about the inspection results, click (Attach icon) and attach your document.

#### **5.2.6 View an RFI Fit up Report**

If you want to view an RFI fit up report, click [![image-1651202346789.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202346789.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202346789.png)(print icon) provided in the **Report** column of the **RFI Fit up Requests List** page. See Fig 5.2.

#### **5.2.7 View Signature Details of Inspectors**

You can view the sign details of the inspectors such as QA, Sub contractor, Client, and Owner, once they completed the RFI fit up inspection and submitted the inspection result details including their signature. To view the signature details, click[![image-1651202403131.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202403131.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202403131.png)(Sign icon) in the **Sign Details** column in the **RFI Fit up Requests List** page.

#### **5.2.8 Bulk Print the RFI Fit up Reports**

If you want to print all the RFI fit up reports added in the **RFI Fit up Requests List** page together, click [![image-1651202451564.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202451564.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202451564.png) (**Bulk Print** button). The Report page shows all the RFI fit up reports together.

#### **5.2.9 Attach a File into an RFI Fit up Request** 

If you want to attach a file with any existing RFI fit up request listed in the **RFI Fit up Requests List** page, you can attach the file by using [![image-1651202499153.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202499153.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202499153.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.2.10 Export RFI Fit up Request List**

You can export a list of RFI fit up requests added in the **RFI Fit up Requests List** page in both the pdf and excel formats by using [![image-1651202537414.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202537414.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202537414.png) (**PDF** button) and [![image-1651202548613.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202548613.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202548613.png) (**Excel** button). To know how to export, see the topic, “**[<u>Export P&amp;ID list</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)**”.

#### **5.2.11 Filter an RFI Fit up Request**

If you want to filter any specific RFI fit up request in the **RFI Fit up Requests List** page,

- you can use the filter box [![image-1651202605997.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202605997.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202605997.png) provided in the upper side of the ****RFI Fit up Requests List****  To filter the any specific RFI fit up request, select the ****Drawing Number**** and ****Date**** in the boxes and click ****Search****. [![image-1651202632269.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202632269.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202632269.png)
- you can use [![image-1651202662798.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202662798.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202662798.png) (****FILTER**** button) located on the ****RFI Fit up Requests List**  To know how to filter, see the topic, “[<u>**Filter P&amp;ID**</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.3 RFI Weld VI Request (Heat Numbers)**

The **RFI Weld VI Request** tab in the **Inspection** menu allows you to add an RFI weld VI request to perform visual inspection of welded pipes and joints used in the piping project. To navigate to the RFI weld VI request adding page,

1. Click **RFI Weld VI Request** in the **Inspection** menu.
    
    The **RFI Weld Visual Request** page opens.
    
    [![image-1651202730986.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202730986.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202730986.png)
    
     **Figure 5.3: RFI Weld Visual Request page**

#### **5.3.1 Add an RFI Weld VI Request**

If you want to add an RFI weld VI request, do the following steps,

1. In the ****Sub Contractor Name**** box, select the name of a sub-contractor from a drop-down list.
2. In the ****Inspection Date and Time**** box, select the inspection date and time. [![image-1651202807100.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202807100.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202807100.png) **Note:** The inspection date should be as current date or upcoming dates. The system will not accept if you have given the previous dates.
3. In the ****Location**** box, select a location from a drop-down list.
4. In the **System** box, select a system from a drop-down list. Before saving the added weld VI request, you must add joints for the weld VI request.
    
    [![image-1651202862835.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202862835.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202862835.png) **Note**: You can add multiple joints for one request.
    
    The **RFI Weld Visual Request** page shows a list of joints for the corresponding line and drawing numbers including the spool number. If you want to add joints for the RFI weld VI request, do the following steps,
    
    [![image-1651202894373.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202894373.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202894373.png)
5. Click [![image-1651202920056.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202920056.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202920056.png)(Add icon) of the respective joints you want to add.
    
    The added joints will be moved and listed in the right side of the page.
    
    [![image-1651202933599.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202933599.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202933599.png)
6. Update the welder details by using[![image-1651202963160.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202963160.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202963160.png)(Add icon) provided in the ****Welder Details****
    1. 1. Click[![image-1651202979402.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202979402.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202979402.png) (Add icon) of the respective joint number. The **Welder- Weld Layer- Weld Process** window opens.
            
            [![image-1651202999679.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651202999679.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651202999679.png)
        2. In the ****Date**** box, select the date.
        3. In the ****Group Name**** box, select the group name from a drop-down list.
        4. In the ****Weld Process**** field, select a weld process.
        5. In the ****Weld Position**** field, select the welding position.
        6. In the ****Weld Layers**** field, select the weld layers you want add.
        7. In the ****Welder Number/ Name**** field, select the welders you want to add.
        8. Click ****Add****. The selected welders will be added and listed in the below table. See the above figure.
        9. In the ****Weld Consumable**** box, select the weld consumable from a drop-down list.
        10. In the ****WPS Number**** box, select the WPS number from a drop-down list.
        11. Click ****Save****. [![image-1651203097946.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203097946.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203097946.png)**Tip**: If you want to remove any added joint, click (**Remove** icon) of the respective joint.
        12. In the ****Description**** box, enter the description for the added RFI weld VI request.
        13. Click ****Save****. The RFI weld VI request is successfully added. If you want to view the added request, navigate to [**<u>View RFI Weld VI</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.4-view-rfi-weld-vi).


### **5.4 View RFI Weld VI (Heat Numbers)**

The **View RFI Weld VI** tab helps you to view and edit the RFI weld VI request, which is added by using the **RFI Weld VI Request** tab. This tab also allows you to add a new RFI weld VI request.

1. Click the **View RFI Weld VI** tab in the **Inspection** menu.
    
    The **RFI Weld Visual Requests List** page opens with a list of added RFI weld VI requests.
    
    [![image-1651203226485.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203226485.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203226485.png)
    
     **Figure 5.4: RFI Weld Visual Requests List page**

#### **5.4.1 Add an RFI Weld VI Request**

If you want to add an RFI weld VI request, do the following,

1. Click [![image-1651203276886.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203276886.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203276886.png) (**ADD** button) in the **RFI Weld Visual Requests List** page.
    
    The system redirects you into **RFI Weld Visual Request** page. To know how to add an RFI weld VI request, See the topic, “[**<u>Add an RFI Weld VI Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.4-view-rfi-weld-vi)”.

Once you have added the RFI weld VI request, you must submit the added request for weld visual inspection.

#### **5.4.2 Add Representative for Added RFI Weld VI Request**

If you want to add a representative for any added RFI weld VI request,

1. Click [![image-1651203398654.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203398654.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203398654.png)(Edit icon) in the ****Representative**** column for the respective RFI weld VI request.
    
    The **Edit Form** window opens.
    
    [![image-1651203412706.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203412706.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203412706.png)
2. In the ****Representative**** box, enter the name of a representative.
3. In the ****Inspection Date**** box, select the date of inspection.
4. In the ****Remarks**** box, enter your remarks if any.
5. Click ****Save****.

#### **5.4.3 Edit an RFI Weld VI Request** 

If you want to edit any existing RFI weld VI request in the **RFI** **Weld Visual Requests List** page, do the following,

1. Click[![image-1651203594989.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203594989.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203594989.png)(Edit icon) in the **Edit** column for the respective RFI weld VI request. See Fig 5.4. The **RFI Weld Visual Request** page opens with the details of the selected RFI weld VI request.
    
    [![image-1651203621851.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203621851.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203621851.png)
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.4.4 Submit an RFI Weld VI Request**

Once you have added the RFI weld VI request, the **Request Status** column in the **RFI Weld Visual Requests List** page is appeared [![image-1651203728786.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203728786.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203728786.png)with (Submit and Reject icons). See Fig 5.4.

1. If you want to submit the RFI weld VI request, click[![image-1651203762346.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203762346.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203762346.png) (Submit icon) in the ****Request Status**** Otherwise click [![image-1651203792080.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651203792080.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651203792080.png) (Reject icon) to reject the request.

The submitted request will be moved to for RFI weld visual inspection.

#### **5.4.5 Add Results of RFI weld Visual Inspection**

After completing the RFI weld visual inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651204298494.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204298494.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204298494.png)(Add icon) in the **Results** column of the respective request. The **RFI Weld Visual Request List** window opens with a list of joints added for the particular request.
    
    [![image-1651204332633.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204332633.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204332633.png)
2. If you want to update the welder details, click[![image-1651204360463.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204360463.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204360463.png) (Add icon) of the respective joint. The **Welder-Weld Layer-Weld Process** window opens.
    
    [![image-1651204372371.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204372371.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204372371.png)
    
    [![image-1651204383612.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204383612.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204383612.png) **Note:** If you want to delete any added weld, click (Delete icon) of the respective welder.
    
    
    1. 1. In the ****Date**** box, select the date.
        2. In the ****Group Name**** box, select the group name from a drop-down list.
        3. In the ****Weld Process**** field, select a weld process.
        4. In the ****Weld Position**** field, select the welding position.
        5. In the ****Weld Layers**** field, select the weld layers you want add.
        6. In the ****Welder Number/ Name**** field, select the welders you want to add.
        7. Click ****Add****. The selected welders will be added and listed in the below table. See the above figure.
        8. In the ****Weld Consumable**** box, select the weld consumable from a drop-down list.
        9. In the ****WPS Number**** box, select the WPS number from a drop-down list.
        10. Click ****Save****.
3. In the ****Result**** column, select the result for each joint from the given result options in the drop-down list.
4. In the ****Remarks**** box, enter your remarks if any.
5. Click ****Save****.

#### **5.4.6 View an RFI Weld VI Report**

If you want to view an RFI weld VI report, click[![image-1651204648220.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204648220.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204648220.png)(print icon) provided in the **Report** column of the **RFI Weld Visual Requests List** page. See Fig 5.4.

#### **5.4.7 View Signature Details of Inspectors**

You can view the sign details of the inspectors such as QA, Sub contractor, Client, and Owner, once they completed the RFI weld visual inspection and submitted the inspection result details including their signature. To view the signature details, click[![image-1651204812728.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651204812728.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651204812728.png) (Sign icon) in the **Sign Details** column in the **RFI Weld Visual Requests List** page.

#### **5.4.8 Bulk Print RFI Weld VI Reports**

If you want to print all the RFI weld VI reports added in the **RFI Weld Visual Requests List** page together, click [![image-1651223226147.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223226147.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223226147.png) (**Bulk Print** button). The Report page shows all the RFI weld VI reports together.

#### **5.4.9 Attach a File into an RFI Weld VI Request** 

If you want to attach a file with any existing RFI weld VI request listed in the **RFI Weld Visual Requests List** page, you can attach the file by using [![image-1651223269890.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223269890.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223269890.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.4.10 Export RFI Weld VI Request List**

You can export a list of RFI weld VI requests added in the **RFI Weld Visual Requests List** page in both the pdf and excel formats by using [![image-1651223324463.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223324463.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223324463.png) (**PDF** button) and [![image-1651223333795.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223333795.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223333795.png) (**Excel** button). To know how to export, see the topic, “**[<u>Export P&amp;ID list</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)**”.

#### **5.4.11 Filter an RFI Weld VI Request**

If you want to filter any specific RFI weld VI request in the **RFI Weld Visual Requests List** page,

- you can use the filter box [![image-1651223385499.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223385499.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223385499.png) provided in the upper side of the **RFI Weld Visual Requests List**  To filter the any specific RFI weld VI request, select the **Drawing Number** and **Date** in the boxes and click **Search**. [![image-1651223413564.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223413564.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223413564.png)
- you can use [![image-1651223433424.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223433424.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223433424.png) (**FILTER** button) located on the **RFI Weld Visual Requests List** page. To know how to filter, see the topic, “[<u>Filter P&amp;ID</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.5 NDT Inspection Request**

The **NDT Inspection Request** tab in the **Inspection** menu helps you to add an NDT inspection request to perform an NDT inspection. To navigate to the NDT inspection request adding page,

1. Click ****NDT Inspection Request**** in the ****Inspection**** menu. The **NDT Inspection Request** page opens.
    
    [![image-1651223631643.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651223631643.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651223631643.png)
    
     **Figure 5.5: NDT Inspection Request page**

#### **5.5.1 Add an NDT inspection request**

If you want to add an NDT inspection request, do the following

1. Click [![image-1651227156663.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227156663.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227156663.png) (**ADD** button) in the **NDT Inspection Request** page.
    
    A new page opens to add an NDT inspection request.
    
    [![image-1651227171999.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227171999.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227171999.png)
    
     **Figure 5.5: NDT Inspection Request page**
    
    [![image-1651227211421.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227211421.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227211421.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
2. In the **Requested By** box, enter the name of person who has requested for the NDT inspection.
3. In the **To** box, select the name of a sub-contractor from a drop-down list.
4. In the **Description/ Spec. Ref. No** box, enter the description for the request.
5. In the **Inspection Date &amp; Time** box, select the date of inspection.
6. In the **Location** box, enter the location where the inspection to be done.
7. In the **Requisition** box, enter the requisition detail.
8. In the **Longitudinal** box, enter the longitudinal value.
9. In the **Drawing No** box, select the drawing number from a drop-down list.
10. In the **Designation** box, enter the designation detail.
11. In the **Cost Centre** box, enter the cost centre detail
12. In the **PWHT Request Type** box, select the PWHT request type from a drop-down list.
13. In the **System** box, select a system from a drop-down list.
14. In the **NDT Type** box, select the type of NDT you want to add. Before saving the added NDT request, you must add joints. You can add multiple joints for one NDT inspection request.
    
    [![image-1651227469136.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227469136.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227469136.png)**Note**: The page shows a list of added joints. If you want to view the joints for the specific ISO drawing, select the respective ISO drawing from a drop-down list.
15. Click[![image-1651227533159.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227533159.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227533159.png) (Add icon) of the respective joint which you want to add. The added joints will be moved to the right side of the page.
    
    [![image-1651227563727.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227563727.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227563727.png)
16. In the **Remarks** box, enter your remarks if any.
17. Click **Save NDT Request**. The added NDT inspection request will be listed in the **NDT Inspection Request** page.

#### **5.5.2 Edit an NDT Inspection Request** 

If you want to edit any existing NDT inspection request in the **NDT Inspection Request** page, do the following steps,

1. Click [![image-1651227654663.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227654663.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227654663.png) (Edit icon) in the **Edit** column for the respective NDT request. See Fig 5.5. The **NDT Inspection Request** page opens with the details of the selected NDT inspection request.
    
    [![image-1651227744309.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227744309.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227744309.png)
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.5.3 Submit and Approve an NDT Inspection Request**

Once you have added the NDT inspection request, the **Submission** column in the **NDT Inspection Request** page is appeared with [![image-1651227804150.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227804150.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227804150.png) (Submit and Reject icons). See Fig 5.5.

1. If you want to submit the NDT inspection request, click[![image-1651227834918.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227834918.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227834918.png) (Submit icon) in the ****Submission**** Otherwise click [![image-1651227860032.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227860032.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227860032.png) (Reject icon) to reject the request. Once the NDT inspection request has been submitted, the **Request Status** column in the **NDT Inspection Request** page is appeared with [![image-1651227889337.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227889337.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227889337.png) (Approve and Reject icons).
2. If you want to accept the NDT inspection request, click [![image-1651227935228.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227935228.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227935228.png)(Approve icon) in the ****Request Status**** Otherwise click [![image-1651227956151.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651227956151.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651227956151.png)(Reject icon) to reject the request. The approved request will be moved to NDT inspection.

#### **5.5.4 View an NDT Inspection Report**

If you want to view an NDT inspection report, click [![image-1651228014197.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651228014197.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651228014197.png) (print icon) provided in the **Report** column of the **NDT Inspection Request** page. See Fig 5.5.

#### **5.5.5 Attach a File into an NDT Inspection Request** 

If you want to attach a file with any existing NDT inspection request listed in the **NDT Inspection Request** page, you can attach the file by using [![image-1651228062872.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651228062872.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651228062872.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.5.6 Export NDT Inspection Request List**

You can export a list of NDT inspection requests added in the **NDT Inspection Request** page in both the pdf and excel formats by using [![image-1651228119589.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651228119589.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651228119589.png) (**PDF** button) and [![image-1651228129539.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651228129539.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651228129539.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.5.7 Filter an NDT Inspection Request**

If you want to filter any specific NDT inspection request in the **NDT Inspection Request** page,

- you can use the filter box [![image-1651238548225.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651238548225.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651238548225.png) provided in the upper side of the **NDT Inspection Request** page. To filter the any specific NDT inspection request, select the request status in the **Request Status** box.
- you can use [ ![image-1651238729214.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651238729214.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651238729214.png) (****FILTER**** button) located on the ****NDT Inspection Request**  To know how to filter, see the topic, “**[<u>Filter P&amp;ID</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)**”.

#### **5.5.8 Import Multiple NDT Inspection Requests**

If you want to import multiple NDT inspection requests together, do the following,

1. Click [![image-1651239757314.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651239757314.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651239757314.png) (**TEMPLATE** button). See Fig 5.5.
    
    An excel worksheet will be downloaded with a predefined template to enter the details of NDT inspection requests.
    
    [![image-1651239899105.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651239899105.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651239899105.png)
2. Enter the required NDT inspection request details in the respective columns of the excel worksheet.
3. Once you have added the NDT inspection request details in the excel worksheet, save the excel worksheet on your computer.
4. Click [![image-1651239958610.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651239958610.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651239958610.png) (****IMPORT**** button). See Fig 5.5. A new window opens for importing the excel worksheet saved on your computer.
    
    [![image-1651240053690.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240053690.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240053690.png)
5. Click [![image-1651240063806.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240063806.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240063806.png) (**Browse** button) to select the excel worksheet to be uploaded.
6. Select the excel worksheet you want to upload from your computer.
7. Click [![image-1651240093776.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240093776.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240093776.png) (****Upload**** button) to export the NDT inspection request that are included in the excel worksheet.

The details of the NDT inspection request in the worksheet will be displayed in the **NDT Inspection Request** page.


### **5.6 NDT Job Order**

The **NDT Job Order** tab in the **Inspection** menu allows you to add a job order for a specific NDT-contractor to carry out the NDT inspection. Once you have added the job order, you can add the NDT request including the quantity and schedule date to complete the NDT inspection.

1. Click **NDT Job Order** in the **Inspection** menu.
    
    The **Job Order** page opens.
    
    [![image-1651240218199.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240218199.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240218199.png)
    
    [![image-1651240228823.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240228823.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240228823.png)
    
     **Figure 5.6: Job Order page**

#### **5.6.1 Add an NDT Job Order**

If you want to add an NDT job order, do the following steps,

1. Click [![image-1651240354668.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240354668.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240354668.png) (**ADD** button) in the **Job Order** page. See Fig 5.6.
    
    A new window opens to add an NDT job order.
    
    [![image-1651240375655.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240375655.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240375655.png)
    
    [![image-1651240392759.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240392759.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240392759.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651240410621.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240410621.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240410621.png)**Tip**: A report number for a new job order will be updated automatically in the **Report Number** box.
2. In the ****NDT Contractor**** box, select the name of an NDT contractor from a drop-down list.
3. In the ****Attention**** box, enter any note if you want for attention.
4. In the ****Date**** box, select the date of adding an NDT job order.
5. In the **Requested By** box, enter the name of a person who has requested for an NDT job order.
6. In the ****Requested Date**** box, select the requested date of an NDT job order.
7. In the ****Supported By**** boxes, enter the name of a project lead and a HOD, respectively.
8. In the ****Supported Date**** box, select the supported date of an NDT job order.
9. Click ****Save****. The NDT job order is successfully added.

#### **5.6.2 Add an NDT Job Request** 

To add an NDT job request,

1. Click [![image-1651240583606.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240583606.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240583606.png)(Add icon) of the respective job order in the ****Add NDT Request**** column of the ****Job Order**** See Fig 5.6. A new window shows a list of added NDT request.
    
    [![image-1651240612206.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240612206.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240612206.png)
2. If you want to add any request, click [![image-1651240634566.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240634566.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240634566.png) (Add icon) of the respective request. The added NDT request will be assigned under the respective job order.
3. If you want to delete any request, click [![image-1651240675614.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240675614.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240675614.png) (Delete icon) of the respective request.

#### **5.6.3 Attach a File into an NDT Job Order** 

If you want to attach any file with any NDT job order listed in the **Job Order** page, you can attach the file by using [![image-1651240807174.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240807174.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240807174.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.6.4 View an NDT Job Order Report**

If you want to view an NDT job order report, click [![image-1651240896862.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651240896862.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651240896862.png) (print icon) provided in the **Report** column of the **Job Order** page. See Fig 5.6.

#### **5.6.5 Edit an NDT Job Order**

If you want to edit any existing NDT job order in the **Job Order** page, do the following,

1. Click [![image-1651241158257.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241158257.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241158257.png)(Edit icon) in the **Edit** column for the respective NDT job order. See Fig 5.6. A new window opens with the added details of NDT job order to edit the job order.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.6.6 Delete an NDT Job Order**

If you want to delete any specific NDT job order, you can use [![image-1651241233671.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241233671.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241233671.png) (Delete icon) provided in the **Delete** column of the **Job Order** page, See Fig 8.6. To know how to delete, see the topic, “[**<u>Delete P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.3%C2%A0delete-a-p%26id)”.

#### **5.6.7 Export NDT Job Order List**

You can export a list of NDT job order added in the **Job Order** page in the pdf and excel formats by using [![image-1651241460912.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241460912.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241460912.png) (**PDF** button) and [![image-1651241471852.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241471852.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241471852.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.


### **5.7 Spool Release Inspection Request**

The **Spool Release Request** tab in the **Inspection** menu helps you to add a spool release request. To navigate to the spool release inspection request adding page,

1. Click ****Spool Release Request**** in the ****Inspection**** menu. The **Spool Release Inspection Request** page opens.
    
    [![image-1651241577517.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241577517.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241577517.png)
    
     **Figure 5.7: Spool Release Inspection Request page**

#### **5.7.1 Add a Spool Release Inspection Request**

If you want to add a spool release inspection request, do the following steps in the **Spool Release Inspection Request p**age, See Fig 5.7.

1. In the ****Inspection Date**** box, select the date of spool inspection.
2. In the **Location** box, select the location where the spool inspection to be performed. Before saving the added spool release inspection request, you must add spools. You can add multiple spools for one spool release inspection request.
    
    [![image-1651241851538.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241851538.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241851538.png) **Note**: The page shows a list of added spools. If you want to view the specific spools, use the filter options provided in the **System**, **Line Number**, **Drawing Number**, and **Spool Number** columns.
3. Click [![image-1651241879363.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241879363.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241879363.png) (Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
    
    [![image-1651241923753.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651241923753.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651241923753.png)
4. In the **Remarks** box, enter your remarks if any.
5. In the **Inspection Item** box, enter the details of inspection items.
6. In the **Subject Coverage** box, enter the details of subject coverage.
7. Click **Save**.

The spool release request will be added and listed in the **View** **Spool Release** page.


### **5.8 View Spool Release**

The **View Spool Release** tab helps you to view and edit the spool release inspection request, which is added by using the **Spool Release Inspection Request** tab. This tab also allows you to add a new spool release request.

1. Click **View Spool Release** in the **Inspection** menu.
    
    The **Spool Release List** page opens with a list of added spool release requests.
    
    [![image-1651242070121.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651242070121.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651242070121.png)
    
     **Figure 5.8: Spool Release List page**

#### **5.8.1 Add a Spool Release Inspection Request**

If you want to add a spool release request, do the following steps,

1. Click [![image-1651242215588.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651242215588.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651242215588.png) (**ADD** button) in the **Spool Release List** page.
    
    The system redirects you into **Spool Release Inspection Request** page. To know how to add a spool release inspection request, See the topic, “[**<u>Add a Spool Release Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.7.1%C2%A0add-a-spool-re)”.

Once you have added the spool release request, you must submit the added request to perform inspection in the piping spool.

#### **5.8.2 Add Representative for Added Spool Release Inspection Request**

If you want to add a representative for any added spool release request,

1. Click [![image-1651242358767.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651242358767.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651242358767.png)(Edit icon) in the **Representative** column for the respective spool release request. The **Edit Form** window opens.
    
    [![image-1651242414597.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651242414597.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651242414597.png)
2. In the ****Inspection Date**** box, select the date of inspection.
3. In the ****Representative**** box, enter the name of a representative.
4. Click ****Save****.

#### **5.8.3 Edit a Spool Release Inspection Request** 

If you want to edit any existing spool release request in the **Spool Release List** page, do the following,

1. Click [![image-1651242854925.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651242854925.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651242854925.png)(Edit icon) in the ****Edit**** column for the respective spool release request. See Fig 5.8. The **Spool Release Inspection Request** page opens with the details of the selected spool release request.
    
    [![image-1651242882181.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651242882181.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651242882181.png)
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.8.4 Submit a Spool Release Inspection Request**

Once you have added the spool release request, the **Request Status** column in the **Spool Release List** page is appeared with [![image-1651243016713.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243016713.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243016713.png) (Submit and Reject icons). See Fig 5.8.

1. If you want to submit the spool release request, click [![image-1651243057735.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243057735.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243057735.png) (Submit icon) in the ****Request Status**** Otherwise click [![image-1651243077996.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243077996.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243077996.png)(Reject icon) to reject the request. The submitted request will be moved to for spool inspection.

#### **5.8.5 Add Results of Spool Release Inspection**

After completing the spool release inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651243199154.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243199154.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243199154.png) (Add icon) in the **Results** column of the respective request.
    
    The **Spool Release List** window opens with a list of spools added for the particular request.
    
    [![image-1651243221400.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243221400.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243221400.png)
2. In the **Result** column, select the result for each spool from the given result options in the drop-down list.
3. In the ****Remarks**** box, enter your remarks if any.
4. Click ****Save****.

#### **5.8.6 View a Piping Spool Release Report**

If you want to view a piping spool release report, click[![image-1651243293904.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243293904.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243293904.png) (print icon) provided in the **Print** column of the **Spool Release List** page. See Fig 5.8.

#### **5.8.7 Attach a File into a Spool Release Inspection Request** 

If you want to attach a file with any existing spool release request listed in the **Spool Release List** page, you can attach the file by using [![image-1651243363769.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243363769.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243363769.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.8.8 View Signature Details of Inspectors**

You can view the sign details of the inspectors such as QA, Sub contractor, Client, and Owner, once they completed the spool release inspection and submitted the inspection result details including their signature. To view the signature details, click [![image-1651243432221.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243432221.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243432221.png) (Sign icon) in the **Sign Details** column in the **Spool Release List** page.

#### **5.8.9 Export Spool Release Inspection Request List**

You can export a list of spool release requests added in the **Spool Release List** page in both the pdf and excel formats by using[![image-1651243526591.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243526591.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243526591.png) (**PDF** button) and [![image-1651243548643.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651243548643.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651243548643.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.8.10 Filter a Spool Release Inspection Request**

If you want to filter any specific spool release request in the **Spool Release List** page, you can use (**FILTER** button) located on the **Spool Release List** page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.9 Inspection Release Note**

The **Inspection Release Note** tab in the Inspection menu helps you to add an inspection release note. To navigate to the inspection release note adding page,

1. Click **Inspection Release Note** in the Inspection menu.
    
    The **Inspection Release Note** page opens.
    
    [![image-1651245058346.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651245058346.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651245058346.png)
    
     **Figure 5.9: Inspection Release Note page**

#### **5.9.1 Add an Inspection Release Note**

If you want to add an inspection release note, do the following steps,

1. In the **Inspection Date** box, select the date of inspection. See Fig 5.9.
2. In the ****Sub Contractor Name**** box, select a sub-contractor from a drop-down list.
3. In the ****Location**** box, select a location where the inspection to be held.
4. In the ****System/Area**** box, enter the name of area/system.
5. In the ****Sub System No**** box, enter the sub system number.
6. In the **Item to be Released** field, select the detail of the item to be released that is whether **Piping** or **Structural.** If another item means select the checkbox of **Others** and enter the item detail.
7. In the **Item to be Released** **for** field, select the reason of the item to be released for that is whether for **Pressure Test** or **Blasting &amp; Painting.** If any other reason means select the checkbox of **Others** and enter the reason.
8. Before saving the added inspection release note, you must add spools. You can add multiple spools for one inspection release note.
    
    [![image-1651245606753.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651245606753.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651245606753.png) **Note**: The page shows a list of added spools. If you want to view the specific spools, use the filter options provided in the **System**, **Line Number**, **Drawing Number**, **Sheet No &amp; Rev No** and **Spool Number** columns.
9. Click [![image-1651245665507.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651245665507.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651245665507.png)(Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
10. In the **Remarks** box, enter your remarks if any.
11. In the **Inspection Item** box, enter the details of inspection items.
12. In the **Subject Coverage** box, enter the detail of subject coverage.
13. Click **Save**.

The inspection release note will be added and listed in the **View** **Inspection Release Note** page.


### **5.10 View Inspection Release Note**

The **View Inspection Release Note** tab helps you to view and edit the inspection release note, which is added by using the **Inspection Release Note** tab. This tab also allows you to add a new inspection release note.

1. Click ****View Inspection Release Note**** in the ******Inspection****** menu. The **Inspection Release Note** page opens with a list of added inspection release notes.
    
    [![image-1651245846288.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651245846288.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651245846288.png)
    
     **Figure 5.10: Inspection Release Note page**

#### **5.10.1 Add an Inspection Release Note**

If you want to add an inspection release note, do the following steps,

1. Click [![image-1651245954971.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651245954971.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651245954971.png) (**ADD** button) in the **Inspection Release Note** page. The system redirects you into **Inspection Release Note** page. To know how to add an inspection release note, See the topic, “[**<u>Add an Inspection Release Note</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.9.1-add-an-inspect)”.

Once you have added the inspection release note, you must submit the added note to perform the release note inspection.

#### **5.10.2 Add a Representative for Added Inspection Release Note**

If you want to add a representative for any added inspection release note,

1. Click [![image-1651246048357.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246048357.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246048357.png) (Edit icon) in the **Representative** column for the respective inspection release note.
    
    The **Edit Form** window opens.
    
    [![image-1651246074758.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246074758.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246074758.png)
2. In the ****Inspection Date**** box, select the date of inspection.
3. In the ****Representative**** box, enter the name of a representative.
4. Click ****Save****.

#### **5.10.3 Edit an Inspection Release Note**

If you want to edit any existing inspection release note in the **Inspection Release Note** page, do the following,

1. Click [![image-1651246148349.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246148349.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246148349.png) (Edit icon) in the ****Edit**** column for the respective inspection release note. See Fig 5.10. The **Inspection Release Note** page opens with the details of the selected inspection release note.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.10.4 Submit an Inspection Release Note**

Once you have added the inspection release note, the **Request Status** column in the **Inspection Release Note** page is appeared with (Submit and Reject icons). See Fig 5.10.

1. If you want to submit the inspection release note, click [![image-1651246272287.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246272287.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246272287.png) (Submit icon) in the ****Request Status**** Otherwise click [![image-1651246306387.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246306387.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246306387.png) Reject icon) to reject the request. The submitted request will be moved to for release note inspection.

#### **5.10.5 Add RFI Data for an Inspection Release Note**

If you want to add the details of RFI data for the added inspection release note, do the following steps,

1. Click (Edit icon) in the **RFI Data** column of the **Inspection Release Note** page. See Fig 5.10.
    
    The **RFI Inspection Request List** window opens.
    
    [![image-1651246399982.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246399982.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246399982.png)
2. In the ****Inspection From**** box, enter the detail from where the inspection should start.
3. In the ****Inspection To**** box, enter the detail to where the inspection should end.
4. In the ****Inspection Details**** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the ****Others**** box, enter any other inspection related details.
6. In the ****Refer to Report No**** box, enter the report number for reference.
7. In the ****RFI Date**** box, choose the RFI date.
8. In the **Inspection Result** option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the ****Remarks**** box, enter your remarks if any.
10. In the ****Inspected by**** box, enter the name of a person who has done inspection.
11. In the ****Inspected Date**** box, choose the date of inspection.
12. In the ****Witnessed By**** box, enter the name of the witnessed person.
13. In the ****Witnessed Date**** box, choose the date of witnessed.
14. In the ****PCML Rep Name**** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the ****MEB Rep Name**** box, enter the representative name of MEB.
17. In the ****MEB Rep Date box****, choose MEB rep date.
18. Click ****Save****.

The RFI data for the inspection release note is added successfully.

#### **5.10.6 Add Results of Inspection Release Note**

After completing the inspection for the added release note, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651246749006.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246749006.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246749006.png) (Add icon) in the ****Results**** column of the respective request. The **INR List** window opens with a list of spools added for the particular request.
    
    [![image-1651246773082.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246773082.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246773082.png)
2. In the ****Result**** column, select the result for each spool from the given result options in the drop-down list.
3. In the ****Remarks**** box, enter your remarks if any.
4. Click ****Save****.

#### **5.10.7 View an RFI Report** 

If you want to view an RFI report, click[![image-1651246849368.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246849368.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246849368.png) (print icon) provided in the **RFI Report** column of the **Inspection Release Note** page. See Fig 5.10.

#### **5.10.8 View an Inspection Release Note Report**

If you want to view an inspection release note report, click[![image-1651246900096.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246900096.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246900096.png)(print icon) provided in the **Print** column of the **Inspection Release Note** page. See Fig 5.10.

#### **5.10.9 Attach a File into an Inspection Release Note** 

If you want to attach a file with any existing inspection release note listed in the **Inspection** **Release Note** page, you can attach the file by using [![image-1651246943706.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651246943706.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651246943706.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.10.10 View a Pipe Spool Release Summary**

If you want to view a pipe spool release summary report, click[![image-1651247026360.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651247026360.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651247026360.png) (print icon) provided in the upper side of the **Inspection Release Note** page. See Fig 5.10.

[![image-1651247021407.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651247021407.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651247021407.png)

#### **5.10.11 Export Inspection Release Note List**

You can export a list of inspection release notes added in the **Inspection Release Note** page in both the pdf and excel formats by using [![image-1651247100963.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651247100963.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651247100963.png) (**PDF** button) and [![image-1651247113589.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651247113589.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651247113589.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.10.12 Filter an Inspection Release Note**

If you want to filter any specific inspection release note in the **Inspection Release Note** page, you can use [![image-1651247158974.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651247158974.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651247158974.png) (**FILTER** button) located on the **Inspection Release Note** page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.11 Dimensional Inspection Request**

The **Dimensional Inspection Request** tab in the **Inspection** menu helps you to add a dimensional inspection request. To navigate to the dimensional inspection request adding page,

1. Click **Dimensional Inspection Request** in the **Inspection** menu.
    
    The **Dimensional Inspection Request** page opens.
    
    [![image-1651247677075.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651247677075.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651247677075.png)
    
     **Figure 5.11: Dimensional Inspection Request page**

#### **5.11.1 Add a Dimensional Inspection Request**

If you want to add a new dimensional inspection request, do the following steps.

1. In the **Inspection Date** box, select the date of dimensional inspection.
2. In the ****Location**** box, select the location where the dimensional inspection to be performed. Before saving the added dimensional inspection request, you must add spools. You can add multiple spools for one dimensional inspection request.
    
    [![image-1651248322032.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651248322032.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651248322032.png) **Note**: The page shows a list of added spools. If you want to view the specific spools, use the filter options provided in the **System**, **Line Number**, **Drawing Number**, and **Spool Number** columns.
3. Click [![image-1651248354041.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651248354041.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651248354041.png) (Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
4. In the **Remarks** box, enter your remarks if any.
5. In the **Inspection Item** box, enter the details of inspection items.
6. Click **Save**.

The dimensional inspection request will be added and listed in the **Dimensional Inspection List** page.


### **5.12 Dimensional Inspection List**

The **Dimensional Inspection List** tab helps you to view and edit the dimensional inspection request, which is added by using the **Dimensional Inspection Request** tab. This tab also allows you to add a new dimensional inspection request.

1. Click ****Dimensional Inspection List**** in the ******Inspection****** menu. The **Dimensional Inspection List** page opens with a list of added dimensional inspection requests.
    
    [![image-1651248630722.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651248630722.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651248630722.png)
    
     **Figure 5.12: Dimensional Inspection List page**

#### **5.12.1 Add a Dimensional Inspection Request**

If you want to add a dimensional inspection request, do the following steps,

1. Click [![image-1651248827437.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651248827437.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651248827437.png) (**ADD** button) in the **Dimensional Inspection List** page.
    
    The system redirects you into the **Dimensional Inspection Request** page. To know how to add a dimensional inspection request, See the topic, “[**<u>Add a Dimensional Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.11.1-add-a-dimensi)”.

Once you have added the dimensional inspection request, you must submit the added request to perform the dimensional inspection.

#### **5.12.2 Add Representative for Added Dimensional Inspection Request**

If you want to add a representative for any added dimensional inspection request,

1. Click [![image-1651248912250.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651248912250.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651248912250.png)(Edit icon) in the ****Representative**** column for the respective spool release request. The **Edit Form** window opens.
    
    [![image-1651248941358.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651248941358.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651248941358.png)
2. In the ****Inspection Date**** box, select the date of inspection.
3. In the ****Representative**** box, enter the name of a representative.
4. Click ****Save****.

#### **5.12.3 Edit a Dimensional Inspection Request** 

If you want to edit any existing dimensional inspection request in the **Dimensional Inspection List** page, do the following,

1. Click [![image-1651249047665.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249047665.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249047665.png)(Edit icon) in the ****Edit**** column for the respective dimensional inspection request. See Fig 5.12. The page opens with the details of the selected dimensional inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.12.4 Submit a Dimensional Inspection Request**

Once you have added the dimensional inspection request, the **Request Status** column in the **Dimensional Inspection List** page is appeared with[![image-1651249119857.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249119857.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249119857.png)(Submit and Reject icons). See Fig 5.12.

1. If you want to submit the dimensional inspection request, click [![image-1651249148290.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249148290.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249148290.png)(Submit icon) in the ****Request Status**** Otherwise click [![image-1651249175802.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249175802.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249175802.png) (Reject icon) to reject the request.

The submitted request will be moved to for the dimensional inspection.

#### **5.12.5 Add Results of Dimensional Inspection**

After completing the dimensional inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click[![image-1651249268524.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249268524.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249268524.png) (Add icon) in the **Results** column of the respective request.
    
    The **Dimensional Inspection List** window opens with a list of added spools.
    
    [![image-1651249285565.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249285565.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249285565.png)
2. In the ****Result**** column, select the result for each spool from the given result options.
3. In the ****Pipe Size**** column, select the result of pipe size.
4. In the ****Dimension**** column, select the result of pipe dimension.
5. In the ****Flange**** column, select the result of flange.
6. In the ****Orientation**** column, select the result of orientation.
7. In the ****Remarks**** box, enter your remarks if any.
8. Click ****Save****.

#### **5.12.6 View a Dimensional Inspection Report**

If you want to view a dimensional inspection report, click[![image-1651249434239.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651249434239.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651249434239.png) (print icon) provided in the **Print** column of the **Dimensional Inspection List** page. See Fig 5.12.

#### **5.12.7 Attach a File into a Dimensional Inspection Request** 

If you want to attach a file with an existing dimensional inspection request listed in the **Dimensional Inspection List** page, you can attach the file by using [![image-1651250022599.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250022599.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250022599.png)(Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”

#### **5.12.8 Export Dimensional Inspection Request List**

You can export a list of dimensional inspection requests added in the **Dimensional Inspection List** page in both the pdf and excel formats by using [![image-1651250180423.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250180423.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250180423.png) (**PDF** button) and [![image-1651250189837.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250189837.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250189837.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.12.9 Filter a Dimensional Inspection Request**

If you want to filter any dimensional inspection request in the **Dimensional Inspection List** page, you can use [![image-1651250230314.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250230314.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250230314.png) (**FILTER** button) located on the **Dimensional Inspection List** page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.13 RFI Hydro Pressure**

Hydro Pressure Inspection is the technique in which pipes are tested at required design pressure of the pipes to check the leak and strength. You can add a request for hydro pressure inspection by using the **RFI Hydro Pressure** tab in the **Inspection** menu.

#### **5.13.1 Add an RFI Hydro Pressure Request**

If you want to add an RFI hydro pressure request, do the following steps,

1. Click **RFI Hydro Pressure** in the **Inspection** menu.
    
    The **RFI Hydro Pressure** page opens.
    
    [![image-1651250531524.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250531524.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250531524.png)
    
     **Figure 5.13: RFI Hydro Pressure page**
2. In the ****Inspection Date &amp; Time**** box, select the inspection date and time.
3. In the ****Sub Contractor**** box, select a sub-contractor from a drop-down list.
4. In the ****Acceptance Code**** box, enter the acceptance code detail.
5. In the ****Designation**** box, enter the designation detail.
6. In the ****Test Temperature**** box, enter the test temperature value.
7. In the ****Test Medium**** box, select the test medium from the drop-down list.
8. In the ****Requested By**** box, enter the name of a person who has requested the hydro pressure inspection.
9. In the ****Classification**** box, enter the classification detail.
10. In the **Drawing No** box, select the drawing number from a drop-down list.
11. In the ****Work Scope**** box, enter the work scope detail.
12. In the ****Cost Centre**** box, enter the cost centre detail.
13. In the ****Holding Time**** box, enter the holding time range.
14. In the ****Pressure Gauge No**** box, enter the pressure gauge number.
15. In the ****Location**** box, select the location where the inspection to be performed.
16. In the ****System**** box, select a system from a drop-down list.
17. In the ****Procedure No**** box, enter the procedure number.
18. In the ****Design Pressure**** box, enter the design pressure range.
19. In the ****Test Pressure**** box, enter the test pressure range.
20. In the ****Instrument**** box, enter the instrument name.
21. In the ****P&amp;ID No**** box, enter the P&amp;ID number.
22. In the ****Remarks**** box, enter your remarks if any.
23. In the ****Description**** box, enter the description for the hydro pressure inspection. Before saving the added NDT request, you must add spools.
    
    [![image-1651250926040.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250926040.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250926040.png) **Note**: You can add multiple spools for one request.
    
    The **RFI Hydro Pressure** page shows a list of added spools. If you want to view the spools for the specific ISO drawing, select the respective ISO drawing from a drop-down list.
    
    [![image-1651250956304.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250956304.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250956304.png)
24. Click [![image-1651250973472.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250973472.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250973472.png) (Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
    
    [![image-1651250993402.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651250993402.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651250993402.png)
25. Click **Save Request**.

The hydro pressure inspection request will be added and listed in the **RFI Hydro Pressure** page.


### **5.14 View RFI Hydro Pressure**

The **View RFI Hydro Pressure** tab helps you to view and edit the hydro pressure inspection request, which is added by using the **RFI Hydro Pressure** tab. This tab also allows you to add a new hydro pressure request.

1. Click **View RFI Hydro Pressure** in the **Inspection** menu.
    
    The **RFI Hydro Pressure** page opens with a list of added hydro pressure requests.
    
    [![image-1651251102133.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251102133.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251102133.png)
    
     **Figure 5.14: RFI Hydro Pressure page**

#### **5.14.1 Add a Hydro Pressure Inspection Request**

If you want to add a hydro pressure inspection request, do the following steps,

1. Click [![image-1651251169548.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251169548.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251169548.png) (**ADD** button) in the **RFI Hydro Pressure** page.
    
    The system redirects you to a new page to add a new hydro pressure inspection request. To know how to add a hydro pressure inspection request, See the topic, “[**<u>Add a Hydro Pressure Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.13.1%C2%A0add-an-rfi-hy)”.

Once you have added the hydro pressure inspection request, you must submit the added request to perform hydro pressure inspection.

#### **5.14.2 Add Representative for Hydro Pressure Inspection Request**

If you want to add a representative for any added hydro pressure inspection request,

1. Click [![image-1651251248556.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251248556.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251248556.png)(Edit icon) in the **Representative** column for the respective hydro pressure inspection request.
    
    The **Edit Form** window opens.
    
    [![image-1651251269633.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251269633.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251269633.png)
2. In the ****Representative**** box, enter the name of a representative.
3. In the ****Inspection Date**** box, select the date of inspection.
4. In the **Remarks** box, enter your remarks if any.
5. Click **Save**.

#### **5.14.3 Edit a Hydro Pressure Inspection Request** 

If you want to edit any existing hydro pressure inspection request in the **RFI Hydro Pressure page, do the following,

1. Click [![image-1651251445172.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251445172.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251445172.png) (Edit icon) in the ****Edit**** column for the respective hydro pressure inspection See Fig 5.14. The **RFI Hydro Pressure** page opens with the details of the selected hydro pressure inspection request.
    
    [![image-1651251470057.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251470057.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251470057.png)
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.14.4 Submit and Approve a Hydro Pressure Inspection Request**

Once you have added the hydro pressure inspection request, the **Submission** column in the **RFI Hydro Pressure** page is appeared with [![image-1651251535766.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251535766.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251535766.png) (Submit and Reject icons).

1. If you want to submit the hydro pressure inspection request, click [![image-1651251564393.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251564393.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251564393.png) (Submit icon) in the ****Submission**** Otherwise click [![image-1651251581952.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251581952.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251581952.png) (Reject icon) to reject the request. Once you have submitted the hydro pressure inspection request, the **Request Status** column in the **RFI Hydro Pressure** page is appeared with [![image-1651251606585.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251606585.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251606585.png) (Approve and Reject icons).
2. If you want to approve the hydro pressure inspection request, click [![image-1651251658922.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251658922.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251658922.png) (Approve icon) in the **Request Status** Otherwise click [![image-1651251669174.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251669174.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251669174.png) (Reject icon) to reject the request. The hydro pressure inspection request will be moved for hydro pressure inspection.

#### **5.14.5 Add Results of Hydro Pressure Inspection**

After completing the hydro pressure inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651251727159.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251727159.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251727159.png) (Add icon) in the **Results** column of the respective request.
    
    The Result window opens a list of spools added for the particular request.
    
    [![image-1651251741652.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651251741652.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651251741652.png)
2. In the ****Result**** column, select the result of each spool from the given result options in the drop-down list.
3. In the ****Temperature**** column, enter the temperature value of each spool.
4. In the ****Start Time**** and ****End Time**** columns, enter the start and end times.
5. In the ****Hydrostatic Test Pressure**** column, enter the hydrostatic test pressure value.
6. In the ****Holding Time Duration**** column, enter the holding time duration.
7. In the ****Remarks**** column, enter your remarks if any.
8. In the ****Attachment**** column, you want to attach any document.
9. Click **Save**.

#### **5.14.6 View a Hydro Pressure Inspection Report**

If you want to view a hydro pressure inspection report, click [![image-1651287048018.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287048018.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287048018.png) (print icon) provided in the **Print** column of the **RFI Hydro Pressure** page. See Fig 5.14.

#### **5.14.7 Attach a File into a hydro pressure inspection Request** 

If you want o attach a file with any existing hydro pressure inspection request listed in the **RFI Hydro Pressure** page, you can attach the file by using [![image-1651287181565.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287181565.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287181565.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.14.8 View Signature Details of Inspectors**

You can view the sign details of the inspectors such as QA, Sub contractor, Client, and Owner, once they completed the hydro pressure inspection and submitted the inspection result details including their signature. To view the signature details, click [![image-1651287223020.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287223020.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287223020.png) (Sign icon) in the **Sign Details** column in the **RFI Hydro Pressure** page.

#### **5.14.9 Export Hydro Pressure Inspection Request List**

You can export a list of hydro pressure requests added in the **RFI Hydro Pressure** page in both the pdf and excel formats by using [![image-1651287259650.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287259650.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287259650.png) (**PDF** button) and [![image-1651287270024.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287270024.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287270024.png) (**Excel** button). To know how to export, see the topic, “[<u>**Export P&amp;ID list**</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.14.10 Filter a Hydro Pressure Inspection Request**

If you want to filter any specific hydro pressure inspection request in the **RFI Hydro Pressure** page, you can use [![image-1651287313019.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287313019.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287313019.png) (**FILTER** button) located on the **RFI Hydro Pressure** page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.15 RFI Painting and Blasting**

The **RFI Painting and Blasting** tab in the **Inspection** menu helps you to add an inspection request for painting and blasting in the piping project. To navigate to the painting and blasting inspection request adding page,

1. Click **RFI Painting and Blasting** in the **Inspection** menu.
    
    The **Blasting and Painting Inspection Record** page opens.
    
    [![image-1651287371263.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287371263.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287371263.png)
    
     **Figure 5.15: Painting and blasting Inspection Request page**

#### **5.15.1 Add a Painting and Blasting Inspection Request**

If you want to add a new painting and blasting inspection request, do the following steps.

1. In the ****Sub Contractor Name**** box, select a sub-contractor from a drop-down list.
2. In the **Inspection Date** **and Time** box, select the date and time of painting and blasting inspection.
3. In the **Location** box, select the location where the painting and blasting inspection to be performed.
4. In the ****Drawing**** box, select a drawing from a drop-down list.
5. In the ****NDT Procedure**** box, select an NDT procedure from a drop-down list.
6. In the ****Coating P.O No**** box, enter the purchase order number of coating.
7. In the ****Shift**** box, enter the shit detail. Before saving the added painting and blasting request, you must add spools. You can add multiple spools for one painting and blasting request.
    
    [![image-1651287622339.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287622339.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287622339.png) **Note**: The page shows a list of added spools. If you want to view the specific spools, use the filter options provided in the **Line Number**, **Drawing Number**, and **Spool Number** columns.
8. Select the checkbox of the respective spool which you want to add.
9. In the **Prepared By** box, enter the name of a person who has prepared the painting and blasting request.
10. In the ****Prepared Date**** box, select the prepared date of the painting and blasting request.
11. In the ****Reviewed By**** box, enter the name of a person who has reviewed the painting and blasting request.
12. In the ****Reviewed Date**** box, select the reviewed date of the painting and blasting request.
13. In the ****Approved By**** box, enter the name of a person who has approved the painting and blasting request.
14. In the ****Approved Date**** box, select the approved date of the painting and blasting request.
15. In the **Remarks** box, enter your remarks if any.
16. Click **Send Request**.

The painting and blasting inspection request will be added and listed in the **Blasting and Painting Inspection List** page.


### **5.16 View Painting and Blasting**

The **View Painting and Blasting** tab helps you to view and edit the painting and blasting inspection request, which is added by using the **RFI Painting and Blasting** tab. This tab also allows you to add a new painting and blasting inspection request.

1. Click **View Painting and Blasting** in the **Inspection** menu.
    
    The **Blasting and Painting Inspection List** page opens with a list of added painting and blasting requests.
    
    [![image-1651287888234.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651287888234.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651287888234.png)
    
     **Figure 5.16: Blasting and Painting Inspection List page**

#### **5.16.1 Add a Painting and Blasting Inspection Request**

If you want to add a painting and blasting inspection request, do the following steps,

1. Click (**ADD** button) in the ****Blasting and Painting Inspection List**** page. The system redirects you to the **RFI Painting and Blasting** page to add a new painting and blasting inspection request. To know how to add a painting and blasting inspection request, See the topic, “[**<u>Add a Painting and Blasting Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.15.1-add-a-paintin)”.

Once you have added the painting and blasting inspection request, you must submit the added request to perform the painting and blasting inspection.

#### **5.16.2 Edit a Painting and Blasting Inspection Request** 

If you want to edit any existing painting and blasting inspection request in the **Blasting and Painting Inspection List page, do the following steps,

1. Click [![image-1651288073148.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288073148.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288073148.png) (Edit icon) in the **Edit** column for the respective painting and blasting inspection request. See Fig 5.16.
    
    The **RFI Painting and Blasting** page opens with the details of the selected painting and blasting inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.16.3 Submit and Approve a Painting and Blasting Inspection Request**

Once you have added the painting and blasting inspection request, the **Submission** column in the **Blasting and Painting Inspection List** page is appeared with [![image-1651288752267.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288752267.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288752267.png) (Submit and Reject icons).

1. If you want to submit the painting and blasting inspection request, click [![image-1651288796183.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288796183.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288796183.png) (Submit icon) in the **Submission** Otherwise click [![image-1651288814438.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288814438.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288814438.png) (Reject icon) to reject the request. Once you have submitted the painting and blasting inspection request, the **Request Status** column in the **Blasting and Painting Inspection List** page is appeared with [![image-1651288827171.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288827171.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288827171.png)(Approve and Reject icons).
2. If you want to approve the painting and blasting inspection request, click [![image-1651288870796.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288870796.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288870796.png) (Approve icon) in the **Request Status** column. Otherwise click [![image-1651288880436.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288880436.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288880436.png) (Reject icon) to reject the request.
    
    The painting and blasting inspection request will be moved for painting and blasting inspection.

#### **5.16.4 Add RFI Data for Piping and Blasting Inspection**

If you want to add the details of RFI data for the added piping and blasting inspection request, do the following steps,

1. Click [![image-1651288950684.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288950684.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288950684.png)(Edit icon) in the ****RFI Data**** column of the ****Blasting and Painting Inspection List****  See Fig 5.16. The **RFI Inspection Request List** window opens.
    
    [![image-1651288975818.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651288975818.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651288975818.png)
2. In the ****Inspection From**** box, enter the detail from where the inspection should start.
3. In the ****Inspection To**** box, enter the detail to where the inspection should end.
4. In the ****Inspection Details**** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the ****Others**** box, enter any other inspection related details.
6. In the ****Refer to Report No**** box, enter the report number for reference.
7. In the ****RFI Date**** box, choose the RFI date.
8. In the ****Inspection Result**** option, if the inspection result is accepted, select ****Accepted**** otherwise select ****Rejected****.
9. In the ****Remarks**** box, enter your remarks if any.
10. In the ****Inspected by**** box, enter the name of a person who has done inspection.
11. In the ****Inspected Date**** box, choose the date of inspection.
12. In the ****Witnessed By**** box, enter the name of the witnessed person.
13. In the ****Witnessed Date**** box, choose the date of witnessed.
14. In the ****PCML Rep Name**** box, enter the representative name of PCML.
15. In the ****PCML Rep Date**** box, choose the PCML rep date.
16. In the ****MEB Rep Name**** box, enter the representative name of MEB.
17. In the ****MEB Rep Date box****, choose MEB rep date.
18. Click ****Save****.

The RFI data for the painting and blasting inspection is added successfully.

#### **5.16.5 View a Painting and Blasting Inspection Report**

If you want to view a painting and blasting inspection report, click [![image-1651289673254.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651289673254.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651289673254.png) (print icon) provided in the **Print** column of the **Blasting and Painting Inspection List** page. See Fig 5.16.

#### **5.16.6 Attach a File into a Painting and Blasting Inspection Request** 

If you want to attach a file with any existing painting and blasting inspection request listed in the **Blasting and Painting Inspection List page, you can attach the file by using [![image-1651289717873.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651289717873.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651289717873.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.16.7 Export Painting and Blasting Inspection Request List**

You can export a list of painting and blasting requests added in the **Blasting and Painting Inspection List** page in both the pdf and excel formats by using [![image-1651290009919.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290009919.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290009919.png) (**PDF** button) and [![image-1651290023068.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290023068.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290023068.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.16.8 Filter a Painting and Blasting Inspection Request**

If you want to filter any specific painting and blasting inspection request in the **Blasting and Painting Inspection List** page, you can filter the request based on the **Spool No** filter box.

[![image-1651290067747.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290067747.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290067747.png)

#### **5.16.9 View a Painting and Blasting Summary Report**

If you want to view a painting and blasting summary report,

1. Click [![image-1651290126047.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290126047.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290126047.png)(print icon) provided in the upper side of the ******Blasting and Painting Inspection List****** page. The **Blasting &amp; Painting Summary Report** page opens.
2. In the ****ISO Drawing No**** box, select the ISO drawing number.
3. In the ****Spool No**** box, select the spool number.
4. Click ****Go****. The paining and blasting summary report detail opens.
    
    [![image-1651290187685.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290187685.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290187685.png)


### **5.17 Other Application for Inspection (AFI) Requests or RFI Request – PWHT/PMI/Hardness/Ferrite**

The **Other AFI Requests** tab in the **Inspection** menu helps you to add other AFI requests such as PWHT, PMI, Hardness and Ferrite requests.

1. Click **Other AFI Requests** in the **Inspection** menu. The **RFI Request for PWHT/PMI/Hardness/Ferrite** page opens.
    
    [![image-1651290253343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290253343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290253343.png)
    
     **Figure 5.17: RFI Request for PWHT/PMI/Hardness/Ferrite page**


#### **5.17 Add an AFI Request**

If you want to add an AFI request, do the following steps,

1. Click (**ADD** button) in the **RFI Request for PWHT/PMI/Hardness/Ferrite** page. The page opens a new window to add the details of the AFI request.
    
    [![image-1651290324578.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290324578.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290324578.png)
2. In the ****Requested By**** box, enter the name of a person who has requested the AFI inspection.
3. In the ****To**** box, select the sub-contractor for the AFI inspection.
4. In the **Location** box, select a location from a drop-down list.
5. In the ****Inspection Date and Time**** box, select the inspection date and time.
6. In the ****Requisition**** box, enter the requisition detail of the AFI inspection.
7. In the ****Drawing No**** box, select the drawing number from a drop-down list.
8. In the ****Designation**** box, enter the designation detail.
9. In the ****Cost Centre**** box, enter the cost centre detail.
10. In ****System**** box, select a system from a drop-down list.
11. In the ****Type**** box, select the type of AFI for which you want to add request.
12. In the ****Test Description**** box, enter the test description detail. Before saving the added request, you must add joints. You can add multiple joints for one request.
    
    [![image-1651290965332.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290965332.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290965332.png)**Note**: The page shows a list of added joints. If you want to view the joints for the specific isometric drawing, use the filter option.
    
    [![image-1651290979529.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290979529.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290979529.png)
13. Click [![image-1651290989725.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651290989725.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651290989725.png) (Add icon) of the respective joint which you want to add. The added joints will be moved to the right side of the page.
    
    [![image-1651291007916.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291007916.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291007916.png)
14. Click **Save**. The AFI inspection request will be added and listed in the **RFI Request for PWHT/PMI/ Hardness /Ferrite page. Once you have added the AFI inspection request, you must submit the added request to perform the respective inspection.

#### **5.17.2 Edit an AFI Inspection Request** 

If you want to edit any existing AFI inspection request in the **RFI Request for PWHT/PMI/ Hardness /Ferrite page, do the following steps,

1. Click [![image-1651291099821.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291099821.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291099821.png) (Edit icon) in the **Edit** column for the respective AFI request. See Fig 5.17.
    
    The page shows the details of the selected AFI request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.17.3 Submit and Approve an AFI Inspection Request**

Once you have added the AFI inspection request, the **Submission** column in the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page is appeared with [![image-1651291175048.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291175048.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291175048.png) (Submit and Reject icons).

1. If you want to submit the AFI inspection request, click [![image-1651291235900.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291235900.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291235900.png)(Submit icon) in the ****Submission**** Otherwise click [![image-1651291244895.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291244895.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291244895.png) (Reject icon) to reject the request. Once you have submitted the AFI inspection request, the **Request Status** column in the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page is appeared with (Approve and Reject icons).
2. If you want to approve the AFI inspection request, click [![image-1651291297042.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291297042.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291297042.png)(Approve icon) in the **Request Status** Otherwise click [![image-1651291311258.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651291311258.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651291311258.png)(Reject icon) to reject the request. The AFI inspection request will be moved for inspection.

#### **5.17.4 Add RFI Data for an AFI Inspection Request**

If you want to add the details of RFI data for the added AFI inspection request, do the following steps,

1. Click (Edit icon) in the **RFI Data** column of the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page. See Fig 5.17. The **RFI Inspection Request List** window opens.
    
    [![image-1651294586880.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651294586880.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651294586880.png)
2. In the ****Inspection From**** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the **Inspection Details** option, select 1<sup>st</sup> Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the ****Others**** box, enter any other inspection related details.
6. In the ****Refer to Report No**** box, enter the report number for reference.
7. In the ****RFI Date**** box, choose the RFI date.
8. In the ****Inspection Result**** option, if the inspection result is accepted, select ****Accepted**** otherwise select ****Rejected****.
9. In the ****Remarks**** box, enter your remarks if any.
10. In the ****Inspected by**** box, enter the name of a person who has done inspection.
11. In the ****Inspected Date**** box, choose the date of inspection.
12. In the ****Witnessed By**** box, enter the name of the witnessed person.
13. In the ****Witnessed Date**** box, choose the date of witnessed.
14. In the ****PCML Rep Name**** box, enter the representative name of PCML.
15. In the ****PCML Rep Date**** box, choose the PCML rep date.
16. In the ****MEB Rep Date box****, choose MEB rep date.
17. Click ****Save****. The RFI data for the AFI inspection is added successfully.

#### **5.17.5 View an AFI Inspection Report**

If you want to view an AFI inspection report, click[![image-1651295130244.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651295130244.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651295130244.png) (print icon) provided in the **Print** column of the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page. See Fig 5.17.

#### **5.17.6 Export AFI Inspection Request List**

You can export a list of AFI requests added in the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page in both the pdf and excel formats by using (**PDF** button) and (**Excel** button). To know how to export, see the topic, “**[<u>Export P&amp;ID list</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)**”.

#### **5.17.7 Filter an AFI Inspection Request**

If you want to filter any specific AFI inspection request in the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page, you can use [![image-1651295192194.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651295192194.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651295192194.png) (**FILTER** button) located on the **RFI Request for PWHT/PMI/ Hardness /Ferrite** page. To know how to filter, see the topic, “**[<u>Filter P&amp;ID</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)**”.


### **5.18 Painting &amp; Coasting FIR**

The **Painting Coasting FIR** tab in the Inspection menu helps you to add a painting &amp; coasting FIR.

To navigate to the painting and coating FIR adding page,

1. Click ****Painting Coasting FIR**** in the ****Inspection**** menu. The **Painting &amp; Coasting FIR** page opens.
    
    [![image-1651295417038.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651295417038.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651295417038.png)
    
     **Figure 5.18: Painting &amp; Coasting FIR page**

#### **5.18.1 Add a Painting and Coasting FIR**

If you want to add a new painting and coasting FIR, do the following steps.

1. In the **Sub Contractor Name** box, select a sub-contractor from a drop-down list.
2. In the **Inspection Date** **and Time** box, select the date and time of painting and blasting inspection.
3. In the ****Location**** box, select the location where the painting and coasting inspection to be performed.
4. In the ****Reference** **Drawing**** box, select a reference drawing from a drop-down list.
5. In the ****System**** box, select a system from a drop-down list.
6. In the ****No** **of Coat Applied**** box, enter the number of applied coating.
7. In the ****Shift**** box, enter the shift detail.
8. In the ****Specification**** box, enter the specification detail.
9. In the ****Job/Item Description**** box, enter the description for the job/item.
10. In the ****Painted Surface**** box, enter the painted surface detail.
11. In the ****Client Paint Specification**** box, enter the client paint specification detail.
12. In the ****Surface Preparation**** box, enter the surface preparation detail.
13. In the ****Painting/Coating Type**** box, enter the painting/coating type.
14. In the ****Visual Inspection**** box, enter the visual inspection detail.
15. In the ****Top Coat D.F.T**** box, enter the top coat detail.
16. In the ****Degree of Cured**** box, enter the degree of cured.
17. In the ****Pinhole Testing**** box, enter the pinhole testing detail.
18. In the ****Wet Sponge Method**** box, enter the wet sponge method detail.
19. In the ****Holiday Detection**** box, enter the holiday detection detail.
20. In the ****Brush Coil**** box, enter the brush coil detail.
21. In the ****V Setting (For Pipeline)****box, enter the K.V setting detail for pipeline. Before saving the added painting and coasting request, you must add spools. You can add multiple spools for one painting and coasting request.
    
    [![image-1651296172594.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296172594.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296172594.png)**Note**: The page shows a list of added spools. If you want to view the specific spools, use the filter options provided in the **Line Number**, **Drawing Number**, and **Spool Number** columns.
22. Select the checkbox of the respective spool which you want to add.
23. In the **Prepared By** box, enter the name of a person who has prepared the painting and coasting request.
24. In the ****Prepared Date**** box, select the prepared date of the painting and coasting request.
25. In the ****Reviewed By**** box, enter the name of a person who has reviewed the painting and coasting request.
26. In the ****Reviewed Date**** box, select the reviewed date of the painting and coasting request.
27. In the ****Approved By**** box, enter the name of a person who has approved the painting and coasting request.
28. In the **Approved Date** box, select the approved date of the painting and coasting request.
29. In the **Remarks** box, enter your remarks if any.
30. Click **Send Request**.

The painting and coasting inspection request will be added and listed in the **Panting and Coasting FIR** page.


### **5.19 View Painting &amp; Coasting FIR**

The **View Painting and Coasting** tab helps you to view and edit the painting and coasting FIR, which is added by using the **Painting &amp; Blasting FIR** tab. This tab also allows you to add a new painting and coasting inspection request.

1. Click **View Painting and Coasting** in the **Inspection** menu.
    
    The **Painting Coasting FIR** page opens with a list of added painting and coasting FIRs.
    
    [![image-1651296366319.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296366319.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296366319.png)
    
     **Figure 5.19: Painting Coasting FIR page**

#### **5.19.1 Add a Painting and Coasting FIR**

If you want to add a painting and coasting FIR, do the following steps,

1. Click [![image-1651296450154.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296450154.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296450154.png) (****ADD**** button) in the ****Painting Coasting FIR**** page. The system redirects you to the **Painting &amp; Coasting FIR** page to add a new painting and coasting request. To know how to add a painting and coasting inspection request, See the topic, “[**<u>Add a Painting and Coasting FIR</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.18.1%C2%A0add-a-paintin)”.

Once you have added the painting and coasting inspection request, you must submit the added request to perform the painting and coasting inspection.

#### **5.19.2 Edit a Painting and Coasting FIR** 

If you want to edit any existing painting and coasting inspection request in the **Painting Coasting FIR** page, do the following steps,

1. Click [![image-1651296571420.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296571420.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296571420.png)(Edit icon) in the **Edit** column for the respective painting and coasting inspection request. See Fig 5.19.
    
    The **Painting and Coasting FIR** page opens with the details of the selected painting and coasting inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.19.3 Submit and Approve a Painting and coasting FIR**

Once you have added the painting and coasting inspection request, the **Submission** column in the **Painting Coasting FIR** page is appeared with [![image-1651296641794.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296641794.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296641794.png)(Submit and Reject icons).

1. If you want to submit the painting and coasting inspection request, click [![image-1651296694368.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296694368.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296694368.png) (Submit icon) in the **Submission** column. Otherwise click [![image-1651296710718.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296710718.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296710718.png) (Reject icon) to reject the request.
    
    Once you have submitted the painting and coasting inspection request, the **Request Status** column in the **Painting Coasting FIR** page is appeared with [![image-1651296791263.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296791263.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296791263.png) (Approve and Reject icons).
2. If you want to approve the painting and coasting inspection request, click [![image-1651296823161.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296823161.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296823161.png)(Approve icon) in the **Request Status** column. Otherwise click [![image-1651296832797.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651296832797.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651296832797.png) (Reject icon) to reject the request.
    
    The painting and coasting inspection request will be moved for painting and coasting inspection.

#### **5.19.4 Add RFI Data for Painting and Coasting Inspection**

If you want to add the details of RFI data for the added painting and coasting inspection request, do the following steps,

1. Click[![image-1651297402429.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297402429.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297402429.png) (Edit icon) in the ****RFI Data**** column of the ****Painting Coasting FIR****  See Fig 5.19. The **RFI Inspection Request List** window opens.
    
    [![image-1651297427253.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297427253.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297427253.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the ****Inspection To**** box, enter the detail to where the inspection should end.
4. In the ****Inspection Details**** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the ****Others**** box, enter any other inspection related details.
6. In the ****Refer to Report No**** box, enter the report number for reference.
7. In the ****RFI Date**** box, choose the RFI date.
8. In the ****Inspection Result**** option, if the inspection result is accepted, select ****Accepted**** otherwise select ****Rejected****.
9. In the ****Remarks**** box, enter your remarks if any.
10. In the ****Inspected by**** box, enter the name of a person who has done inspection.
11. In the ****Inspected Date**** box, choose the date of inspection.
12. In the ****Witnessed By**** box, enter the name of the witnessed person.
13. In the ****Witnessed Date**** box, choose the date of witnessed.
14. In the ****PCML Rep Name**** box, enter the representative name of PCML.
15. In the ****PCML Rep Date**** box, choose the PCML rep date.
16. In the ****MEB Rep Name**** box, enter the representative name of MEB.
17. In the ****MEB Rep Date box****, choose MEB rep date.
18. Click ****Save****. The RFI data for the painting and coasting inspection is added successfully.

#### **5.19.5 View an RFI Report**

If you want to view an RFI report, click [![image-1651297756957.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297756957.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297756957.png)(print icon) provided in the **RFI Report** column of the **Painting Coasting FIR** page. See Fig 5.19.

#### **5.19.6 View a Painting and Coasting FIR Report**

If you want to view a painting and coasting FIR report, click [![image-1651297807548.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297807548.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297807548.png) (print icon) provided in the **Print** column of the **Painting Coasting FIR** page. See Fig 5.19.

#### **5.19.7 Attach a File into a Painting and Coasting FIR**

If you want to attach a file with any existing painting and coasting inspection request listed in the **Painting Coasting FIR** page, you can attach the file by using (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.19.8 Export Painting and Coasting FIR List**

You can export a list of painting and coasting requests added in the **Painting Coasting FIR** page in both the pdf and excel formats by using [![image-1651297892649.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297892649.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297892649.png) (**PDF** button) and [![image-1651297901162.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297901162.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297901162.png) (**Excel** button). To know how to export, see the topic, “[<u>**Export P&amp;ID list**</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.19.9 Filter a Painting and Coasting FIR**

If you want to filter any specific painting and coasting inspection request in the **Painting Coasting FIR** page, you can filter the request based on the **Spool No** filter box. [![image-1651297953730.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651297953730.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651297953730.png)


### **5.20 Final Inspection Report**

The **Final Inspection Report** tab in the **Inspection** menu helps you to add a final inspection report. To navigate to the final inspection report adding page,

1. Click **Final Inspection Report** in the **Inspection** menu.
    
    The **Final Inspection Report** page opens with a **Weld Map Drawing Detail** window.
    
    [![image-1651298030230.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651298030230.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651298030230.png) **Figure 5.20: Final Inspection Report page**

#### **5.20.1 Add a Final Inspection Report**

If you want to add a new final inspection report, do the following steps,

1. In the **Sub Contractor Name** box, select a sub-contractor from a drop-down list.
2. In the ****Inspection Date** **and Time**** box, select the date and time of final inspection.
3. In the ****Location**** box, select the location where the final inspection to be performed.
4. In the ****Paint System No**** box, enter the paint system number.
5. In the ****System/Area**** box, enter the system/area name.
6. In the ****Sub System No**** box, enter the sub system number.
7. In the ****Shift**** box, enter the shift detail.
8. In the ****Specification**** box, enter the specification detail.
9. In the ****Job/Item Description**** box, enter the description for the job/item.
10. In the ****Painted Surface**** box, enter the painted surface detail.
11. In the ****Client Paint Specification**** box, enter the client paint specification detail.
12. In the ****Surface Preparation**** box, enter the surface preparation detail.
13. In the ****Painting/Coating Type**** box, enter the painting/coating type.
14. In the ****Visual Inspection**** box, enter the visual inspection detail.
15. In the ****Top Coat D.F.T**** box, enter the top coat detail.
16. In the ****Degree of Cured**** box, enter the degree of cured.
17. In the ****Pinhole Testing**** box, enter the pinhole testing detail.
18. In the ****Wet Sponge Method**** box, enter the wet sponge method detail.
19. In the ****Holiday Detection**** box, enter the holiday detection detail.
20. In the ****Brush Coil**** box, enter the brush coil detail.
21. In the ****V Setting (For Pipeline)**** box, enter the K.V setting detail for pipeline.
22. In the ****No of Coat Applied**** box, enter the number of coats applied. Before saving the added final inspection request, you must add weld map drawing detail.
23. Click [![image-1651298457300.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651298457300.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651298457300.png) (**ADD** button) in the **Weld Map Drawing Detail** window. See Figure 5.19.
    
    The **Edit Form** window shows a new window to add the details of weld map drawing.
    
    [![image-1651298474872.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651298474872.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651298474872.png)
24. In the **Weld Map Drawing No** box, enter the weld map drawing number.
25. In the **Sheet No** box, enter the sheet number.
26. In the **Revision** box, enter the revision for the weld map drawing.
27. In the **Description** box, enter the description for the weld map drawing.
28. In the **Quantity** box, enter the quantity of the weld map drawing.
29. In the **Remarks** box, enter your remarks if any.
30. Click **Update**.
    
    The weld map drawing is updated.
31. In the ****Prepared By**** box, enter the name of a person who has prepared the final inspection request.
32. In the ****Prepared Date**** box, select the prepared date of the final inspection request.
33. In the ****Reviewed By**** box, enter the name of a person who has reviewed the final inspection request.
34. In the ****Reviewed Date**** box, select the reviewed date of the final inspection request.
35. In the ****Approved By**** box, enter the name of a person who has approved the final inspection request.
36. In the ****Approved Date**** box, select the approved date of the final inspection request.
37. In the **Remarks** box, enter your remarks if any.
38. Click **Send Request**. The final inspection request will be added and listed in the **Final Inspection Report** page.


### **5.21 View Final Inspection Report**

The **View Final Inspection Report** tab helps you to view and edit the final inspection request, which is added by using the **Final Inspection Report** tab. This tab also allows you to add a new final inspection request.

1. Click **View Final Inspection Report** in the **Inspection** menu.
    
    The **Final Inspection Report** page opens with a list of added final inspection reports.
    
    [![image-1651298703752.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651298703752.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651298703752.png) **Figure 5.21: View Final Inspection Report page**

#### **5.21.1 Add a Final Inspection Report**

If you want to add a final inspection report, do the following steps,

1. Click [![image-1651298840283.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651298840283.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651298840283.png) (**ADD** button) in the **View** **Final Inspection Report** page.
    
    The system redirects you to the **Final Inspection Report** page to add a new final inspection report. To know how to add a final inspection report, See the topic, “[**<u>Add a Final Inspection Report</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.20.1%C2%A0add-a-final-i)”.

Once you have added the final inspection report, you must submit the added report to perform the final inspection.

#### **5.21.2 Edit a Final Inspection Report**

If you want to edit any existing final inspection report in the **Final Inspection Report** page, do the following steps,

1. Click [![image-1651298970266.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651298970266.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651298970266.png) (Edit icon) in the **Edit** column for the respective final inspection report. See Fig 5.21.
    
    The **Final Inspection Report** page opens with the details of the selected final inspection report.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.21.3 Submit and Approve a Final Inspection Report**

Once you have added the final inspection report, the **Submission** column in the **Final Inspection Report** page is appeared with [![image-1651299063545.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651299063545.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651299063545.png) (Submit and Reject icons).

1. If you want to submit the final inspection report, click [![image-1651299100573.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651299100573.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651299100573.png)(Submit icon) in the **Submission** column. Otherwise click [![image-1651299113955.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651299113955.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651299113955.png)(Reject icon) to reject the request.
    
    Once you have submitted the final inspection report, the **Request Status** column in the **Final Inspection Report** page is appeared with [![image-1651299143065.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651299143065.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651299143065.png)(Approve and Reject icons).
2. If you want to approve the final inspection report, click (Approve icon) in the ****Request Status**** Otherwise click (Reject icon) to reject the request. The final inspection report will be moved for final inspection.

#### **5.21.4 Add RFI Data for a Final Inspection Report**

If you want to add the details of RFI data for the added final inspection report, do the following steps,

1. Click [![image-1651299842353.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651299842353.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651299842353.png) (Edit icon) in the ****RFI Data**** column of the ****Final Inspection Report****  See Fig 5.21. The **RFI Inspection Request List** window opens.
    
    [![image-1651300057471.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300057471.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300057471.png)
2. In the ****Inspection From**** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the **Inspection To** box, enter the detail to where the inspection should end.
5. In the **Others** box, enter any other inspection related details.
6. In the ****Refer to Report No**** box, enter the report number for reference.
7. In the ****RFI Date**** box, choose the RFI date.
8. In the ****Inspection Result**** option, if the inspection result is accepted, select ****Accepted**** otherwise select ****Rejected****.
9. In the ****Remarks**** box, enter your remarks if any.
10. In the ****Inspected by**** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the ****Witnessed By**** box, enter the name of the witnessed person.
13. In the ****Witnessed Date**** box, choose the date of witnessed.
14. In the ****PCML Rep Name**** box, enter the representative name of PCML.
15. In the ****PCML Rep Date**** box, choose the PCML rep date.
16. In the ****MEB Rep Name**** box, enter the representative name of MEB.
17. In the ****MEB Rep Date box****, choose MEB rep date.
18. Click ****Save****. The RFI data for the final inspection report is added successfully.

#### **5.21.5 View an RFI Report**

If you want to view an RFI report, click [![image-1651300381418.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300381418.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300381418.png) (print icon) provided in the **RFI Report** column of the **Final Inspection Report** page. See Fig 5.21.

#### **5.21.6 View a Final Inspection Report**

If you want to view a final inspection report, click [![image-1651300440368.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300440368.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300440368.png)(print icon) provided in the **Print** column of the **Final Inspection Report** page. See Fig 5.21.

#### **5.21.7 Attach a File into a Final Inspection Report**

If you want to attach a file with any existing final inspection report listed in the **Final Inspection Report** page, you can attach the file by using [![image-1651300515525.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300515525.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300515525.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.21.8 Export Final Inspection Report List**

You can export a list of final inspection reports added in the **Final Inspection Report** page in both the pdf and excel formats by using [![image-1651300568875.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300568875.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300568875.png) (**PDF** button) and [![image-1651300578458.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300578458.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300578458.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.


### **5.22 Generate Daily Pipe Welder Record (DPWR)**

The **Generate Daily Pipe Welder Record** tab in the **Inspection** menu helps you to generate a DPWR.

1. Click ****Generate Daily Pipe Welder Record**** in the ****Inspection**** menu. The **Daily Pipe Welder Record** page opens.
    
    [![image-1651300910465.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651300910465.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651300910465.png)
    
     **Figure 5.22: Daily Pipe Welder Record** **page**

The **Daily Pipe Welder Record** page shows the list of welding completed on each day including the details of the welder, location, and report type.

- In this page, the welding completed details are grouped based on the respective date.
- Each group has a maximum of 20 number of welding.
- Each group is separated by different group number.
- You can generate a report for each group individually by using the respective report generating option provided in the ****Daily** **Pipe** **Welder Record**** page.

2\. If you want to generate report of DPWR for any group or date, click [![image-1651301045470.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651301045470.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651301045470.png) (**Generate Report** button) of the respective group or date.

The generated reports will be moved to the [**<u>Daily </u><u>Pipe</u><u> Welder Record</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.23%C2%A0daily-pipe-weld) page. To view the generated reports, navigate to the [**<u>Daily Pipe Welder Record</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.23%C2%A0daily-pipe-weld) tab.


### **5.23 Daily Pipe Welder Record (DWPR)**

The **Daily Pipe Welder Record** tab in the **Inspection** menu helps you to view a DPWR report, which is generated using the **Generate** **Daily Pipe Welder Record** tab. To view the generated report,

1. Click ****Daily** **Pipe** **Welder Record**** in the ****Inspection**** menu. The **Daily Pipe Welder Record** page opens including the generated DPWR reports.
    
    [![image-1651301244398.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651301244398.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651301244398.png)
    
     **Figure 5.23: Daily Pipe Welder Record page**
    
    The generated DPWR reports are listed based on the welding date.
2. If you want to view the DPWR report for any particular date, click (Expand icon) of the respective date.
    
    The **Reports** window opens including the report number and report type.
3. Click [![image-1651301402867.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651301402867.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651301402867.png)(****Print**** icon) in the ******Print******  column. The Report will be opened.
    
    [![image-1651301449911.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651301449911.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651301449911.png)


### **5.24 Individual Pipe Welder Record**

The **Individual Pipe Welder Record** tab in the **Inspection** menu used to view the completed pipe welding details of each welder individually.

1. Click **Individual Pipe Welder Record** in the **Inspection** menu.
    
    The **Individual Pipe Welder Record** page opens.
    
    [![image-1651301719384.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651301719384.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651301719384.png)
    
     **Figure 5.24: Individual Pipe Welder Record page**
2. In the **Welder** box, select a welder from a drop-down list.
3. In the **Joint Category** box, select a joint category from the given option.
    
    The completed welding details of selected welder will be displayed.


#### **5.25 Weekly Welders Performance Record**

If you want to view the performance record of welders on weekly basis, navigate to the **Weekly Welders Performance Record** tab in the **Inspection** menu.

1. Click ****Weekly Welders Performance Record**** in the ****Inspection**** menu. The **Weekly Welders Performance Record** page opens.
    
    [![image-1651301904025.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651301904025.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651301904025.png)
    
     **Figure 5.25: Weekly Welders Performance Record page**
2. If you want to view the performance record of welders for all the projects, select the checkbox of the **All Project** option.
3. In the **NDT Type** box, select the NDT type from a drop-down list.
4. In the ****Joint Category**** box, select the joint category of pipe whether ****Shop****, ****Field****, or ****All**** from a drop-down list.
5. In the ****From Date**** and ****To Date**** boxes, select the from and to dates.
6. Click ****Show Report****. The performance record of welders will be opened.
    
    [![image-1651304259967.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304259967.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304259967.png)

#### **5.25.1 Print a Weekly Welders Performance Record**

If you want to print a weekly welders performance record, use [![image-1651304335454.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304335454.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304335454.png) and [![image-1651304353011.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304353011.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304353011.png) (print icons) provided in the **Weekly Welders Performance Record** page.

1. If you want to print the current page of the weekly welder performance record, click [ ![image-1651304377904.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304377904.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304377904.png) (print icon including the page number).
2. If you want to print all the pages of the weekly welder performance record, click[![image-1651304426762.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304426762.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304426762.png) (print icon).

#### **5.25.2 Export a Weekly Welders Performance Record**

You can export the weekly welders performance record in various formats by using the option [![image-1651304479763.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304479763.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304479763.png) provided in the upper right corner of the **Weekly Welders Performance Record** page.


### **5.26 RFI and AFI Excel Import**

The **RFI and AFI Excel Import** tab in the **Inspection** menu helps you to upload various data related with RFI and AFI for different fields included in the **Project Data** menu instead of uploading data for each field individually. If you want to import data for different fields, do the following,

1. Click the ****RFI and AFI Excel Import**** tab in the ******Inspection****** menu. The **File Upload** page opens.
    
    [![image-1651304582162.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304582162.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304582162.png)
2. Download a template by clicking [![image-1651304618715.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304618715.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304618715.png) (****TEMPLATE**** button) to enter the details of RFI and AFI data. An excel worksheet will be downloaded as a pre-defined template.
3. Enter the relevant details in the respective column of the excel worksheet based on the columns listed in the ****System Column**** field.
4. Click [![image-1651304673383.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304673383.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304673383.png) (****Choose File**** button). Once the file has been uploaded successfully, you receive a message, “**Successfully uploaded**”
5. Click [![image-1651304786081.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304786081.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304786081.png) (**Get Columns** button).
    
    The columns added in the excel worksheet will be listed in the **Excel Column** field.
6. Click [![image-1651304832151.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304832151.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304832151.png). The system automatically maps the **System Column** field and the **Excel Column** field and displays in the **Mapped Columns** field.
    
    [![image-1651304860355.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304860355.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304860355.png)
7. If you want to map any columns or to unmap any mapped columns, select the respective columns and then click [![image-1651304881413.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304881413.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304881413.png) (****Map**** button) and [![image-1651304899901.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304899901.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304899901.png) (****UnMap**** button) accordingly. [![image-1651304929038.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304929038.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304929038.png) **Note**: If you want to unmap all columns, click [![image-1651304946162.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304946162.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304946162.png).
8. Once you have completed the mapping and un mapping of columns, in the **Upload Range From** and **To** fields, enter the range of rows you want to upload from the excel worksheet.
    
    [![image-1651304997061.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651304997061.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651304997061.png)**Note**: In the **Total Rows** field, the system indicates the total number of rows filled in the excel worksheet.
    
    [![image-1651305018953.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651305018953.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651305018953.png) **Tip**: You must enter the upload starting range as two in the **Upload Range From** field because a first row in the excel worksheet is having heading of the columns.
9. Click [![image-1651305592173.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651305592173.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651305592173.png) (****Populate Value**** button).
10. Click [![image-1651305624416.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651305624416.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651305624416.png) (**Process** button).
    
    Once you have clicked the Process button, the system processes the columns and displays in the **Excel Import** page.
    
    [![image-1651305449362.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651305449362.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651305449362.png)
11. Click [![image-1651305474379.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651305474379.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651305474379.png) (****Import**** button) to import the data added in the excel worksheet.

#### **5.27 RFI and AFI Joint Status**

The **RFI and AFI Joint Status** tab in the **Inspection** menu used to view the RFI and AFI fit up and weld inspection completed status for the joints.

1. Click **RFI and AFI Joint Status** in the ****Inspection.****The **RFI and AFI Joints Status** page opens.
    
    [![image-1651310952534.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651310952534.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651310952534.png)
    
     **Figure 5.27: RFI and AFI Joints Status page**

You can view the status of the joints by selecting one of the below options given in the page.

- Joints – RFI Fit up completed &amp; Ready for AFI Fit up
- Joints – AFI Fit up completed &amp; Ready for RFI Weld VI
- Joints – RFI Weld VI completed &amp; Ready for AFI Weld VI

For example, if you select the **Joints – AFI Fit up completed &amp; Ready for RFI Weld VI** option, then the system shows the list of joints which has completed the AFI fit up and are ready for RFI weld VI.

#### **5.27.1 Export the RFI and AFI Joints Status**

You can export the joint status including a list of joints in the **RFI and AFI Joints Status** page in both the pdf and excel formats by using [![image-1651336086938.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336086938.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336086938.png) (**PDF** button) and [![image-1651336097442.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336097442.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336097442.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.


### **5.28 RFI and AFI Status**

The **RFI and AFI Status** tab in the **Inspection** menu used to view and check the status of the RFI and AFI inspection status.

1. Click ****RFI and AFI Status**** in the ******Inspection****** menu. The **RFI and AFI Status** page opens.
    
    [![image-1651336176679.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336176679.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336176679.png)
    
     **Figure 5.28: RFI and AFI Status page**
    
    The page shows the total number of added RFI and AFI inspection requests, and also shows the number of completed and outstanding inspections.

#### **5.28.1 Export the RFI and AFI Status**

You can export the RFI and AFI status in both the pdf and excel formats by using [![image-1651336488936.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336488936.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336488936.png) (**PDF** button) and [![image-1651336500232.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336500232.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336500232.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.


### **5.29 Threaded Joint Report**

The **Threaded Joint Report** tab in the **Inspection** menu used to view and update the completed status of the threaded joints.

1. Click ****Threaded Joint Report**** in the ****Inspection**** menu. The **Threaded Joints** page opens.
    
    [![image-1651336585220.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336585220.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336585220.png)
    
     **Figure 5.29: Threaded Joints page**
2. In the ****Status**** column, select the status of the joints. If you select **Pending,** the page shows the details of the joints which are pending.
3. Click ****Search****.
4. In the ****Complete**** column, if the particular joint has completed then enable the checkbox of the respective joint.
5. In the ****Completed by**** box, enter the name of a person who has completed the joint work.
6. In the ****Completed Date**** box, select the completed date of the joint work.

#### **5.29.1 Export a Threaded Joint Report**

You can export the threaded joint report in both the pdf and excel formats by using [![image-1651336729349.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336729349.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336729349.png) (**PDF** button) and [![image-1651336739411.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336739411.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336739411.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.


### **5.30 Welder Performance Report**

The **Welder Performance Report** tab in the **Inspection** menu used to view the performance report of each welder for a particular project.

1. Click **Welder Performance Report** in the **Inspection** menu.
    
    The **Welder Performance Report** page opens.
    
    [![image-1651336819421.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336819421.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336819421.png)
    
     **Figure 5.30: Welder Performance Report page**
2. In the ****Project**** box, select a project from a drop-down list.
3. In the ****From Date**** and ****To Date**** boxes, select the from and to dates.
4. In the ****Joint Type**** box, select the joint type.
5. Click ****Load Report****.. The performance report for the selected project will be opened.
    
    [![image-1651336901427.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336901427.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336901427.png)

#### **5.30.1 Print a Welder Performance Report**

If you want to print a welder performance report, use [![image-1651336946103.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336946103.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336946103.png)and [![image-1651336961637.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336961637.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336961637.png) (print icons) provided in the **Welder Performance Report** page.

1. If you want to print the current page of the welder performance report, click [![image-1651336984177.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651336984177.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651336984177.png) (print icon including the page number).
2. If you want to print all the pages of the welder performance report, click [![image-1651337034498.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651337034498.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651337034498.png)(print icon).

#### **5.30.2 Export a Welder Performance Report**

You can export the welder performance report in various formats by using the option [![image-1651337120307.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651337120307.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651337120307.png) provided in the upper right corner of the **Welder Performance Report** page.


### **5.31 Create Auto Fit up and Visual Request**

If you want to create the new fit up and visual requests in both RFI and AFI automatically, you can create by using the **Create Auto Fit up and Visual Request** tab in the **Inspection** menu.

1. Click ****Create Auto Fit up and Visual Request**** in the ****Inspection**** menu. The **RFI and AFI Create** page opens.
    
    [![image-1651337211459.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/scaled-1680-/image-1651337211459.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-04/image-1651337211459.png)
    
     **Figure 5.31: RFI and AFI Create page**
2. In the ****Sub Contractor Name**** box, select a sub-contractor.
3. In the ****Inspection Date and Time**** box, select the inspection date and time.
4. In the ****Location**** box, select the location.
5. In the ****Select RFI/AFI**** box, if you want to create the fit up or visual request, select ****Fit up**** or ****Visual****. If you want to create both fit up and visual, select ****Both****. The page shows the list of drawing numbers, sheet numbers, and spool numbers.
6. Select the checkbox of the respective drawing, sheet and spool number which you want to add for creating the request.
7. Click ****Generate****. The selected RFI and AFI request will be added and moved into the respective requests page.


### **5.32 Weld Rejection Statistics Record**

If you want to view the statistics report of weld rejection rate, navigate to the **Weld Rejection Statistics Record** tab in the **Inspection** menu.

1. Click **Weld Rejection Statistics Record** in the **Inspection** menu. The **Weld Rejection Statistics Report** page opens.
    
    [![image-1651416424177.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416424177.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416424177.png)
    
     **Figure 5.32: Weld Rejection Statistics Report page**
2. In the ****Sub Contractor**** box, select a sub-contractor from a list.
3. In the ****From Date**** and ****To Date**** boxes, select the from and to dates.
4. Click ******Load Report**.****The statistics report of the weld rejection rate will be displayed.
    
    [![image-1651416494666.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416494666.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416494666.png)

#### **5.32.1 Print a Weld Rejection Statistics Record**

If you want to print the weld rejection statistics details, use [![image-1651416542790.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416542790.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416542790.png)and [![image-1651416556751.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416556751.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416556751.png) (print icons) provided in the **Weld Rejection Statistics Report** page.

1. If you want to print the current page of the weld rejection statistics record, click (print icon including the page number).
2. If you want to print all the pages of the weld rejection statistics record, click [![image-1651416633546.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416633546.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416633546.png)(print icon).

#### **5.32.2 Export a Weld Rejection Statistics Record**

You can export the weld rejection statistics details in various formats by using the option [![image-1651416683351.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416683351.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416683351.png) provided in the upper right corner of the **Weld Rejection Statistics Report** page.


### **5.33 View Spool Contractor**

The **View Spool Contractor** tab in the **Inspection** menu used to view and add the details of the spool installation contractor.

1. Click **View Spool Contractor** in the **Inspection** menu.
    
    The **Spool Installation Contractor** page opens.
    
    [![image-1651416742295.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416742295.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416742295.png)
    
     **Figure 5.33: Spool Installation Contractor page**
2. In the **Sheet No/ Drawing No/ Revision** box, select the respective sheet, drawing and revision numbers.
    
    The list of spools for the selected drawing number opens.
3. Enter the contractor name for the respective spools in the ****Contractor Name****
4. Click ****Save Changes****.


### **5.34 RFI Mechanical Completion Request**

Mechanical completion takes place through all phases of the piping project, starting at equipment supplier and continuing through fabrication up to commissioning phase. Mechanical completion encompasses all disciplines. If you want to add an RFI mechanical completion request,

1. Click ****RFI Mechanical Completion Request**** in the ****Inspection**** menu. The **RFI Mechanical Completion Request** page opens.
    
    [![image-1651416989995.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651416989995.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651416989995.png)
    
     **Figure 5.34: RFI Mechanical Completion Request page**

#### **5.34.1 Add an RFI Mechanical Completion Request**

If you want to add an RFI mechanical completion request, do the following steps,

1. In the **Sub Contractor** box, select a sub-contractor from a drop-down list.
2. In the ****Inspection Date**** box, select the date of inspection.
3. In the ****Location**** box, enter the name of the location. Before saving the added RFI mechanical completion request, you must add a system. You can add multiple system for one request.
    
    [![image-1651417125530.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651417125530.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651417125530.png) **Note**: The page shows a list of added systems. If you want to view the specific system, use the **Search by Test Pack No** filter box or use the filter options provided in the **System**, **Sub System**, **Test Pack**, and **Check Records** columns.
4. Select the checkbox of the respective system which you want to add.
5. In the **Remarks** box, enter your remarks if any.
6. In the **Description** box, enter the description for the request.
7. In the **Work Scope** box, enter the work scope detail.
8. Click **Save**. The RFI mechanical completion request will be added and listed in the **View RFI Mechanical Completion** page.


### **5.35 View RFI Mechanical Completion**

The **View RFI Mechanical Completion** tab helps you to view and edit the RFI mechanical completion request, which is added by using the **RFI Mechanical Completion Request** tab. This tab also allows you to add a new RFI mechanical completion request.

1. Click ****View RFI Mechanical Completion**** in the ****Inspection**** menu. The **View RFI Mechanical Completion List** page opens with a list of added RFI mechanical completion requests.
    
    [![image-1651417447008.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651417447008.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651417447008.png)
    
     **Figure 5.35: View RFI Mechanical Completion List page**

#### **5.35.1 Add an RFI Mechanical Completion Request**

If you want to add an RFI mechanical completion request, do the following steps,

1. Click (****ADD**** button) in the ****View RFI Mechanical Completion List**** page. The system redirects you to a new page to add a new RFI mechanical completion request. To know how to add an RFI mechanical completion request, See the topic, “[**<u>Add an RFI Mechanical Completion Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.34.1%C2%A0add-an-rfi-me)”.

Once you have added the RFI mechanical completion request, you must submit the added request to perform mechanical completion inspection.

#### **5.35.2 Edit an RFI Mechanical Completion Request** 

If you want to edit any existing mechanical completion request in the **View RFI Mechanical Completion List** page, do the following,

1. Click [![image-1651418870378.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651418870378.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651418870378.png) (Edit icon) in the ****Edit**** column for the respective RFI mechanical completion request. See Fig 8.35. The **RFI Mechanical Completion Request** page opens with the details of the selected RFI mechanical completion request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.35.3 Submit and Approve an RFI Mechanical Completion Request**

Once you have added the RFI mechanical completion request, the **Submission** column in the **RFI Mechanical Completion Request** page is appeared with [![image-1651418959326.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651418959326.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651418959326.png)(Submit and Reject icons).

1. If you want to submit the mechanical completion request, click [![image-1651418988857.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651418988857.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651418988857.png) (Submit icon) in the ****Submission**** Otherwise click [![image-1651419010008.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419010008.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419010008.png) (Reject icon) to reject the request.
    
    Once you have submitted the mechanical completion request, the **Request Status** column in the **View RFI Mechanical Completion List** page is appeared with [![image-1651419042833.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419042833.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419042833.png) (Approve and Reject icons).
2. If you want to approve the mechanical completion request, click [![image-1651419111744.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419111744.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419111744.png)(Approve icon) in the ****Request Status**** Otherwise click [![image-1651419129412.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419129412.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419129412.png) (Reject icon) to reject the request.

The mechanical completion request will be moved for mechanical completion inspection.

#### **5.35.4 Add Results of Mechanical Completion Inspection**

After completing the mechanical completion inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651419228291.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419228291.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419228291.png)(Add icon) in the **Results** column of the respective request.
    
    The Result window opens a list of test pack added for the particular request.
    
    [![image-1651419244562.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419244562.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419244562.png)
2. In the ****Result**** column, select the result of each test pack from the given result options in the drop-down list.
3. In the ****Remarks**** column, enter your remarks if any.
4. Click ****Approve All &amp;**** ****Save****.

#### **5.35.5 View a Mechanical Completion Inspection Report**

If you want to view a mechanical completion inspection report, click [![image-1651419343803.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419343803.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419343803.png)(print icon) provided in the **Print** column of the **View RFI Mechanical Completion List** page. See Fig 5.35.

#### **5.35.6 Attach a File into a Mechanical Completion inspection Request** 

If you want to attach a file with any existing mechanical completion inspection request listed in the **View RFI Mechanical Completion List** page, you can attach the file by using [![image-1651419396286.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419396286.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419396286.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.35.7 Export Mechanical Completion Inspection Request List**

You can export a list of mechanical completion inspection requests added in the **View RFI Mechanical Completion List** page in both the pdf and excel formats by using [![image-1651419463880.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419463880.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419463880.png) (**PDF** button) and [![image-1651419476238.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419476238.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419476238.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.35.8 Filter a Mechanical Completion Inspection Request**

If you want to filter any specific mechanical completion inspection request in the **View RFI Mechanical Completion List** page, you can use [![image-1651419532888.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419532888.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419532888.png) (**FILTER** button) located on the **View RFI Mechanical Completion List page. To know how to filter, see the topic, “**[<u>Filter P&amp;ID</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)**”.


### **5.36 RFI Static Commissioning**

Static Commissioning take place when Mechanical completion is completed for a system or part of a system. If you want to add an RFI static commissioning request,

1. Click **RFI Static Commissioning** in the **Inspection** menu. The **RFI Static Commissioning Request** page opens.
    
    [![image-1651419615186.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419615186.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419615186.png)
    
     **Figure 5.36: RFI Static Commissioning Request page**

#### **5.36.1 Add an RFI Static Commissioning Request**

If you want to add an RFI static commissioning request, do the following steps,

1. In the **Sub Contractor** box, select a sub-contractor from a drop-down list.
2. In the **Inspection Date** box, select the date of inspection.
3. In the **Location** box, enter the name of the location.
    
    Before saving the added RFI static commissioning request, you must add a system. You can add multiple systems for one request.
    
    [![image-1651419760307.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651419760307.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651419760307.png) **Note**: The page shows a list of added systems. If you want to view the specific system, use the **Search by Test Pack No** filter box or use the filter options provided in the **System**, **Sub System**, **Test Pack**, and **Check Records** columns.
4. Select the checkbox of the respective system which you want to add.
5. In the **Remarks** box, enter your remarks if any.
6. In the **Description** box, enter the description for the request.
7. In the **Work Scope** box, enter the work scope detail.
8. Click **Save**.

The RFI mechanical completion request will be added and listed in the **View RFI Static Commissioning** page.


### **5.37 View RFI Static Commissioning**

The **View RFI Static Commissioning** tab helps you to view and edit the RFI static commissioning request, which is added by using the **RFI Static Commissioning** tab. This tab also allows you to add a new RFI static commissioning request.

1. Click ****View RFI Static Commissioning**** in the ******Inspection****** menu. The **View RFI Static Commissioning List** page opens with a list of added RFI static commissioning requests.
    
    [![image-1651420065662.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651420065662.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651420065662.png)
    
     **Figure 5.37: View RFI Static Commissioning List page**

#### **5.37.1 Add an RFI Static Commissioning Request**

If you want to add an RFI static commissioning request, do the following steps,

1. Click [![image-1651420210211.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651420210211.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651420210211.png) (****ADD**** button) in the ******View RFI Static Commissioning List page.******The system redirects you to a new page to add a new RFI static commissioning request. To know how to add an RFI static commissioning request, See the topic, “[**<u>Add an RFI Static Commissioning Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.36.1-add-an-rfi-st)”.

Once you have added the RFI static commissioning request, you must submit the added request to perform the static commissioning.

#### **5.37.2 Edit an RFI Static Commissioning Request** 

If you want to edit any existing static commissioning request in the **View RFI Static Commissioning List** page, do the following,

1. Click (Edit icon) in the **Edit** column for the respective RFI static commissioning request. See Fig 5.37.
    
    The **RFI Static Commissioning Request** page opens with the details of the selected RFI request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.37.3 Submit and Approve an RFI Static Commissioning Request**

Once you have added the RFI static commissioning request, the **Submission** column in the **RFI Static Commissioning Request** page is appeared with [![image-1651423781694.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423781694.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423781694.png)(Submit and Reject icons).

1. If you want to submit the static commissioning request, click [![image-1651423771606.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423771606.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423771606.png) (Submit icon) in the **Submission** column. Otherwise click [![image-1651423800885.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423800885.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423800885.png)(Reject icon) to reject the request.
    
    Once you have submitted the static commissioning request, the **Request Status** column in the **View RFI Static Commissioning List** page is appeared with [![image-1651423822281.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423822281.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423822281.png) (Approve and Reject icons).
2. If you want to approve the static commissioning request, click [![image-1651423854611.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423854611.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423854611.png)(Approve icon) in the ****Request Status**** Otherwise click [![image-1651423867916.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423867916.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423867916.png) (Reject icon) to reject the request. The static commissioning request will be moved for static commissioning inspection.

#### **5.37.4 Add Results of Static Commissioning Inspection**

After completing the static commissioning inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651423936644.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423936644.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423936644.png) (Add icon) in the **Results** column of the respective request.
    
    The Result window opens a list of system added for the particular request.
    
    [![image-1651423955896.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651423955896.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651423955896.png)
2. In the **Result** column, select the result of each system from the given result options in the drop-down list.
3. In the **Remarks** column, enter your remarks if any.
4. Click **Approve All &amp;** **Save**.

#### **5.37.5 View a Static Commissioning Inspection Report**

If you want to view a static commissioning inspection report, click [![image-1651424025434.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424025434.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424025434.png)(print icon) provided in the **Print** column of the **View RFI Static Commissioning List** page. See Fig 5.37.

#### **5.37.6 Attach a File into a Static Commissioning Inspection Request** 

If you want to attach a file with any existing static commissioning inspection request listed in the **View RFI Static Commissioning List** page, you can attach the file by using [![image-1651424068516.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424068516.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424068516.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.37.7 Export Static Commissioning Inspection Request List**

You can export a list of static commissioning inspection requests added in the **View RFI Static Commissioning List** page in both the pdf and excel formats by using [![image-1651424111522.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424111522.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424111522.png) (**PDF** button) and [![image-1651424120464.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424120464.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424120464.png) (**Excel** button). To know how to export, see the topic, “[<u>**Export P&amp;ID list**</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.37.8 Filter a Static Commissioning Inspection Request**

If you want to filter any specific static commissioning inspection request in the **View RFI Static Commissioning List** page, you can use [![image-1651424170119.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424170119.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424170119.png) (**FILTER** button) located on the **View RFI Static Commissioning List page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.38 RFI Fit up Generic**

The **RFI Fit up Request Generic** tab in the **Inspection** menu helps you to add a generic RFI fit up request.

1. Click **RFI Fit up Request Generic** in the **Inspection** menu.
    
    The **RFI Fit up Request Generic** page opens.
    
    [![image-1651424242470.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424242470.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424242470.png)
    
    [![image-1651424250282.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424250282.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424250282.png)
    
     **Figure 5.38: RFI Fit up Request Generic page**

#### **5.38.1 Add an RFI Fit up Request Generic**

If you want to add an RFI fit up request generic, do the following,

1. Click [![image-1651424343469.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424343469.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424343469.png) (**ADD** button) in the **RFI Fit up Request Generic** page. A new window opens to add an RFI fit up request generic.
    
    [![image-1651424374653.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424374653.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424374653.png)
    
    [![image-1651424383656.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424383656.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424383656.png)**Tip**: A report number for a new RFI fit up request generic will be updated automatically in the **Report Number** box.
2. In the **Description** box, enter the description for the RFI fit up request generic.
3. In the **System** box, select a system from a drop-down list.
4. In the **Inspection Date** box, choose the date of inspection.
5. In the **Frame No** box, enter the frame number.
6. In the **Elevation** box, enter the elevation value.
7. In the **Longitudinal** box, enter the longitudinal value.
8. In the **Location** box, enter the location where the inspection to be done.
9. In the **Drawing No** box, select the drawing number from a drop-down list.
10. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
11. In the **Remarks** box, enter your remarks if any.
12. Click **Save**. The RFI fit up request generic is inserted successfully. Once you have added the RFI fit up request generic, you must add the RFI data for the added request.

#### **8.38.2 Add RFI data for an Added RFI Fit up Request Generic**

If you want to add RFI data for the added RFI fit up request generic, do the following,

1. Click [![image-1651424546968.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424546968.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424546968.png)(Edit icon) in the **RFI Data** column of the **RFI Fit up Request Generic** page. See Fig 5.38. The **RFI Inspection Request List** window opens.
    
    [![image-1651424570282.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651424570282.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651424570282.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the **Inspection Details** option, select 1<sup>st</sup> Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the **Others** box, enter any other inspection related details.
6. In the **Refer to Report No** box, enter the report number for reference.
7. In the **RFI Date** box, choose the RFI date.
8. In the Inspection Result option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the **Remarks** box, enter your remarks if any.
10. In the **Inspected by** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the **Witnessed By** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**. The RFI data is successfully added.

#### **5.38.3 Clone an RFI Fit up Request Generic** 

The **Clone** option in the **RFI Fit up Request Generic** page used to create a RFI weld VI generic request in the [**<u>RFI Weld VI Generic</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.39-rfi-weld-vi-gen) page, as a copy of RFI fit up request generic, See Fig 5.39.

If you click [![image-1651425124423.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425124423.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425124423.png) (Clone icon) in the **Clone** column of the **RFI Fit up Request Generic** page, an RFI weld VI generic request is added in the **RFI weld VI generic** page.

[![image-1651425139612.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425139612.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425139612.png)**Tip**: You can create multiple copies of RFI weld VI generic request for a single RFI fit up request generic.

#### **5.38.4 Print an RFI Report**

If you want to print an RFI report, click [![image-1651425274307.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425274307.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425274307.png) (print icon) provided in the **RFI** **Report** column of the **RFI Fit up Request Generic** page. See Fig 5.38.

#### **5.38.5 Submit an RFI Fit up Request Generic**

Once you have added the RFI fit up request generic, the **Submission** column in the **RFI Fit up Request Generic** page is appeared with [![image-1651425316951.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425316951.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425316951.png)(Submit and Reject icons).

1. If you want to submit the RFI fit up request generic, click [![image-1651425337798.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425337798.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425337798.png)(Submit icon) in the **Submission** Otherwise click [![image-1651425351825.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425351825.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425351825.png) (Reject icon) to reject the request.

#### **5.38.6 Print an RFI Fit up Request Generic Report**

If you want to print an RFI fit up request generic report, click [![image-1651425421742.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425421742.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425421742.png)(print icon) provided in the **Report** column of the **RFI Fit up Request Generic** page. See Fig 5.38.

#### **5.38.7 Attach a File into an RFI Fit up Request Generic**

If you want to attach any file with any RFI fit up request generic added in the **RFI Fit up Request Generic page, you can attach the file by using [![image-1651425478937.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425478937.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425478937.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.38.8 View Signature Details of QA User, Surveyor, and Client** 

Once the RFI fit up inspection has completed, the QA, surveyor, and client add their signature based on their corresponding roles. You can view their signature by using[![image-1651425527501.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425527501.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425527501.png) (Sign icon) in the **Sign Details** column in the **RFI Fit up Request Generic** page.

#### **5.38.9 Edit an RFI Fit up Request Generic**

If you want to edit any existing RFI weld VI generic in the **RFI Weld VI Generic** page, do the following,

1. Click[![image-1651425695691.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425695691.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425695691.png)(Edit icon) in the **Edit** column for the respective RFI weld VI generic. See Fig 5.39. A new window opens to edit the RFI weld VI generic.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.38.10 Export RFI Weld VI Generic List**

You can export a list of RFI weld VI generic added in the **RFI Weld VI Generic** page in the pdf and excel formats by using [![image-1651425771131.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425771131.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425771131.png) (**PDF** button) and [![image-1651425783009.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425783009.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425783009.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.38.11 Filter an RFI Weld VI Generic**

If you want to filter any RFI weld VI generic from the list of RFI weld VI generic in the **RFI Weld VI Generic** page, you can use [![image-1651425823936.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425823936.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425823936.png) (**FILTER** button) located on the **View RFI Mechanical Completion List page. To know how to filter, see the topic, “**[<u>Filter P&amp;ID</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)**”.

### **5.39 RFI Weld VI Generic**

Once the RFI fit up inspection process has completed, the materials are moved for weld inspection process. The **RFI Weld VI Generic** tab in the **Inspection** menu helps you to add a generic RFI weld VI request.

1. Click **RFI Weld VI Generic** in the **Inspection** menu.
    
    The **RFI Weld VI Generic** page opens.
    
    [![image-1651688032861.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651688032861.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651688032861.png)
    
    [![image-1651688043418.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651688043418.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651688043418.png)
    
    [![image-1651688057432.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651688057432.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651688057432.png)
    
     **Figure 5.39: RFI Weld VI Generic page**

#### **5.39.1 Add an RFI Weld VI Generic** 

If you want to add an RFI weld VI generic, do the following,

1. Click [![image-1651690492306.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651690492306.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651690492306.png) (**ADD** button) in the **RFI Weld VI Generic** page. A new window opens to add an RFI weld VI generic.
    
    [![image-1651690514499.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651690514499.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651690514499.png)
    
    [![image-1651690534288.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651690534288.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651690534288.png)**Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651690550149.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651690550149.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651690550149.png) **Tip**: A report number for a new RFI weld VI generic will be updated automatically in the **Report Number** box.
2. In the **Description** box, enter the description for the RFI weld VI generic.
3. In the **System** box, select a system from a drop-down list.
4. In the **Inspection Date** box, choose the date of inspection.
5. In the **Frame No** box, enter the frame number.
6. In the **Elevation** box, enter the elevation value.
7. In the **Longitudinal** box, enter the longitudinal value.
8. In the **Location** box, enter the location where the inspection to be done.
9. In the **Drawing No** box, select the drawing number from a drop-down list.
10. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
11. In the **Remarks** box, enter your remarks if any.
12. Click **Save**.

The RFI weld VI generic is added successfully. Once you have added the RFI weld VI generic, you must add the RFI data for the added request.

#### **5.39.2 Add RFI data for RFI Weld VI Generic**

If you want to add RFI data for the added RFI weld VI generic, do the following,

1. Click [![image-1651691833242.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651691833242.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651691833242.png)(Edit icon) in the **RFI Data** column of the **RFI Weld VI Generic** page. See Fig 5.39. The **RFI Inspection Request List** window opens.
    
    [![image-1651691864240.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651691864240.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651691864240.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the ****Inspection Details**** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the **Others** box, enter any other inspection related details.
6. In the **Refer to Report No** box, enter the report number for reference.
7. In the **RFI Date** box, choose the RFI date.
8. In the Inspection Result option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the **Remarks** box, enter your remarks if any.
10. In the **Inspected by** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the **Witnessed By** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**.

The RFI data is successfully added.

#### **5.39.3 Clone an RFI Weld VI Generic**

The **Clone** option in the **RFI Weld VI Generic** page used to create a vacuum test request, an air test request, a hydrostatic test request, and an NDT request, as a copy of RFI weld VI generic request.

1. Click [![image-1651692329078.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651692329078.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651692329078.png) (Clone icon) in the **Clone** column of the **RFI Weld VI Generic** page. The Clone box opens.
    
    [![image-1651692357401.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651692357401.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651692357401.png)
2. Select any test from the given list.
3. Click [![image-1651692384498.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651692384498.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651692384498.png) (**Add** button).
    
    A new request for the selected test will be added in the respective pages.

#### **5.39.4 Print an RFI Report**

If you want to print an RFI report, click[![image-1651693014480.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651693014480.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651693014480.png) (print icon) provided in the **RFI** **Report** column of the **RFI Weld VI Generic** page. See Fig 5.39.

#### **5.39.5 Submit an RFI Weld VI Generic**

Once you have added the RFI weld VI generic, the **Submission** column in the **RFI Weld VI Generic** page is appeared with[![image-1651693203082.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651693203082.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651693203082.png)(Submit and Reject icons).

1. If you want to submit the RFI weld VI generic, click[![image-1651693761189.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651693761189.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651693761189.png) (Submit icon) in the **Submission** Otherwise click[![image-1651693771139.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651693771139.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651693771139.png) (Reject icon) to reject the request.

#### **5.39.6 Print an RFI Weld VI Generic Report**

1. If you want to print an RFI weld VI generic report, click[![image-1651693864312.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651693864312.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651693864312.png)(print icon) provided in the **Report** column of the **RFI Weld VI Generic** See Fig 5.39.

#### **5.39.7 View Signature Details of QA User, Surveyor, and Client** 

Once the weld VI inspection has completed, the QA, surveyor, and client add their signature based on their corresponding roles. You can view their signature by using[![image-1651693985485.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651693985485.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651693985485.png)(Sign icon) in the **Sign Details** column in the **RFI Weld VI Generic** page.

#### **5.39.8 Attach a File into an RFI Weld VI Generic**

If you want to attach any file with any RFI weld VI generic added in the **RFI Weld VI Generic page, you can attach the file by using[![image-1651694073141.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651694073141.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651694073141.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.39.9 Edit an RFI Weld VI Generic**

If you want to edit any existing RFI weld VI generic in the **RFI Weld VI Generic** page, do the following,

1. Click[![image-1651694198554.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651694198554.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651694198554.png) (Edit icon) in the **Edit** column for the respective RFI weld VI generic. See Fig 5.39. A new window opens to edit the RFI weld VI generic.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.39.10 Export RFI Weld VI Generic List**

You can export a list of RFI weld VI generic added in the **RFI Weld VI Generic** page in the pdf and excel formats by using [![image-1651694318708.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651694318708.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651694318708.png)(**PDF** button) and [![image-1651694335286.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651694335286.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651694335286.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.39.11 Filter an RFI Weld VI Generic**

If you want to filter any RFI weld VI generic from the list of RFI weld VI generic in the **RFI Weld VI Generic** page, you can use[![image-1651694420929.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651694420929.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651694420929.png) (**FILTER** button) located on the **View RFI Mechanical Completion List page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.



### **5.40 NDT Inspection Generic**

NDT inspection used to find out welding defects of the materials. Once the fit up and welding process of the materials has completed, the materials will be moved for the NDT inspection. The currently following NDT inspection methods are RT, UT, MT, PT, Ultrasonic Thickness Gaging (UTG), Magnetic Particle Inspection (MPI) after load test, UT/MT, and PT after load test.

The **NDT Inspection Generic** tab in the **Inspection** menu helps you to add an NDT inspection generic. If you want to navigate the NDT inspection generic,

1. Click **NDT Inspection Generic** in the **Inspection** menu. The **NDT Inspection Generic** page opens.
    
    [![image-1651425901242.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425901242.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425901242.png)
    
    [![image-1651425909456.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425909456.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425909456.png)
    
    [![image-1651425918468.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425918468.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425918468.png)
    
     **Figure 5.40: NDT Inspection Generic page**

#### **5.40.1 Add an NDT Inspection Generic** 

If you want to add an NDT inspection generic, do the following,

1. Click [![image-1651425992025.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651425992025.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651425992025.png) (**ADD** button) in the **NDT Inspection Generic** page. A new window opens to add an NDT Inspection generic.
    
    [![image-1651426025961.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426025961.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426025961.png)
    
    [![image-1651426037257.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426037257.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426037257.png) **Note**: The fields notified with a symbol (\*) are mandatory. You must enter the relevant details in that fields before saving.
    
    [![image-1651426056877.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426056877.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426056877.png) **Tip**: A report number for a new NDT inspection generic will be updated automatically in the **Report Number** box.
2. In the **Description** box, enter the description for the NDT inspection generic.
3. In the **System** box, select a system from a drop-down list.
4. In the **Inspection Date** box, choose the date of inspection.
5. In the **Frame No** box, enter the frame number.
6. In the **Elevation** box, enter the elevation value.
7. In the **Longitudinal** box, enter the longitudinal value.
8. In the **Location** box, enter the location where the inspection to be done.
9. In the **Drawing No** box, select the drawing number from a drop-down list.
10. In the **Designation** box, enter the designation detail.
11. In the **Cost Centre** box, enter the cost centre detail.
12. In the **Requisition** box, select the type of request from a drop-down list.
13. In the **Welding Position** box, enter the position of welding.
14. In the **Weld Type** box, enter the type of welding.
15. In the **Thickness** box, enter the thickness of the welding.
16. In the **Sub Contractor** box, select the sub-contractor from a drop-down list.
17. In the **Welder** box, select the name of a welder from a drop-down list.
18. In the **WPS** box, enter the WPS detail.
19. In the **Process** box, select the welding process to be done from a specified category.
20. In the **NDT Type** box, select the type of NDT to be done from a specified category.
21. In the **Remarks** box, enter your remarks if any.
22. Click **Save**.

The NDT inspection generic is added successfully. Once you have added the NDT inspection generic, you must add the RFI data for the added NDT inspection generic.

#### **5.40.2 Add RFI Data for NDT Inspection Generic**

If you want to add RFI data for the added NDT inspection generic, do the following,

1. Click [![image-1651426269187.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426269187.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426269187.png) (Edit icon) in the **RFI Data** column of the **NDT Inspection Generic**  See Fig 5.40. The **RFI Inspection Request List** window opens.
    
    [![image-1651426306146.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426306146.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426306146.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the **Inspection Details** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the **Others** box, enter any other inspection related details.
6. In the **Refer to Report No** box, enter the report number for reference.
7. In the **RFI Date** box, choose the RFI date.
8. In the **Inspection Result** option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the **Remarks** box, enter your remarks if any.
10. In the **Inspected by** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the **Witnessed By** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**. The RFI data is successfully added.

#### **5.40.3 Print an RFI Report**

If you want to print an RFI report, click [![image-1651426624774.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426624774.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426624774.png)(print icon) provided in the **RFI** **Report** column of the **NDT Inspection Generic** page. See Fig 5.40.

#### **5.40.4 Submit an NDT Inspection Generic**

Once you have added the NDT inspection generic, the **Submission** column in the **NDT Inspection Generic** page is appeared with[![image-1651426709164.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426709164.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426709164.png)(Submit and Reject icons).

1. If you want to submit the added NDT inspection generic, click [![image-1651426946998.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426946998.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426946998.png)(Submit icon) in the **Submission** column. Otherwise click [![image-1651426992565.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651426992565.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651426992565.png) (Reject icon) to reject the request.

#### **5.40.5 Print an NDT Inspection Generic Report**

If you want to print an NDT inspection generic report, click[![image-1651427028783.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427028783.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427028783.png) (print icon) provided in the **Report** column of the **NDT Inspection Generic** page. See Fig 5.40.

#### **5.40.6 View Signature Details of QA User, Surveyor, and Client** 

Once the NDT inspection has completed, the QA, surveyor, and client add their signature based on their corresponding roles. You can view their signature by using [![image-1651427075870.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427075870.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427075870.png) (Sign icon) in the **Sign Details** column in the **NDT Inspection Generic** page.

#### **5.40.7 Attach a File into an NDT Inspection Generic**

If you want to attach any file with any NDT inspection generic added in the **NDT Inspection Generic page, you can attach the file by using [![image-1651427127824.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427127824.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427127824.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.40.8 Edit an NDT Inspection Generic**

If you want to edit any existing NDT inspection generic in the **NDT Inspection Generic** page, do the following,

1. Click [![image-1651427188344.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427188344.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427188344.png)(Edit icon) in the **Edit** column for the respective NDT inspection generic. See Fig 5.40. A new window opens to edit the NDT inspection generic.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.40.9 Export NDT Inspection Generic List**

You can export a list of NDT inspection generic added in the **NDT Inspection Generic** page in the pdf and excel formats by using [![image-1651427268813.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427268813.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427268813.png) (**PDF** button) and [![image-1651427281553.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427281553.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427281553.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.40.10 Filter an NDT Inspection Generic**

If you want to filter any NDT inspection generic from the list of NDT inspection generic in the **NDT Inspection Generic** page, you can use [![image-1651427325711.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427325711.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427325711.png) (**FILTER** button) located on the **NDT Inspection Generic** page. To know how to filter, see the topic, “[<u>**Filter P&amp;ID**</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.41 View RFI Fit up (Unique Numbers)**

The **View RFI Fit up** tab helps you to add a new RFI fit up request. This tab also allows you to view and edit the added RFI fit up request.

1. Click **View RFI Fit up** in the **Inspection** menu.
    
    The **RFI Fit up Requests List** page opens.
    
    [![image-1651427384134.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427384134.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427384134.png)
    
     **Figure 5.41: RFI Fit up Requests List page**

#### **5.41.1 Add an RFI Fit up Request**

If you want to add an RFI fit up request, do the following,

1. Click [![image-1651427486684.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427486684.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427486684.png) (**ADD** button) in the **RFI Fit up Requests List** page. A new page opens to add an RFI fit up request.
    
    [![image-1651427529650.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427529650.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427529650.png)
    
     **Figure 5.41.1: A page for adding an RFI fit up request**
    
    [![image-1651427557166.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427557166.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427557166.png) **Tip**: A report number and an RFI number for a new RFI fit up request will be updated automatically in the **Report Number** and the **RFI Number** boxes, respectively.
2. In the **Sub Contractor** box, select the name of a sub-contractor from a drop-down list.
3. In the **Inspection Date &amp; Time** box, select the date of inspection. [![image-1651427598014.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427598014.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427598014.png) **Note**: The fit up inspection date should not be later than the RFI weld visual inspection date.
4. In the **Location** box, enter the location detail.
5. In the **Description** box, enter the description for the inspection.
    
    [![image-1651427630404.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651427630404.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651427630404.png) **Note**: Before saving the added RFI fit up request, you must add the joints. You can add multiple joints for any added fit up request by using a box provided in the left side of the page.
6. Click **Save**.

#### **5.41.2 Add Joints for an RFI Fit up Request**

If you want to add joints for any added RFI fit up request, do the following steps,

[![image-1651431118087.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431118087.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431118087.png)

1. Click the check box of the respective joints.
2. Click [![image-1651431150888.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431150888.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431150888.png) (**Add Selected Joints** button). The selected joints are moved into the **Added Joints** box located in the right side of the page.
    
    [![image-1651431179627.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431179627.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431179627.png)
3. If you want to update the unique numbers and WPS number for any joint, click the **Unique No** and **WPS Number** columns for the respective joints and then enter the unique numbers and select the WPS number from a drop-down list.
4. Click **Save**.
    
    The selected joints are successfully added for the RFI fit up request.

#### **5.41.3 Import Multiple Joints for an RFI Fit up Request**

If you want to import multiple joints together, do the following,

1. Click [![image-1651431257723.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431257723.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431257723.png) (**TEMPLATE** button) on the **Added Joints** box.
    
    A template will be downloaded as an excel worksheet to enter the details of multiple joints.
    
    [![image-1651431274316.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431274316.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431274316.png)
2. Enter the relevant details in the required columns on the excel worksheet.
3. Once you have added the joint details in the excel worksheet, save the excel worksheet on your computer.
4. Click [![image-1651431307320.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431307320.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431307320.png) (**IMPORT** button). A new window opens for importing the excel worksheet saved on your computer.
    
    [![image-1651431333144.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431333144.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431333144.png)
5. Click [![image-1651431352044.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431352044.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431352044.png) (**Browse** button) to select the excel worksheet to be uploaded.
6. Select the excel worksheet you want to upload from your computer.
7. Click [![image-1651431376049.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431376049.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431376049.png) (**Upload** button) to export the joints that are included in the excel worksheet.

The details of the joints in the worksheet will be displayed in the page.

The RFI fit up request is added successfully. Once you have added the RFI fit up request, you must submit the added request for inspection.

#### **5.41.4 Submit an RFI Fit up Request**

Once you have added the RFI fit up request, the **Request Status** column in the **RFI Fit up Requests List** page is appeared with [![image-1651431487236.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431487236.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431487236.png) (Submit and Reject icons). See Fig 5.41.

1. If you want to submit the RFI fit up request, click [![image-1651431518451.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431518451.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431518451.png)(Submit icon) in the **Request Status** Otherwise click [![image-1651431532974.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431532974.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431532974.png)(Reject icon) to reject the request.

#### **5.41.5 Change a Representative for Any RFI Fit up Request**

If you want to change a representative for any added RFI fit up request,

1. Click [![image-1651431593336.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431593336.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431593336.png) (Edit icon) in the **Representative** column for the respective RFI fit up request.
    
    The **Edit Form** window opens.
    
    [![image-1651431606643.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651431606643.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651431606643.png)
2. In the **Representative** box, enter the name of a representative.
3. Click **Save**.

#### **5.41.6 Print an RFI Fit up Report**

If you want to print an RFI fit up report, click [![image-1651432298538.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432298538.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432298538.png) (print icon) provided in the **Report** column of the **RFI Fit up Requests List** page. See Fig 5.41.

#### **5.41.7 Add Result for an Added RFI Fit up Request** 

Once you have fit up inspection, you can add the results. To add results,

1. Click [![image-1651432356265.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432356265.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432356265.png) (Add icon) in the **Results** column of the **RFI Fit up Requests List** page.
    
    The Result window opens.
    
    [![image-1651432370139.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432370139.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432370139.png)
2. If you want to check and update the unique number details for both the components, click [![image-1651432391933.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432391933.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432391933.png)(Edit icon) in the **Update Unique Number 1** and **Update Unique Number 2** columns and update.
3. If you want to update the WPS number, select the respective number in the **WPS** column and change the WPS number from a drop-down list.
4. If you want to update the result, select the respective result in the **Result** column from a drop-down list.
5. In the **Remarks** box, enter your remarks if any.
6. Click **Save changes**.

#### **5.41.8 Attach a File into an RFI Fit up Request** 

If you want to attach any file with any RFI fit up request listed in the **RFI Fit up Requests List page, you can attach the file by using [![image-1651432486195.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432486195.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432486195.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.41.9 Edit an RFI Fit up Request** 

If you want to edit any existing RFI fit up request in the **RFI Fit up Requests List** page, do the following,

1. Click [![image-1651432542926.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432542926.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432542926.png) (Edit icon) in the **Edit** column for the respective RFI fit up request. See Fig 5.41. A new page opens to edit the RFI fit up request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.41.10 Export RFI Fit up Request List**

You can export a list of RFI fit up request added in the **RFI Fit up Requests List** page in the pdf and excel formats by using [![image-1651432628555.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432628555.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432628555.png) (**PDF** button) and [![image-1651432638077.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432638077.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432638077.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.41.11 Filter an RFI Fit Up Request** 

If you want to filter any RFI fit up request from the list of RFI fit up requests in the **RFI Fit up Requests List** page, you can use [![image-1651432698911.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432698911.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432698911.png) (**FILTER** button). To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.42 View RFI Weld VI (Unique Numbers)**

The **View RFI Weld VI** tab helps you to add a new RFI weld VI request. This tab also allows you to view and edit the added RFI weld VI request.

1. Click **View RFI Weld VI** in the **Inspection** menu.
    
    The **RFI Weld Visual Request List** page opens.
    
    [![image-1651432752542.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432752542.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432752542.png)
    
     **Figure 5.42: RFI Weld Visual Request List page**

#### **8.42.1 Add an RFI Weld VI Request**

If you want to add an RFI weld VI request, do the following,

1. Click [![image-1651432818954.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432818954.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432818954.png) (**ADD** button) in the **RFI Weld Visual Request List** Page. A new page opens to add an RFI weld VI request.
    
    [![image-1651432853375.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432853375.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432853375.png)
    
    [![image-1651432862747.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432862747.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432862747.png) **Tip**: A report number and an RFI number for a new RFI weld VI request will be updated automatically in the **Report Number** and the **RFI Number** boxes, respectively.
2. In the **Sub Contractor** box, select the name of a sub-contractor from a drop-down list.
3. In the **Inspection Date &amp; Time** box, select the date of inspection.
4. In the **Location** box, enter the location detail. [![image-1651432929724.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651432929724.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651432929724.png)**Note**: Before saving the added RFI weld VI request, you must add the joints. You can add multiple joints for any added RFI weld VI request by using a box provided in the left side of the **RFI Weld Visual Request** page.
5. Click **Save**.

#### **5.42.2 Add Joints for an RFI Weld VI Request**

If you want to add joints for any added RFI weld VI request, do the following,

[![image-1651433001485.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433001485.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433001485.png)

1. In the **RFI Report Number** box, select an RFI report number from a drop-down list. A list of joints including the ISO drawing and spool numbers opens for the selected RFI report number.
2. Click the check box of the respective joints.
3. Click [![image-1651433045501.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433045501.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433045501.png) (**Add Selected Joints** button). The selected joints are moved into the **Added Joints** box located in the right side of the page.
    
    [![image-1651433073627.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433073627.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433073627.png)
4. If you want to update the WPS number for any joint, click the **WPS Number** column for the respective joints and then select the WPS number from a drop-down list.
5. If you want to update the welder details, click [![image-1651433107494.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433107494.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433107494.png) (Add icon) in the Welder Details column.
    
    The **Weld-Weld Layer- Weld Process** window opens.
    
    [![image-1651433130267.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433130267.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433130267.png)
6. In the **Date** box, select the date of adding welder details.
7. In the **Weld Process** column, select a weld process.
8. In the **Weld Position** column, select a weld position.
9. In the **Weld Layers** column, select a weld layer. A list of welders will be displayed in the **Welder Number/Name** column for the selected criteria.
10. Select a welder you want to add.
11. Click [![image-1651433209333.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433209333.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433209333.png)(**Add** button). The selected welder details will be listed below.
    
    [![image-1651433231832.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433231832.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433231832.png) **Note**: If you want to add welder details for the next joint, click [![image-1651433248649.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433248649.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433248649.png) (**Next Joint** button).
12. Click **Save**. The selected joints are successfully added for the RFI weld VI request.

#### **5.42.3 Import Multiple joints for an RFI Weld VI Request**

You can import multiple joints together by using a pre-defined excel template given in the application. If you want to import multiple joints together, do the following,

1. Click [![image-1651433312393.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433312393.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433312393.png) (**TEMPLATE** button) on the **Added Joints** box. A template will be downloaded as an excel worksheet to enter the details of multiple joints.
    
    [![image-1651433356628.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433356628.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433356628.png)
2. Enter the relevant details in the required columns on the excel worksheet.
3. Once you have added the joint details in the excel worksheet, save the excel worksheet on your computer.
4. Click [![image-1651433392459.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433392459.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433392459.png) (**IMPORT** button). A new window opens for importing the excel worksheet saved on your computer.
    
    [![image-1651433415504.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433415504.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433415504.png)
5. Click [![image-1651433524821.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433524821.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433524821.png) (**Browse** button) to select the excel worksheet to be uploaded.
6. Select the excel worksheet you want to upload from your computer.
7. Click [![image-1651433552075.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433552075.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433552075.png) (**Upload** button) to export the joints that are included in the excel worksheet. The details of the joints in the worksheet will be displayed in the page.

The RFI weld VI request is added successfully. Once you have added the RFI weld VI request, you must submit the added request for inspection.

#### **5.42.4 Submit an RFI Weld VI Request**

Once you have added the RFI weld VI request, the **Request Status** column in the **RFI Weld Visual Request List** page is appeared [![image-1651433666499.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433666499.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433666499.png)with (Submit and Reject icons). See Fig 5.42.

1. If you want to submit the RFI weld VI request, click [![image-1651433684525.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433684525.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433684525.png)(Submit icon) in the **Request Status** column. Otherwise click [![image-1651433697946.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433697946.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433697946.png) (Reject icon) to reject the request.

#### **5.42.5 Add a Representative for Any RFI Weld VI Request**

If you want to add a representative for any added RFI weld VI request,

1. Click [![image-1651433749565.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433749565.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433749565.png)(Edit icon) in the **Representative** column for the respective RFI weld VI request. The **Edit Form** window opens.
    
    [![image-1651433764540.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433764540.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433764540.png)
2. In the **Representative** box, enter the name of a representative.
3. Click **Save**.

#### **5.42.6 Add Result for an RFI Weld VI Request**

If you want to add for the added RFI weld VI inspection request, do the following,

1. Click [![image-1651433832495.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433832495.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433832495.png)(Add icon) in the **Results** column of the **RFI Weld Visual Request List** page, for the respective RFI weld VI request. See Fig 5.42. A new window opens including the line, drawing number, joint number and WPS number including welder details for the respective RFI weld VI request.
    
    [![image-1651433867422.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433867422.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433867422.png)
2. If you want to update the welder details, click [![image-1651433900284.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651433900284.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651433900284.png) (Add icon) in the **Welder Details** column and update the welder details.
3. In the **Visual OD** column, select the result for visual OD.
4. In the **Visual ID** column, select the result for visual ID.
5. In the **Debris** column, select the result for debris.
6. In the **Drift** column, select the result for drift.
7. In the **Result** column, select the results from a drop-down list based on your inspection.
8. In the **Remarks** column, enter your remarks if any.
9. Click **Save**.

#### **5.42.7 Print an RFI Weld VI Request**

If you want to print an RFI weld VI report, click [![image-1651434038428.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434038428.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434038428.png)(print icon) provided in the **Report** column of the **RFI Weld Visual Request List** page. See Fig 5.42.

#### **5.42.8 Attach a File into an RFI Weld VI Request**

If you want to attach any file with any RFI weld VI request listed in the **RFI Weld Visual Request List** page, you can attach the file by using [![image-1651434098004.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434098004.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434098004.png)(Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.42.9 Edit an RFI Weld VI Request**

If you want to edit any existing RFI weld VI request in the **RFI Weld Visual Request List** page, do the following,

1. Click [![image-1651434341071.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434341071.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434341071.png)(Edit icon) in the **Edit** column for the respective RFI weld VI request. See Fig 5.42.
    
    A new page opens to edit the RFI weld VI request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.42.10 Export RFI Weld VI Request List**

You can export a list of RFI weld VI request added in the **RFI Weld Visual Request List** page in the pdf and excel formats by using [![image-1651434503796.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434503796.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434503796.png) (**PDF** button) and [![image-1651434514726.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434514726.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434514726.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.42.11 Filter an RFI Weld VI Request**

If you want to filter any RFI weld VI request from the list of RFI weld VI requests in the **RFI Weld Visual Request List** page, you can use [![image-1651434833853.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434833853.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434833853.png) (**FILTER** button). To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.43 View AFI Fit up (Unique Numbers)**

The **View AFI Fit up** allows you to add a new AFI fit up request. This tab also helps you to view and edit the added AFI fit up request.

1. Click **View AFI Fit up** in the **Inspection** menu.
    
    The **AFI Fit up Request List** page opens.
    
    [![image-1651434885483.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434885483.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434885483.png)
    
     **Figure 5.43: AFI Fit up Request List page**


#### **5.43.1 Add an AFI Fit up Request**

If you want to add an AFI fit up request, do the following,

1. Click [![image-1651434960555.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434960555.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434960555.png) (**ADD** button) in the **AFI Fit up Request List** page.
    
    The **AFI Fit up Inspection Request** page opens to add an AFI fit up request.
    
    [![image-1651434976662.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434976662.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434976662.png)

[![image-1651434991128.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651434991128.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651434991128.png)**Tip**: A report number and RFI number for a new AFI fit up request will be updated automatically in the **Report Number** and **RFI Number** boxes.

2. In the **Representative (AI)** box, enter representative name for the application inspection and enter their email id and contact number in the **Email** and **Contact No** boxes, respectively.
3. In the **Representative (Client)** box, enter representative name from the client and enter their email id and contact number in the **Email** and **Contact No** boxes, respectively.
4. In the **Inspection Date** box, select the date of inspection.
5. In the **Representative (Contractor)** box, enter representative name from the contractor and enter their email id and contact number in the **Email** and **Contact No** boxes, respectively.
6. In the **Location** box, enter the location detail.
7. In the **Remarks** box, enter your remarks if any.
8. In the **Inspection Item** box, enter the details of items to be inspected.
9. In the **Subject Coverage** box, enter the subject coverage detail.
    
    [![image-1651435176622.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435176622.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435176622.png)**Note**: Before saving the added AFI fit up request, you must add the joints. You can add multiple joints for any added fit up request by using a box provided in the left side of the page.
10. Click **Save**.
    
    Once you enter the details to add an AFI fit up request, a list of joints including the joint numbers, sheet numbers, and spool and drawing numbers opens.

#### **5.43.2 Add Joints for an AFI Fit up Request**

If you want to add joints for any added AFI fit up request, do the following,

1. Click the check box of the respective joints.
2. Click [![image-1651435266493.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435266493.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435266493.png) (**Add Selected Joints** button). The selected joints are moved into the **Added Joints** box located in the right side of the page.
    
    [![image-1651435295850.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435295850.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435295850.png)

The selected joints are successfully added for the AFI fit up request.

Once you have added the RFI fit up request, you must submit the added request for inspection.

#### **5.43.3 Submit an AFI Fit up Request**

Once you have added the AFI fit up request, the **Request Status** column in the **AFI Fit up Request List page is appeared with [![image-1651435383249.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435383249.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435383249.png) (Submit and Reject icons). See Fig 5.43.

1. If you want to submit the AFI fit up request, click [![image-1651435414597.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435414597.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435414597.png) (Submit icon) in the **Request Status** Otherwise click [![image-1651435447388.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435447388.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435447388.png) (Reject icon) to reject the request.

#### **5.43.4 Change Representative for Any AFI Fit up Request**

If you want to change the added representative for any AFI fit up request,

1. Click [![image-1651435491352.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435491352.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435491352.png)(Edit icon) in the **Representative** column for the respective AFI fit up request. The **Edit Form** window opens.
    
    [![image-1651435515203.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435515203.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435515203.png)
2. In the **Representative** box, edit the name of a representative.
3. Click **Save**.

#### **5.43.5 Print an AFI Fit up Report**

If you want to print an AFI fit up report, click [![image-1651435586901.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435586901.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435586901.png)(print icon) provided in the **Report** column of the **AFI Fit up Request List** page. See Fig 5.43.

#### **5.43.6 Add Result of AFI Fit up Inspection**

If you want to update results for the AFI fit up inspection request, do the following,

1. Click [![image-1651435649572.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435649572.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435649572.png) (Add icon) in the **Results** column of the **AFI Fit up Request List** page. A new window opens.
    
    [![image-1651435668711.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435668711.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435668711.png)
2. In the **Result** column, select the results of AFI inspection from a drop-down list, for the respective drawing and joint numbers.
3. In the **Remarks** column, enter your remarks if any.
4. Click **Save**.

#### **5.43.7 Attach a File into an AFI Fit up Request** 

If you want to attach any file with any AFI fit up request listed in the **AFI Fit up Request List page, you can attach the file by using [![image-1651435747491.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435747491.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435747491.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.43.8 Edit an AFI Fit up Request** 

If you want to edit any existing AFI fit up request in the **AFI Fit up Request List page, do the following,

1. Click [![image-1651435798588.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435798588.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435798588.png)(Edit icon) in the **Edit** column for the respective AFI fit up request. See Fig 5.43.
    
    A new page opens to edit the AFI fit up request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.43.9 Export AFI Fit up Request List**

You can export a list of AFI fit up request added in the **AFI Fit up Request List** page in the pdf and excel formats by using [![image-1651435875820.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435875820.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435875820.png) (**PDF** button) and [![image-1651435886053.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435886053.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435886053.png) **Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

### **8.44 View AFI Weld VI (Unique Numbers)**

The **View AFI Weld VI** allows you to add a new AFI weld VI request. This tab also helps you to view and edit the added AFI weld VI request.

1. Click **View AFI Weld VI** in the **Inspection** menu.
    
    The **AFI** **Weld Visual Request List** page opens.
    
    [![image-1651435967663.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651435967663.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651435967663.png)
    
     **Figure 5.44: AFI** **Weld Visual Request List page**

#### **8.44.1 Add an AFI Weld VI Request**

If you want to add an AFI weld VI request, do the following,

1. Click [![image-1651436297680.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436297680.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436297680.png) (**ADD** button) in the **AFI** **Weld Visual Request List** page.
    
    The **AFI Weld Visual Inspection Request** page opens to add an AFI weld VI request.
    
    [![image-1651436319326.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436319326.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436319326.png)
    
    [![image-1651436334902.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436334902.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436334902.png)**Tip**: A report number and RFI number for a new AFI weld VI request will be updated automatically in the **Report Number** and **RFI Number** boxes.
2. In the **Representative (AI)** box, enter representative name for the application inspection and enter their email id and contact number in the **Email** and **Contact No** boxes, respectively.
3. In the **Representative (Client)** box, enter representative name from the client and enter their email id and contact number in the **Email** and **Contact No** boxes, respectively.
4. In the **Inspection Date** box, select the date of inspection.
5. In the **Representative (Contractor)** box, enter representative name from the contractor and enter their email id and contact number in the **Email** and **Contact No** boxes, respectively.
6. In the **Inspection Item** box, enter the details of items to be inspected.
7. In the **Subject Coverage** box, enter the subject coverage detail.
8. In the **Remarks** box, enter your remarks if any. [![image-1651436436044.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436436044.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436436044.png) **Note**: Before saving the added AFI weld VI request, you must add the joints. You can add multiple joints for any added weld VI request by using a box provided in the left side of the page.
9. Click **Save**.

#### **5.44.2 Add Joints for an AFI Weld VI Request**

If you want to add joints for any added AFI weld VI request, do the following,

1. Click the check box of the respective joints.
2. Click [![image-1651436528886.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436528886.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436528886.png) (**Add Selected Joints** button). The selected joints are moved into the **Added Joints** box located in the right side of the page.
    
    [![image-1651436578437.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436578437.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436578437.png)
3. Click **Save**.

The selected joints are successfully added for the AFI weld VI request.

The AFI weld VI request is successfully added. Once you have added the AFI weld VI request, you must submit the added weld VI request for inspection.

#### **5.44.3 Submit an AFI Weld VI Request**

Once you have added the AFI weld VI request, the **Request Status** column in the **AFI** **Weld Visual Request List page is appeared with [![image-1651436719301.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436719301.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436719301.png)(Submit and Reject icons). See Fig 5.44.

1. If you want to submit the RFI weld VI request, click [![image-1651436746891.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436746891.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436746891.png)(Submit icon) in the **Request Status** Otherwise click [![image-1651436761124.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436761124.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436761124.png) (Reject icon) to reject the request.

#### **5.44.4 Change a Representative for Any AFI Weld VI Request**

If you want to change a representative for any added AFI weld VI request,

1. Click [![image-1651436823162.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436823162.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436823162.png) (Edit icon) in the **Representative** column for the respective AFI weld VI request. The **Edit Form** window opens.
    
    [![image-1651436848432.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436848432.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436848432.png)
2. In the **Representative** box, enter the name of a representative.
3. Click **Save**.

#### **5.44.5 Add Result for an AFI Weld VI Inspection**

If you want to add result for the added AFI weld VI inspection, do the following,

1. Click [![image-1651436934741.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436934741.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436934741.png) (Add icon) in the **Results** column of the **AFI** **Weld Visual Request List** page, for the respective AFI weld VI request. See Fig 5.44. A new window opens including the line, drawing numbers and joint number for the respective AFI weld VI request.
    
    [![image-1651436964255.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651436964255.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651436964255.png)
2. In the **Result** column, select the results from a drop-down list based on your inspection.
3. In the **Remarks** column, enter your remarks if any.
4. Click **Save**.

#### **5.44.6 Print an AFI Weld VI Report**

If you want to print an AFI weld VI report, click[![image-1651437040171.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437040171.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437040171.png) (print icon) provided in the **Report** column of the **AFI** **Weld Visual Request List** page. See Fig 5.44.

#### **5.44.7 Attach a file into an AFI weld VI request** 

If you want to attach any file with any AFI weld VI request listed in the **AFI** **Weld Visual Request List** page, you can attach the file by using [![image-1651437108192.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437108192.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437108192.png)(Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.44.8 Edit an AFI Weld VI Request** 

If you want to edit any existing AFI weld VI request in the **AFI** **Weld Visual Request List** page, do the following steps,

1. Click [![image-1651437163743.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437163743.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437163743.png) (Edit icon) in the **Edit** column for the respective AFI weld VI request. See Fig 5.44.
    
    A new page opens to edit the AFI weld VI request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.44.9 Export AFI Weld VI Request List**

You can export a list of AFI weld VI request added in the **AFI** **Weld Visual Request List** page in the pdf and excel formats by using[![image-1651437237289.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437237289.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437237289.png) (**PDF** button) and [![image-1651437255234.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437255234.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437255234.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.44.10 Filter an AFI weld VI request** 

If you want to filter any AFI weld VI request from the list of AFI weld VI requests in the **AFI** **Weld Visual Request List** page, you can use [![image-1651437302567.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437302567.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437302567.png) (**FILTER** button). To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.45 RFI Line Walk**

The **RFI Line Walk** tab in the **Inspection** menu is used to add a request for line walk inspection.

#### **5.45.1 Add a Line Walk Inspection Request**

If you want to add a line walk inspection request, do the following steps,

1. Click **RFI Line Walk** in the **Inspection** menu. The **RFI Line Walk** page opens.
    
    [![image-1651437403080.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437403080.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437403080.png)
    
     **Figure 5.45: RFI Line Walk page**
2. In the **Requested By** box, enter the name of a person who has requested the line walk inspection.
3. In the **Location** box, select the location where the inspection to be performed.
4. In the **Inspection Date &amp; Time** box, select the inspection date and time.
5. In the **Classification** box, enter the classification detail.
6. In the **System** box, select a system from a drop-down list.
7. In the **Sub Contractor** box, select a sub-contractor from a drop-down list.
8. In the **Acceptance Code** box, enter the acceptance code detail.
9. In the **Designation** box, enter the designation detail.
10. In the **Test Temperature** box, enter the test temperature value.
11. In the **Test Medium** box, select the test medium from the drop-down list.
12. In the **Drawing No** box, select the drawing number from a drop-down list.
13. In the **Work Scope** box, enter the work scope detail.
14. In the **Cost Centre** box, enter the cost centre detail.
15. In the **Holding Time**box, enter the holding time range.
16. In the **Pressure Gauge No** box, enter the pressure gauge number.
17. In the **Procedure No** box, enter the procedure number.
18. In the **Design Pressure** box, enter the design pressure range.
19. In the **Test Pressure** box, enter the test pressure range.
20. In the **Instrument** box, enter the instrument name.
21. In the **P&amp;ID No** box, enter the P&amp;ID number.
22. In the **Remarks** box, enter your remarks if any.
23. In the **Description** box, enter the description for the line walk inspection. Before saving the added line walk inspection request, you must add spools.
    
    [![image-1651437670438.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437670438.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437670438.png) **Note**: You can add multiple spools for one request.
    
    The **RFI Line Walk** page shows a list of added spools. If you want to view the spools for the specific ISO drawing, select the respective ISO drawing from a drop-down list.
    
    [![image-1651437719674.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437719674.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437719674.png)
24. Click [![image-1651437736378.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437736378.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437736378.png) (Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
25. Click **Save Request**.

The line walk inspection request will be added and listed in the **RFI Line Walk Report** page.

### **5.46 View RFI Line Walk**

The **View RFI Line Walk** tab helps you to view and edit the line walk inspection request, which is added by using the **RFI Line Walk** tab. This tab also allows you to add a new line walk inspection request.

1. Click **View RFI Line Walk** in the **Inspection** menu. The **RFI Line Walk Report** page opens with a list of added line walk inspection requests.
    
    [![image-1651437863575.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651437863575.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651437863575.png)
    
     **Figure 5.46: RFI Line Walk Report page**

#### **5.46.1 Add a Line Walk Inspection Request**

If you want to add a line walk inspection request, do the following steps,

1. Click (**ADD** button) in the **RFI Line Walk Report** page. The system redirects you to a new page to add a new line walk inspection request. To know how to add a line walk inspection request, See the topic, “[**<u>Add a Line Walk Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.45.1%C2%A0add-a-line-wa)”.

Once you have added the line walk inspection request, you must submit the added request to perform the line walk inspection.

#### **5.46.2 Add Representative for a Line Walk Inspection Request**

If you want to add a representative for any added line walk inspection request,

1. Click (Edit icon) in the **Representative** column for the respective line walk inspection request. The **Edit Form** window opens.
    
    [![image-1651438066675.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438066675.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438066675.png)
2. In the **Representative** box, enter the name of a representative.
3. In the **Inspection Date** box, select the date of inspection.
4. In the **Remarks** box, enter your remarks if any.
5. Click **Save**.

#### **5.46.3 Edit a Line Walk Inspection Request**

If you want to edit any existing line walk inspection request in the **RFI Line Walk Report** page, do the following,

1. Click [![image-1651438150399.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438150399.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438150399.png)(Edit icon) in the **Edit** column for the respective line walk inspection request. See Fig 5.46. The **RFI Line Walk Report** page opens with the details of the selected line walk inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.46.4 Submit and Approve a Line Walk Inspection Request**

Once you have added the line walk inspection request, the **Submission** column in the **RFI Line Walk Report** page is appeared with [![image-1651438223698.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438223698.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438223698.png)(Submit and Reject icons).

1. If you want to submit the line walk inspection request, click[![image-1651438265792.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438265792.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438265792.png)(Submit icon) in the **Submission** column. Otherwise click [![image-1651438284282.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438284282.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438284282.png) (Reject icon) to reject the request.
    
    Once you have submitted the line walk inspection request, the **Request Status** column in the **RFI Line Walk Report** page is appeared with[![image-1651438309416.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438309416.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438309416.png)(Approve and Reject icons).
2. If you want to approve the line walk inspection request, click [![image-1651438364790.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438364790.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438364790.png)(Approve icon) in the **Request Status** Otherwise click [![image-1651438389182.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438389182.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438389182.png) (Reject icon) to reject the request.

The line walk inspection request will be moved for line walk inspection.

#### **5.46.5 Add RFI Data for a Line Walk Inspection Request**

If you want to add RFI data for the added line walk inspection request, do the following,

1. Click [![image-1651438469907.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438469907.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438469907.png)(Edit icon) in the **RFI Data** column of the **RFI Line Walk Report**  See Fig 5.46. The **RFI Inspection Request List** window opens.
    
    [![image-1651438496650.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438496650.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438496650.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the **Inspection Details** option, select 1<sup>st</sup> Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the **Others** box, enter any other inspection related details.
6. In the **Refer to Report No** box, enter the report number for reference.
7. In the **RFI Date** box, choose the RFI date.
8. In the **Inspection Result** option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the **Remarks** box, enter your remarks if any.
10. In the **Inspected by** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the **Witnessed By** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**.

The RFI data is successfully added.

#### **5.46.6 View an RFI Report**

If you want to view an RFI report, click [![image-1651438717825.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438717825.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438717825.png)(print icon) provided in the **RFI Report** column of the **RFI Line Walk Report** page. See Fig 5.46.

#### **5.46.7 Add Results of Line Walk Inspection**

After completing the line walk inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651438803823.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438803823.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438803823.png) (Add icon) in the **Results** column of the respective request. The Result window opens a list of spools added for the particular request.
    
    [![image-1651438824876.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438824876.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438824876.png)
2. In the **Result** column, select the result of each spool from the given result options in the drop-down list.
3. In the **Temperature** column, enter the temperature value of each spool.
4. In the **Start Time** and **End Time** columns, enter the start and end times.
5. Click **Save**.

#### **5.46.8 Attach a File into a Line Walk Inspection Request**

If you want to attach a file with any existing line walk inspection request listed in the **RFI Line Walk Report** page, you can attach the file by using [![image-1651438934559.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438934559.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438934559.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.46.9 Export Line Walk Inspection Request List**

You can export a list of line walk inspection requests added in the **RFI Line Walk Report** page in both the pdf and excel formats by using [![image-1651438983474.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438983474.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438983474.png) (**PDF** button) and [![image-1651438995767.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651438995767.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651438995767.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.46.10 Filter a Line Walk Inspection Request**

If you want to filter any specific line walk inspection request in the **RFI Line Walk Report** page, you can use [![image-1651439037389.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439037389.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439037389.png) (**FILTER** button) located on the **RFI Line Walk Report** page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.



### **5.47 RFI Flushing**

The **RFI Flushing** tab in the **Inspection** menu is used to add a request for pipe flushing inspection.

#### **5.47.1 Add a Flushing Inspection Request**

If you want to add a flushing inspection request, do the following steps,

1. Click **RFI Flushing** in the **Inspection** menu. The **RFI Flushing** page opens.
    
    [![image-1651439162179.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439162179.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439162179.png)
    
     **Figure 5.47: RFI Flushing page**
2. In the **Requested By** box, enter the name of a person who has requested the flushing inspection.
3. In the **Location** box, select the location where the inspection to be performed.
4. In the **Inspection Date &amp; Time**box, select the inspection date and time.
5. In the **Classification** box, enter the classification detail.
6. In the **System** box, select a system from a drop-down list.
7. In the **Sub Contractor** box, select a sub-contractor from a drop-down list.
8. In the **Acceptance Code** box, enter the acceptance code detail.
9. In the **Designation** box, enter the designation detail.
10. In the **Test Temperature** box, enter the test temperature value.
11. In the **Test Medium** box, select the test medium from the drop-down list.
12. In the **Drawing No** box, select the drawing number from a drop-down list.
13. In the **Work Scope** box, enter the work scope detail.
14. In the **Cost Centre** box, enter the cost centre detail.
15. In the **Holding Time** box, enter the holding time range.
16. In the **Pressure Gauge No** box, enter the pressure gauge number.
17. In the **Procedure No** box, enter the procedure number.
18. In the **Design Pressure** box, enter the design pressure range.
19. In the **Test Pressure** box, enter the test pressure range.
20. In the **Instrument** box, enter the instrument name.
21. In the **P&amp;ID No** box, enter the P&amp;ID number.
22. In the **Remarks** box, enter your remarks if any.
23. In the **Description** box, enter the description for the flushing inspection.
    
    Before saving the added flushing inspection request, you must add spools.
    
    [![image-1651439356347.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439356347.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439356347.png) **Note**: You can add multiple spools for one request.
    
    The **RFI Flushing** page shows a list of added spools. If you want to view the spools for the specific ISO drawing, select the respective ISO drawing from a drop-down list. [![image-1651439397100.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439397100.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439397100.png)
24. Click [![image-1651439408070.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439408070.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439408070.png)(Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
25. Click **Save Request**.

The flushing inspection request will be added and listed in the **RFI Flushing Report** page.


### **5.48 View RFI Flushing**

The **View RFI Flushing** tab helps you to view and edit the flushing inspection request, which is added by using the **RFI Flushing** tab. This tab also allows you to add a new flushing inspection request.

1. Click **View RFI Flushing** in the **Inspection** menu. The **RFI Flushing Report** page opens with a list of added flushing inspection requests.
    
    [![image-1651439509180.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439509180.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439509180.png)
    
     **Figure 5.48: RFI Flushing Report page**

#### **5.48.1 Add a Flushing Inspection Request**

If you want to add a flushing inspection request, do the following steps,

1. Click [![image-1651439613769.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439613769.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439613769.png) (**ADD** button) in the **RFI Flushing Report** page.
    
    The system redirects you to a new page to add a new flushing inspection request. To know how to add a flushing inspection request, See the topic, “[**<u>Add a Flushing Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.47.1%C2%A0add-a-flushin)”.

Once you have added the flushing inspection request, you must submit the added request to perform the flushing inspection.

#### **5.48.2 Add Representative for a Flushing Inspection Request**

If you want to add a representative for any added flushing inspection request,

1. Click [![image-1651439689832.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439689832.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439689832.png)(Edit icon) in the **Representative** column for the respective flushing inspection request. The **Edit Form** window opens.
    
    [![image-1651439718130.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439718130.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439718130.png)
2. In the **Representative** box, enter the name of a representative.
3. In the **Inspection Date** box, select the date of inspection.
4. In the **Remarks** box, enter your remarks if any.
5. Click **Save**.

#### **5.48.3 Edit a Flushing Inspection Request**

If you want to edit any existing flushing inspection request in the **RFI Flushing Report** page, do the following,

1. Click[![image-1651439822540.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439822540.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439822540.png)(Edit icon) in the **Edit** column for the respective flushing inspection See Fig 5.48. The **RFI Flushing Report** page opens with the details of the selected flushing inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.48.4 Submit and Approve a Flushing Inspection Request**

Once you have added the flushing inspection request, the **Submission** column in the **RFI Flushing Report** page is appeared with [![image-1651439907831.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439907831.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439907831.png)(Submit and Reject icons).

1. If you want to submit the flushing inspection request, click [![image-1651439944247.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439944247.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439944247.png)(Submit icon) in the **Submission** Otherwise click [![image-1651439960920.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439960920.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439960920.png)(Reject icon) to reject the request. Once you have submitted the flushing inspection request, the **Request Status** column in the **RFI Flushing Report** page is appeared with [![image-1651439989387.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651439989387.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651439989387.png)(Approve and Reject icons).
2. If you want to approve the flushing inspection request, click[![image-1651440012735.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440012735.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440012735.png) (Approve icon) in the **Request Status** Otherwise click [![image-1651440030261.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440030261.png) ](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440030261.png)(Reject icon) to reject the request.

The flushing inspection request will be moved for flushing inspection.

#### **5.48.5 Add RFI Data for a Flushing Inspection Request**

If you want to add RFI data for the added flushing inspection request, do the following,

1. Click [![image-1651440122290.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440122290.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440122290.png)(Edit icon) in the **RFI Data** column of the **RFI Flushing Report**  See Fig 5.48. The **RFI Inspection Request List** window opens.
    
    [![image-1651440158830.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440158830.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440158830.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the **Inspection Details** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the **Others** box, enter any other inspection related details.
6. In the **Refer to Report No** box, enter the report number for reference.
7. In the **RFI Date** box, choose the RFI date.
8. In the **Inspection Result** option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the **Remarks** box, enter your remarks if any.
10. In the **Inspected by** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the **Witnessed By** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**.

The RFI data is successfully added.

#### **5.48.6 View an RFI Report**

If you want to view an RFI report, click [![image-1651440450815.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440450815.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440450815.png)(print icon) provided in the **RFI Report** column of the **RFI Flushing Report** page. See Fig 5.48.

#### **5.48.7 Add Results of Flushing Inspection**

After completing the flushing inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651440497663.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440497663.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440497663.png) (Add icon) in the **Results** column of the respective request.
    
    The Result window opens a list of spools added for the particular request.
    
    [![image-1651440518343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440518343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440518343.png)
2. In the **Result** column, select the result of each spool from the given result options in the drop-down list.
3. In the **Temperature** column, enter the temperature value of each spool.
4. In the **Start Time** and **End Time** columns, enter the start and end times.
5. Click **Save**.

#### **5.48.8 Attach a File into a Flushing Inspection Request**

If you want to attach a file with any existing flushing inspection request listed in the **RFI Flushing Report** page, you can attach the file by using [![image-1651440609417.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440609417.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440609417.png)(Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.48.9 Export Flushing Inspection Request List**

You can export a list of flushing inspection requests added in the **RFI Flushing Report** page in both the pdf and excel formats by using [![image-1651440650319.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440650319.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440650319.png) (**PDF** button) and [![image-1651440660942.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440660942.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440660942.png) (**Excel** button). To know how to export, see the topic, “[**<u>Export P&amp;ID list</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)”.

#### **5.48.10 Filter a Flushing Inspection Request**

If you want to filter any specific flushing inspection request in the **RFI Flushing Report** page, you can use [![image-1651440703497.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440703497.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440703497.png) (**FILTER** button) located on the **RFI Flushing Report** page. To know how to filter, see the topic, “[**<u>Filter P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.


### **5.49 RFI Chemical Cleaning**

The **RFI Chemical Cleaning** tab in the **Inspection** menu is used to add a request for the pipe chemical cleaning inspection.

#### **5.49.1 Add a Chemical Cleaning Inspection Request**

If you want to add a chemical cleaning inspection request, do the following steps,

1. Click **RFI Chemical Cleaning** in the **Inspection** menu. The **RFI Chemical Cleaning** page opens.
    
    [![image-1651440795617.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651440795617.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651440795617.png)
    
     **Figure 5.49: RFI Chemical Cleaning page**
2. In the ****Requested By**** box, enter the name of a person who has requested the chemical cleaning inspection.
3. In the ****Location**** box, select the location where the inspection to be performed.
4. In the **Inspection Date &amp; Time** box, select the inspection date and time.
5. In the **Classification** box, enter the classification detail.
6. In the **System** box, select a system from a drop-down list.
7. In the **Sub Contractor** box, select a sub-contractor from a drop-down list.
8. In the **Acceptance Code** box, enter the acceptance code detail.
9. In the **Designation** box, enter the designation detail.
10. In the **Test Temperature** box, enter the test temperature value.
11. In the **Test Medium** box, select the test medium from the drop-down list.
12. In the **Drawing No** box, select the drawing number from a drop-down list.
13. In the **Work Scope** box, enter the work scope detail.
14. In the **Cost Centre** box, enter the cost centre detail.
15. In the **Holding Time** box, enter the holding time range.
16. In the **Pressure Gauge No** box, enter the pressure gauge number.
17. In the **Procedure No** box, enter the procedure number.
18. In the **Design Pressure** box, enter the design pressure range.
19. In the **Test Pressure** box, enter the test pressure range.
20. In the **Instrument** box, enter the instrument name.
21. In the **P&amp;ID No** box, enter the P&amp;ID number.
22. In the **Remarks** box, enter your remarks if any.
23. In the **Description** box, enter the description for the chemical cleaning inspection. Before saving the added chemical cleaning inspection request, you must add spools.
    
    [![image-1651588915460.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651588915460.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651588915460.png)**Note**: You can add multiple spools for one request.
    
    The **RFI Chemical Cleaning** page shows a list of added spools. If you want to view the spools for the specific ISO drawing, select the respective ISO drawing from a drop-down list.
    
    [![image-1651588945673.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651588945673.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651588945673.png)
24. Click [![image-1651588986707.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651588986707.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651588986707.png)(Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
25. Click **Save Request**.

The chemical cleaning inspection request will be added and listed in the **RFI Chemical Cleaning Report** page.

### **5.50 View RFI Chemical Cleaning**

The **View RFI Chemical Cleaning** tab helps you to view and edit the chemical cleaning inspection request, which is added by using the **RFI Chemical Cleaning** tab. This tab also allows you to add a new chemical cleaning inspection request.

1. Click **View RFI Chemical Cleaning** in the **Inspection** menu. The **RFI Chemical Cleaning Report** page opens with a list of added chemical cleaning inspection requests.
    
    [![image-1651589148449.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589148449.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589148449.png)
    
     **Figure 5.50: RFI Chemical Cleaning Report page**

#### **5.50.1 Add a Chemical Cleaning Inspection Request**

If you want to add a chemical cleaning inspection request, do the following steps,

1. Click [![image-1651589221375.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589221375.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589221375.png) (**ADD** button) in the **RFI Chemical Cleaning Report** page. The system redirects you to a new page to add a new chemical cleaning inspection request. To know how to add a chemical cleaning inspection request, See the topic, “[**<u>Add a </u><u>Chemical Cleaning </u><u>Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.49.1%C2%A0add-a-chemica)”.
    
    Once you have added the chemical cleaning inspection request, you must submit the added request to perform the chemical cleaning inspection.

#### **5.50.2 Add Representative for a Chemical Cleaning Inspection Request**

If you want to add a representative for any added chemical cleaning inspection request,

1. Click [![image-1651589308476.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589308476.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589308476.png)(Edit icon) in the **Representative** column for the respective chemical cleaning inspection request. The **Edit Form** window opens.
    
    [![image-1651589327829.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589327829.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589327829.png)
2. In the **Representative** box, enter the name of a representative.
3. In the **Inspection Date** box, select the date of inspection.
4. In the **Remarks** box, enter your remarks if any.
5. Click **Save**.

#### **5.50.3 Edit a Chemical Cleaning Inspection Request**

If you want to edit any existing chemical cleaning inspection request in the **RFI Chemical Cleaning Report** page, do the following,

1. Click [![image-1651589481941.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589481941.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589481941.png)(Edit icon) in the **Edit** column for the respective chemical cleaning inspection See Fig 5.50. The **RFI Chemical Cleaning Report** page opens with the details of the selected chemical cleaning inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click **Save**.

#### **5.50.4 Submit and Approve a Chemical Cleaning Inspection Request**

Once you have added the chemical cleaning inspection request, the **Submission** column in the **RFI Chemical Cleaning Report** page is appeared with [![image-1651589558239.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589558239.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589558239.png) (Submit and Reject icons).

1. If you want to submit the chemical cleaning inspection request, click [![image-1651589590074.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589590074.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589590074.png) (Submit icon) in the **Submission** Otherwise click [![image-1651589606094.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589606094.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589606094.png) (Reject icon) to reject the request. Once you have submitted the chemical cleaning inspection request, the **Request Status** column in the **RFI Chemical Cleaning Report** page is appeared with [![image-1651589625179.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589625179.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589625179.png) (Approve and Reject icons).
2. If you want to approve the chemical cleaning inspection request, click [![image-1651589653940.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589653940.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589653940.png)(Approve icon) in the ****Request Status**** Otherwise click [![image-1651589672065.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589672065.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589672065.png) (Reject icon) to reject the request. The chemical cleaning inspection request will be moved for chemical cleaning inspection.

#### **5.50.5 Add RFI Data for a Chemical Cleaning Inspection Request**

If you want to add RFI data for the added chemical cleaning inspection request, do the following,

1. Click [![image-1651589790180.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589790180.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589790180.png) (Edit icon) in the **RFI Data** column of the **RFI Chemical Cleaning Report**  See Fig 5.50. The **RFI Inspection Request List** window opens.
    
    [![image-1651589810916.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651589810916.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651589810916.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the ****Inspection Details**** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the ****Others**** box, enter any other inspection related details.
6. In the ****Refer to Report No**** box, enter the report number for reference.
7. In the ****RFI Date**** box, choose the RFI date.
8. In the **Inspection Result** option, if the inspection result is accepted, select **Accepted** otherwise select **Rejected**.
9. In the ****Remarks**** box, enter your remarks if any.
10. In the ****Inspected by**** box, enter the name of a person who has done inspection.
11. In the ****Inspected Date**** box, choose the date of inspection.
12. In the ****Witnessed By**** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**.

The RFI data is successfully added.


#### **5.50.6 View an RFI Report**

If you want to view an RFI report, click[![image-1651590041754.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590041754.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590041754.png)(print icon) provided in the **RFI Report** column of the **RFI Chemical Cleaning Report** page. See Fig 5.50.

#### **5.50.7 Add Results of Chemical Cleaning Inspection**

After completing the chemical cleaning inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651590101313.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590101313.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590101313.png) (Add icon) in the **Results** column of the respective request. The Result window opens a list of spools added for the particular request.
    
    [![image-1651590122102.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590122102.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590122102.png)
2. In the **Result** column, select the result of each spool from the given result options in the drop-down list.
3. In the **Temperature** column, enter the temperature value of each spool.
4. In the **Start Time** and **End Time** columns, enter the start and end times.
5. Click **Save**.

#### **5.50.8 Attach a File into a Chemical Cleaning Inspection Request**

If you want to attach a file with any existing chemical cleaning inspection request listed in the **RFI Chemical Cleaning Report** page, you can attach the file by using [![image-1651590279773.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590279773.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590279773.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.50.9 Export Chemical Cleaning Inspection Request List**

You can export a list of chemical cleaning inspection requests added in the **RFI Chemical Cleaning Report** page in both the pdf and excel formats by using [![image-1651590339890.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590339890.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590339890.png) (**PDF** button) and [![image-1651590351607.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590351607.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590351607.png) (**Excel** button). To know how to export, see the topic, “**[<u>Export P&amp;ID list</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)**”.

#### **5.50.10 Filter a Chemical Cleaning Inspection Request**

If you want to filter any specific chemical cleaning inspection request in the **RFI Chemical Cleaning Report** page, you can use [![image-1651590406512.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590406512.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590406512.png) (**FILTER** button) located on the **RFI Chemical Cleaning Report** page. To know how to filter, see the topic, “[<u>**Filter P&amp;ID**</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)”.

### **5.51 RFI Reinstatement**

The **RFI Reinstatement** tab in the **Inspection** menu is used to add a request for pipe reinstatement inspection.

#### **5.51.1 Add a Reinstatement Inspection Request**

If you want to add a reinstatement inspection request, do the following steps,

1. Click **RFI Reinstatement** in the **Inspection** menu. The **RFI Reinstatement** page opens.
    
    [![image-1651590505981.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590505981.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590505981.png)
    
     **Figure 5.51: RFI Reinstatement page**
2. In the ****Requested By**** box, enter the name of a person who has requested the reinstatement inspection.
3. In the ****Location**** box, select the location where the inspection to be performed.
4. In the **Inspection Date &amp; Time** box, select the inspection date and time.
5. In the **Classification** box, enter the classification detail.
6. In the **System** box, select a system from a drop-down list.
7. In the **Sub Contractor** box, select a sub-contractor from a drop-down list.
8. In the **Acceptance Code** box, enter the acceptance code detail.
9. In the **Designation** box, enter the designation detail.
10. In the **Test Temperature** box, enter the test temperature value.
11. In the **Test Medium** box, select the test medium from the drop-down list.
12. In the **Drawing No** box, select the drawing number from a drop-down list.
13. In the **Work Scope** box, enter the work scope detail.
14. In the **Cost Centre** box, enter the cost centre detail.
15. In the **Holding Time** box, enter the holding time range.
16. In the **Pressure Gauge No** box, enter the pressure gauge number.
17. In the **Procedure No** box, enter the procedure number.
18. In the **Design Pressure** box, enter the design pressure range.
19. In the **Test Pressure** box, enter the test pressure range.
20. In the **Instrument** box, enter the instrument name.
21. In the **P&amp;ID No** box, enter the P&amp;ID number.
22. In the **Remarks** box, enter your remarks if any.
23. In the **Description** box, enter the description for the reinstatement inspection.
    
    Before saving the added reinstatement inspection request, you must add spools.
    
    [![image-1651590679343.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590679343.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590679343.png) **Note**: You can add multiple spools for one request.
    
    The **RFI Reinstatement** page shows a list of added spools. If you want to view the spools for the specific ISO drawing, select the respective ISO drawing from a drop-down list.
    
    [![image-1651590705505.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590705505.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590705505.png)
24. Click [![image-1651590723201.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590723201.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590723201.png) (Add icon) of the respective spool which you want to add. The added spools will be moved to the right side of the page.
25. Click **Save Request**.

The reinstatement inspection request will be added and listed in the **RFI Reinstatement Report** page.

### **5.52 View RFI Reinstatement**

The **View RFI Reinstatement** tab helps you to view and edit the reinstatement inspection request, which is added by using the **RFI Reinstatement** tab. This tab also allows you to add a new reinstatement inspection request.

1. Click **View RFI Reinstatement** in the **Inspection** menu.
    
    The **RFI Reinstatement Report** page opens with a list of added reinstatement inspection requests.
    
    [![image-1651590896257.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651590896257.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651590896257.png)
    
     **Figure 5.52: RFI Reinstatement Report page**

#### **5.52.1 Add a Reinstatement Inspection Request**

If you want to add a reinstatement inspection request, do the following steps,

1. Click (**ADD** button) in the **RFI Reinstatement Report** page. The system redirects you to a new page to add a new reinstatement inspection request. To know how to add a reinstatement inspection request, See the topic, “[**<u>Add a Reinstatement Inspection Request</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/inspection/#bkmrk-5.51.1%C2%A0add-a-reinsta)”.

Once you have added the reinstatement inspection request, you must submit the added request to perform the reinstatement inspection.

#### **5.52.2 Add Representative for a Reinstatement Inspection Request**

If you want to add a representative for any added reinstatement inspection request,

1. Click [![image-1651591073123.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591073123.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591073123.png)(Edit icon) in the **Representative** column for the respective reinstatement inspection request. The **Edit Form** window opens.
    
    [![image-1651591098312.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591098312.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591098312.png)
2. In the **Representative** box, enter the name of a representative.
3. In the **Inspection Date** box, select the date of inspection.
4. In the **Remarks** box, enter your remarks if any.
5. Click **Save**.

#### **5.52.3 Edit a Reinstatement Inspection Request**

If you want to edit any existing reinstatement inspection request in the **RFI Reinstatement Report** page, do the following,

1. Click [![image-1651591195935.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591195935.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591195935.png) (Edit icon) in the **Edit** column for the respective reinstatement inspection See Fig 5.52. The **RFI Reinstatement Report** page opens with the details of the selected reinstatement inspection request.
2. Click any box where you want to edit the details, and then edit the details in the respective box.
3. Click ****Save****.

#### **5.52.4 Submit and Approve a Reinstatement Inspection Request**

Once you have added the reinstatement inspection request, the **Submission** column in the **RFI Reinstatement Report** page is appeared with [![image-1651591272141.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591272141.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591272141.png) (Submit and Reject icons).

1. If you want to submit the reinstatement inspection request, click [![image-1651591301087.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591301087.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591301087.png) (Submit icon) in the **Submission** Otherwise click [![image-1651591317099.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591317099.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591317099.png) (Reject icon) to reject the request. Once you have submitted the reinstatement inspection request, the **Request Status** column in the **RFI Reinstatement Report** page is appeared with[![image-1651591351175.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591351175.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591351175.png) (Approve and Reject icons).
2. If you want to approve the reinstatement inspection request, click [![image-1651591377901.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591377901.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591377901.png) (Approve icon) in the ****Request Status**** Otherwise click [![image-1651591393637.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591393637.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591393637.png) (Reject icon) to reject the request. The reinstatement inspection request will be moved for reinstatement inspection.

#### **5.52.5 Add RFI Data for a Reinstatement Inspection Request**

If you want to add RFI data for the added reinstatement inspection request, do the following,

1. Click [![image-1651591477577.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591477577.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591477577.png)(Edit icon) in the **RFI Data** column of the **RFI Reinstatement Report**  See Fig 5.52. The **RFI Inspection Request List** window opens.
    
    [![image-1651591497373.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591497373.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591497373.png)
2. In the **Inspection From** box, enter the detail from where the inspection should start.
3. In the **Inspection To** box, enter the detail to where the inspection should end.
4. In the ****Inspection Details**** option, select 1<sup>st</sup>Inspection, 2<sup>nd</sup> Inspection or 3<sup>rd</sup> Inspection according to the inspection details.
5. In the **Others** box, enter any other inspection related details.
6. In the **Refer to Report No** box, enter the report number for reference.
7. In the **RFI Date** box, choose the RFI date.
8. In the ****Inspection Result**** option, if the inspection result is accepted, select ****Accepted**** otherwise select ****Rejected****.
9. In the **Remarks** box, enter your remarks if any.
10. In the **Inspected by** box, enter the name of a person who has done inspection.
11. In the **Inspected Date** box, choose the date of inspection.
12. In the **Witnessed By** box, enter the name of the witnessed person.
13. In the **Witnessed Date** box, choose the date of witnessed.
14. In the **PCML Rep Name** box, enter the representative name of PCML.
15. In the **PCML Rep Date** box, choose the PCML rep date.
16. In the **MEB Rep Name** box, enter the representative name of MEB.
17. In the **MEB Rep Date box**, choose MEB rep date.
18. Click **Save**.

The RFI data is successfully added.


#### **5.52.6 View an RFI Report**

If you want to view an RFI report, click [![image-1651591702432.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591702432.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591702432.png) (print icon) provided in the **RFI Report** column of the **RFI Reinstatement Report** page. See Fig 5.52.

#### **5.52.7 Add Results of Reinstatement Inspection**

After completing the reinstatement inspection for the added request, you can add the inspection result details. To add results, do the following steps,

1. Click [![image-1651591768252.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591768252.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591768252.png) (Add icon) in the **Results** column of the respective request. The Result window opens a list of spools added for the particular request.
    
    [![image-1651591789927.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591789927.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591789927.png)
2. In the ****Result**** column, select the result of each spool from the given result options in the drop-down list.
3. In the ****Temperature**** column, enter the temperature value of each spool.
4. In the **Start Time** and **End Time** columns, enter the start and end times.
5. Click **Save**.

#### **5.52.8 Attach a File into a Reinstatement Inspection Request**

If you want to attach a file with any existing reinstatement inspection request listed in the **RFI Reinstatement Report** page, you can attach the file by using [![image-1651591888170.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591888170.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591888170.png) (Attach icon) in the **Attachment** column. To know how to attach, follow the procedures given in the topic “[**<u>Attach a file into </u><u>P&amp;ID</u>**](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.7%C2%A0attach-a-file-)”.

#### **5.52.9 Export Reinstatement Inspection Request List**

You can export a list of reinstatement inspection requests added in the **RFI Reinstatement Report** page in both the pdf and excel formats by using [![image-1651591936770.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591936770.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591936770.png) (**PDF** button) and [![image-1651591950522.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591950522.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591950522.png) (**Excel** button). To know how to export, see the topic, “**[<u>Export P&amp;ID list</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.4%C2%A0export-p%26id-li)**”.

#### **5.52.10 Filter a Reinstatement Inspection Request**

If you want to filter any specific reinstatement inspection request in the **RFI Reinstatement Report** page, you can use [![image-1651591997799.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651591997799.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651591997799.png) (**FILTER** button) located on the **RFI Reinstatement Report** page. To know how to filter, see the topic, “**[<u>Filter P&amp;ID</u>](http://wiki.cuteinfocomm.com/books/cuteqm/page/project-data/#bkmrk-3.1.5%C2%A0filter-a-p%26id)**”.


### **5.53 Inspection Requisition Summary Report**

The **Inspection Requisition Summary** tab in the **Inspection** menu used to view the inspection requisition summary report for a particular period.

1. Click **Inspection Requisition Summary** in the **Inspection** menu. The **Requisition Inspection Summary** page opens.
    
    [![image-1651592061350.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592061350.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592061350.png)
    
     **Figure 5.53: Requisition Inspection Summary page**
2. In the **Start Date** and **End Date** boxes, select the start and end dates.
3. Click **Get Report**.
    
    The inspection requisition summary report for the selected period will be opened.
    
    [![image-1651592115499.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592115499.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592115499.png)

#### **5.53.1 Print an Inspection Requisition Summary Report**

If you want to print an inspection requisition summary report, use[![image-1651592168087.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592168087.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592168087.png) and [![image-1651592178752.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592178752.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592178752.png) (print icons) provided in the **Requisition Inspection Summary** page.

1. If you want to print the current page of the inspection requisition summary report, click [![image-1651592202297.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592202297.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592202297.png) (print icon including the page number).
2. If you want to print all the pages of the inspection requisition summary report, click [![image-1651592256145.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592256145.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592256145.png)(print icon).

#### **5.53.2 Export an Inspection Requisition Summary Report**

You can export the inspection requisition summary report in various formats by using the option [![image-1651592398427.png](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/scaled-1680-/image-1651592398427.png)](http://wiki.cuteinfocomm.com/uploads/images/gallery/2022-05/image-1651592398427.png) provided in the upper right corner of the **Requisition Inspection Summary** page.